Question

Which of the following the planned-order receipt (assuming order quantity to be multiples of 1200) using an MRP program if th
0 0
Add a comment Improve this question Transcribed image text
Answer #1

9)

Gross requirement = 2070

On hand = 400

Planned order receipt = Gross requirement - On hand = 2070-400 = 1670

However, it needs to be in multiple of 1200, so order quantity will be 1200*2 = 2400

Ans 2400

10)

Projected available balance = Planned order receipt + On hand - Gross requirement = 2400 + 400 - 2070 = 730

Ans 730

Add a comment
Know the answer?
Add Answer to:
Which of the following the planned-order receipt (assuming order quantity to be multiples of 1200) using...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • MRP /ERP IN M 1) Each E subassembly is made up of two (2) G parts, four (5) H part, and One J par...

    MRP /ERP IN M 1) Each E subassembly is made up of two (2) G parts, four (5) H part, and One J part Draw the product structure tree diagram. the information provided below, complete the following MRP Record Transaction Processing for Part E and Part G only if the following information is provided (Do not order more quantity of any resources that is needed to maintain the production) sing the product structure free diagram and Subassembly Part Part Part...

  • manufacturing plng/ control 1. Suppose that your company sells a product for which the annual demand...

    manufacturing plng/ control 1. Suppose that your company sells a product for which the annual demand is 10,000 units. Holding costs are $1.00 per unit per year, and setup costs are $200 per order (a) What is the economic order quantity for your product? (b) What will be the annual total cost holding and ordering? 2. A company has currently 100 workers. A worker works 40 hours a week, and can at most work 20 hours of overtime per week....

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT