Answer a= Lead time to receive the material from the previous workstation = Average processing time per unit * number of units per container + Average waiting time per container
Lead time to receive the material from the previous workstation =0.005*400 +1.1 =3.1 days
L=3.1 days
Demand Rate, D = 1750 parts per day
Container size, C = 400
Number of containers, N = 16
Implied safety factor = N*C/(D*L) – 1 =16*400/(1750*3.1)-1 =0.17972
Answer b-= Desired Lead time, L = N*C/D/(1+s) =(16-2)*400/1750/(1+0.17972)
Desired Lead time, L=2.713
New waiting time=2.713 days
You are asked to analyze the kanban system of LeWin, a French manufacturer of gaming devices....
Gestalt, Inc. uses a kanban system in its automobile production facility in Germany. This facility operates 20 hours per day to produce the Jitterbug, a replacement for the obsolete but immensely popular Jitney Beetle. Suppose that a certain part requires 120 seconds of processing at machine cell 33B and an average container of parts averages 1.6 hours of waiting time there. Management has allowed a 12 percent buffer for unexpected occurrences. Each container holds 33 parts, and 9 containers are...
b. If the muda or waste in the system were eliminated completely, how many containers would be needed? Markland First National Bank of Rolla utilizes kanban techniques in its check processing facility. The following information is known about the process. Each kanban container can hold 50 checks and spends 24 minutes a day in processing and 2 hours a day in materials handling and waiting. Finally, the facility operates 24 hours per day and utilizes a policy variable for unforeseen...
Explain how the production schedule is developed and communicated to the shop-floor in a Just-in-Time (JIT) manufacturing system. Q. B8 (a) (10 marks) Define kanban as it is understood in JIT systems and explain the role and operation of a conveyance or C kanban in the production system. (b) (6 marks) (c) Data for a particular part that is controlled by a two-card kanban system on a JIT feeder line is as follows: daily demand: 500 units average waiting and...