Thank you in advance! o serve 60 custom- 15. Johnson Cogs wants to set up a...
Question 1- Assembly Line Balancing A ball-bearing assembly firm wants to set up an assembly line that must have an output of 60 units per hour. The work elements, task times and their precedence relationships are shown in Table 1: Table 1 Work Element Time (sec.) Immediate Predecessor(s) A 40 NONE B 30 A C 50 A D 40 B E 6 B F 25 C G 15 C H 20 D, E I 18 F, G J 30 H,...