Question

cnaarens furnishings. The company uses a job-order costing system, Kidcos work-in-process inventory at the end or November consisted of the following jobs Richmond started kodCo, inc in Albuquerque, New Mexico to produce affordable 20.000 15.000 250,000 The companys November 30 finished-goods inventory, which is valued using the FIFO (first-in ust outy method consisted of five items Accumulated Cost S 480,000 Duantity and Unit Cost 7 500 unts 364 aach 13000 unes $23 each 1 1,200 unts a s102 each 21,000 unts a 555 each 19.400 units & 335 each 99,000 1,142.400 1.155,000 kidco applies manufacturing overnead on the basis or direct-labor hours. The companys overhead budget for the year totals $4.500.000 The company plans to use 600.000 direct-iabor hours during this period, which is the firms estimated practical capacity Through the first 11 rionths of the year, a totat of 555 000 direct-labor hours were worked, and total overheacd amountea to $4.273,500 November. Ine balance in kidco s Raw-Materiat Inventory account, which includes w matenai and purchased parts, was s668.000. Aoditions to inventory and requisitions rom mventery during Decermser inctuded the toliowing 104,000 10,800 82.000 81/000 124.000 62.000 65,000 xt 098 ,000 carnages? Dunng December KidCos factory payrott consisted of the fotowing: $122,400 3,200 3.500 h 14,000 3.000 138.000 29,400 S7 600 $621,100 ndrect labor The following list shows the jobs that were completed and the unit sales for December Job No. CBS102 PLP088 STRO77 Quantity Completed 20,000 15,000 10000 5000 Items Quantity Shipped 17,500 21,000 14,000 18,000 Crbs Cribs. Sroters Strolers Dressers Carriages6,000 Required 1. Explain when t is appropriate for a company to use a job-order costing system 2. calculate the dollar balance in Kidcos Work-in-Process Inventory account as of December 31 3. Calculate the dollar amount related to the playpens in KidCos Finished-Goods Inventory account as of December 31

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Answer 1.
A Job order costing system is appropriate in any environment where costs can be readily identified with specific products, batches, contracts or projects.
Answer 2.
WIP - Dec-31 - DRS114
DRS114 Balance - Nov 30    250,000.00
December Additions:
Direct Material    124,000.00
Purchased Parts      87,000.00
Direct Labor    200,500.00
Manufacturing Overhead - 19,500 hrs X $7.50    146,250.00    557,750.00
WIP Inventory, Dec 31    807,750.00
Pre-determined Overhead Rate = $4,500,000 / 600,000 Hours = $7.50 per hour
Pre-determined Overhead Rate = $7.50 per hour
Answer 3.
Finished Goods Inventory - Playpens - Dec 31
Units
Beginning Inventory - Nov 30      19,400.00
Units Completed in December      15,000.00
Units Available for Sale      34,400.00
Units Shipped in December      21,000.00
Finished Goods Inventory - Playpens - Dec 31      13,400.00
Since, KIDCo uses FIFO Method, all units in Finished Goods Inventory were completed in December.
Units Cost per Playpen:
WIP - Nov 30    420,000.00
December Additions:
Direct Material Used        3,000.00
Purchased Parts      10,800.00
Direct Labor      43,200.00
Manuafacturing Overhead - 4,400 Hrs X $7.50      33,000.00      90,000.00
Total Costs    510,000.00
Units Completed      15,000.00
Cost per Unit - $510,000 / 15,000 Units              34.00
Value of Finished Goods = $34 X 13,400 Units
Value of Finished Goods = $455,600
Add a comment
Know the answer?
Add Answer to:
cnaaren's furnishings. The company uses a job-order costing system, Kidco's work-in-process inventory at the end or...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 3 Sunland, Inc. manufactures ergonomically designed computer furniture. Sunland uses a job order costing system....

    Question 3 Sunland, Inc. manufactures ergonomically designed computer furniture. Sunland uses a job order costing system. On November 30, the Work in Process Inventory consisted of the following jobs: Job No. Item Units Accumulated Cost CC723 Computer caddy 21,000 $930,000 CH291 Chair 15,000 439,000 PS812 Printer stand 27,000 253,000 $1,622,000 On November 30, Sunland’s Raw Materials Inventory account totaled $697,000, and its Finished Goods Inventory totaled $3,469,400. Sunland applies manufacturing overhead on the basis of machine hours. The company’s manufacturing...

  • Swifty, Inc. manufactures ergonomically designed computer furniture. Swifty uses a job order costing system. On November...

