9)
Gross requirement = 2070
On hand = 400
Planned order receipt = Gross requirement - On hand = 2070-400 = 1670
However, it needs to be in multiple of 1200, so order quantity will be 1200*2 = 2400
Ans 2400
10)
Projected available balance = Planned order receipt + On hand - Gross requirement = 2400 + 400 - 2070 = 730
Ans 730
Which of the following the planned-order receipt (assuming order quantity to be multiples of 1200) using...
MRP /ERP IN M 1) Each E subassembly is made up of two (2) G parts, four (5) H part, and One J part Draw the product structure tree diagram. the information provided below, complete the following MRP Record Transaction Processing for Part E and Part G only if the following information is provided (Do not order more quantity of any resources that is needed to maintain the production) sing the product structure free diagram and Subassembly Part Part Part...
manufacturing plng/ control 1. Suppose that your company sells a product for which the annual demand is 10,000 units. Holding costs are $1.00 per unit per year, and setup costs are $200 per order (a) What is the economic order quantity for your product? (b) What will be the annual total cost holding and ordering? 2. A company has currently 100 workers. A worker works 40 hours a week, and can at most work 20 hours of overtime per week....