A cantilever sheet pile is driven into a granular soil where the water table is 2 m (L1) below the top of the sand.The properties of the sand are ?' = 40 degrees, ? = 17.5 kN/m3, and ?sat = 17.5 kN/m3. It is proposed to excavate to a depth of 6 m (L) below the ground level.
a.)Determine the actual depth to which the sheet pile must be driven (L+D) , using the net lateral pressure diagram. Note: Dactual = 1.3(Dtheory)
b.) Determine maximum moment and location. Assuming an allowable stress of 170 MN/m2, select a sheet pile from the attached table.
A cantilever sheet pile is driven into a granular soil where the water table is 2...
Figure shows a cantilever sheet-pile wall penetrating a granular soil. Assume, γ = 15.5 kN/m3, γsat = 18 kN/m3, φ΄ = 18o, and γw = 10 kN/m3.(a) Draw the pressure diagram of the cantilever sheet-pile wall (may not necessarily be on scale).(b) Determine the theoretical depth of embedment.(c) What should be the minimum section modulus of the sheet piles? Use σall = 180 MN/m2.
A 15m long pile is driven into sand as shown in the figure. What would be the skin resistance (Qs) of the pile? Hint: Use the Brom's method given (L' 15D). Diameter 0.3 m 2-ΣΡΔL ) 350 y 20 kN/m3 f= σ,' tan δ K 1.4x (1-sinø) S 0.8 '350 Ys22 kN/m3 Unit frictional resistance, Ko MAX AL T Depth (b) (a) Unit frictional resistance for piles in sand Figure 11.18 Selected Answer: 3 b. 242.4 kN a. 228.4 kN...
Question II (%35): Please, determine the length, L, of a driven timber pile required to support the load as shown in Figure below. The diameter of the pile is 450 mm. A factor of safety of 2 is required. 275 kN 15 m Medium clay $ = 30 kPa, y = 17 kN/m3 0'8 = 30°, OCR = 1.6 L Stiff clay 5,= 60 kPa, Ysa = 18.8 kN/m3 0 = 240, OCR = 4
Base on the soil profile above (Fig.3), it was designed to use driven pile with dimension 500mm x 500mm to carry out the following design load (use factor of safety = 2): i. 200 kN ii. 1000 kN iii. 3000 kN Determine the required depth of driven pile (assume no defective of pile during installation process) Sand Layer 1 r = 16.5 kN/m Ysat = 18.5 kN/m c' = 0 kPa O' = 30° 20 m Sand Layer 2 y...
C5 A concrete pile 450 mm in diameter and 15 m long is driven into a clay. The undrained strength of the soil varies linearly with depth such that cu-0.22 Ơ'z Determine the allowable pile load capacity. The factor of safety required is 2 and Vsat- 17 kN/m3. Groundwater is at the surface.
2- Assume a 460 mm pipe filled with concrete shown below needs a length of 30 meters to carry the allowable load of 670kN. If the same pile is driven into the same soil profile but different cohesion (soft clay c-12kPa, medium stiff clay c 85kPa), to carry the same 670 kN axial load, how much do you recommend the length of the pile to be increased or decreased? Show calculations and use the Meyerhof and the method. (30 pts)...
The soil conditions adjacent to a sheet pile wall are given in the Figure 2 below, a surcharge pressure of 40 kN/m2 being carried on the surface behind the wall. Draw the active and passive lateral earth pressure diagrams; and determine the active and passive forces acting on 1m length of the wall. The properties of the clay layer: Cohesion: c 10 kN/m2 Shear resistance angle: #25° Unit weight: y-19.5 kN/m3 9-40 kN/m Clay Clay Figure 3 The following may...
6. (a) In piling technology, explain the difference between a "displacement pile" and (2 marks) a "non-displacement pile". (b) Using graph paper, sketch 3 curves illustrating typical trends of variation of pile head resistance, shaft resistance and base resistance with increasing settlement, as expected from load testing a CFA pile in clay. Explain the differences between the three curves (6 marks) (c) A bored cast in-situ pile of 0.6 m diameter by 10 m long is installed through a 6...
help with problems 1 & 2 please and explain Problem 1 A deposit of Swedish clay is 15 m thick drained at both top and bottom. The coefficient of consolidation for the clay layer was estimated to be 1 x 10 cm/sec from laboratory test. The ultimate consolidation settlement (Sc) was calculated under the applied load in the field and was found 80 cm. Find the following: a) How long would it take for settlement of 40 cm and 70...
Using boring log data to determine soil properties ( ϕ’,c,γ) for each soil layers (interpolation may be needed) BORING LOG: BH-1 SHEET 1 o 1 PROJECT CONTRACTOR DRILLER: INSPECTOR: PROJECT CUIENT CUENT PROJECT COORDINATESN RIG TYPE DRILLING METHOD HAMMER TYPE SURFACE ELEV: 781.5 TOTAL DEPTH: 23 REF ALIGNMENT STATION OFFSET LOCATION: Tucson COMMENTS TIME TIME START DATE: FINISH DATE: cu L.D. O.D. Length Hammer WT Hammer Fall 622.75 N Drill Rod Size I.D. 1O.D.) BLOWS 762mm SOIL SAMPLE VISUAL MATERIAL...