    Swifty, Inc. manufactures ergonomically designed computer furniture. Swifty uses a job order costing system. On November 30, the Work in Process Inventory consisted of the following jobs: Job CC73 Computer Caddy, 23,000 units, $970,000 accumulated cost Job CH291 Chair, 16,000 units, $434,000 accumulated cost Job PS812 Printer stand, 30,000 units, $252,000 accumulated cost Total cost $1,656,000 On November 30, Swifty’s Raw Materials Inventory account totaled $676,000, and its Finished Goods Inventory totaled $3,476,400. Swifty applies manufacturing overhead on the basis...

  • Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were...

    Kenworth Company uses a job-order costing system. Only three jobs—Job 105, Job 106, and Job 107—were worked on during November and December. Job 105 was completed on December 10; the other two jobs were still in production on December 31, the end of the company’s operating year. Data from the job cost sheets of the three jobs follow:    Job Cost Sheet    Job 105 Job 106 Job 107   November costs incurred:      Direct materials $ 20,500 $ 13,300 $ 0...

  • Question 3 Coronado, Inc. manufactures ergonomically designed computer furniture. Coronado uses a job order costing system....

    Question 3 Coronado, Inc. manufactures ergonomically designed computer furniture. Coronado uses a job order costing system. On November 30, the Work in Process Inventory consisted of the following jobs: Units Job No. CC723 CH291 PS812 Item Computer caddy Chair Printer stand Accumulated Cost $980,000 434,000 296,000 $1,710,000 20,000 28,000 and On November 30, Coronado's Raw Materials Inventory account totaled $677,000, and its Finished Goods Inventory totaled $3,464,400. Coronado applies manufacturing overhead on the basis of machine hours. The company's manufacturing...

  • The Healthy Heart Company uses a normal job-order costing system in its only production department. Overhead...

    The Healthy Heart Company uses a normal job-order costing system in its only production department. Overhead is applied to jobs by a plant-wide overhead rate based on direct labor hours. The first year of operation began on December 1, 2018. During the month of December 2018, Healthy Heart purchased direct materials with a total cost of $4,000. Of the $4,000, Healthy Heart uſed $500 on Job 100. Job 100 was the only job worked during the month of December 2018....

  • The Healthy Heart Company uses a normal job-order costing system in its only production department. Overhead...

    The Healthy Heart Company uses a normal job-order costing system in its only production department. Overhead is applied to jobs by a plant-wide overhead rate based on direct labor hours. The first year of operation began on December 1, 2018. During the month of December 2018, Healthy Heart purchased direct materials with a total cost of $4,000. Of the $4,000, Healthy Heart used $500 on Job 100. Job 100 was the only job worked during the month of December 2018....

  • The Film Company uses a job-order costing system. The following information pertains to the company's activities...

    The Film Company uses a job-order costing system. The following information pertains to the company's activities for the month of December: On December 1, the company had two jobs in work in process as follows: Job 6 $20,000 and Job 8 $14,000 On December 1, the company had job in Finished Goods as follows: Job 10 $50,000 Jobs 12 and 13 were started during the month. Materials were purchased on account in December for $54,000 Materials were requisitioned for use...

  • The Healthy Heart Company uses a normal job-order costing system in its only production department. Overhead...

    The Healthy Heart Company uses a normal job-order costing system in its only production department. Overhead is applied to jobs by a plant-wide overhead rate based on direct labor hours. The first year of operation began on December 1, 2018. During the month of December 2018, Healthy Heart purchased direct materials with a total cost of $4,000. Of the $4,000, Healthy Heart used $500 on Job 100. Job 100 was the only job worked during the month of December 2018....

  • Finlon Upholstery Inc. uses a job-order costing system to accumulate manufacturing costs. The company's work-in-process on...

    Finlon Upholstery Inc. uses a job-order costing system to accumulate manufacturing costs. The company's work-in-process on December 31, 2001, consisted of one job (no. 2077), which was carried on the year-end balance sheet at $156,800. There was no finished-goods inventory on this date. Finlon applies manufacturing overhead to production on the basis of direct-labor cost. (The budgeted direct-labor cost is the company's practical capacity, in terms of direct-labor hours multiplied by the budgeted direct-labor rate.) Budgeted totals for 2002 for...

  • Problem for Job Order Costing Tiny Homes uses a job costing system to account for the...

    Problem for Job Order Costing Tiny Homes uses a job costing system to account for the individual prefabricated homes of January 1, its accounting records showed inventories as follows the individual prefabricated homes it builds. As Materials and supplies Work in process (Jobs 422 and 423) Finished goods (Job 421) $120,000 180,000 175,000 The work in process in ventory consisted of two jobs: Job# 422 423 Direct Materials $36,000 Direct Labor Manufacturing Overh $40,000 $20,000 $96,000 $36,000 $180,000 $76,000 $68,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT