Question

Gary’s Gears is a production facility that produces metal gears. The first step is stamping, which...

Gary’s Gears is a production facility that produces metal gears. The first step is stamping, which happens at a press. There are two identical presses that operate simultaneously (gears can be stamped on either press). A press stamps one part at a time. It takes 1 minute to stamp a part, including loading and unloading. Before beginning a new batch of parts, there is a 20-minute setup involving die change. The batch size is 100 parts. In other words, after stamping 100 parts, the press must be set up again. The stamped parts are stored in a buffer area, called as the work-in-process (WIP) inventory rack. From here, the parts are taken to the furnace, where they are annealed (heat treated). Parts from different batches can be annealed together. To perform annealing, a boat (a type of fixture for holding stamped parts) loaded with parts is inserted into the furnace. While those parts are being annealed, newly stamped parts are loaded onto a spare furnace boat. Each boat can hold 70 parts. Once the boat is full, additional stamped parts are placed in the WIP inventory rack. After annealing is completed, the boat in the furnace is swapped with the boat outside the furnace and the next annealing cycle begins. Each annealing cycle takes a total of 30 minutes. The time to load and unload parts from a boat is very short, and can be neglected. The above system operates 8 hours a day, Monday through Friday. On Mondays, however, the furnace and both boats are cleaned. Thus, all parts stamped by the presses go straight to the WIP inventory rack on Mondays.

Questions

1. What is the throughput capacity of this system, in parts per week? In other words, how many parts can be processed per week?

2. What is the required buffer capacity of the WIP inventory rack?

3. What is the average inventory level in the WIP inventory rack (averaged over the factory operating hours)?

4. What is the system throughput capacity if the WIP inventory rack can hold only 500 parts?

5. What is the average number of factory operating hours that a part spends in the WIP rack in question 2? (Parts that do not wait in the WIP rack should be included in this average, and have zero waiting time by definition.)

6. What is the average number of factory operating hours that a part spends in the WIP rack in question 4? (Parts that do not wait in the WIP rack should be included in this average, and have zero waiting time by definition.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Here the factory produces metal gears.

The first step is stamping gears and it happens in a press. they have two identical press which works simultaneously.

the press stamps one part at a time = time taken is one min for a stamp a part which includes both loading and unloading.

A) no of part =1

time is taken by one part = 1 min

each batch contains 100 parts so 100 parts need 100 min

calculation :

1 hour = 60 min

so 100 parts take average of 1 hour 40 min in (WIP) Work - in- process

B) 2nd process is anealing (heat treated )

in this 70 part is loaded to perform annealing remaining is placed in WIP rack by doing so total 30 minutes is spend.

8 hours is spent in a day for the entire process.

each single part average of 1 min in WIP.

Add a comment
Know the answer?
Add Answer to:
Gary’s Gears is a production facility that produces metal gears. The first step is stamping, which...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT