Performance Lawn Equipment (PLE) is considering changing their process to make mower blades. They conducted seven...

Performance Lawn Equipment (PLE) is considering changing their process to make mower blades. They conducted seven production runs and recorded costs. Will the new process save PLE money? Use α = 0.05. (Show all six steps of hypothesis testing.)

Current

New Process

$242.00

$242.00

$176.00

$275.00

$286.00

$199.00

$269.00

$219.00

$327.00

$273.00

$264.00

$265.00

$296.00

$435.00

0 0
Add a comment Improve this question Transcribed image text
Answer #1

(1) List all the information

From The Given dta

For Current Year: \bar{x} 1 = 265.714, s1 = 47.801, n1 = 7

For: New Year:     \bar{x} 2 = 272.571, s2 = 77.105, n2 = 7

\alpha = 0.05

(2) State the Null and alternate hypothesis

The Hypothesis:

H0: \mu_1 = \mu_2:

H0: \mu_1 < \mu_2:

This is a Left tailed test

__________________________________

(3) State the test to be used and verify the requirements

We use a 2 sample t test, pooled variances, with df = n1 + n2 - 2 = 7 + 7 - 2 = 12

The requirements are

(1) Samples are simple random samples

(2) The samples are independent of each other

__________________________________________

(4) Compute the standardized test statistic


The Pooled Variance:

S_p^2 = \frac{(n1-1)*s1^2+(n2-1)*s2^2}{n1+n2-2} = \frac{6*47.801^2+6*77.105^2}{7+7-2} = 4115

The Test Statistic:

t = \frac{\bar{x}_1-\bar{x}_2}{\sqrt{S_p^2}(\frac{1}{n1}+\frac{1}{n2})} = \frac{266.714-272.572}{\sqrt{4115*(\frac{1}{7}+\frac{1}{7})}} = -0.17

______________________________________________

(5) Find the p value and compare it to the level of significance.

The p value at t = -0.17) is 0.5665.

p value is > 0.05

_________________________________________________

(6) Make a decision, and then write the final conclusion

Fail To Reject H0. There isn't sufficient evidence at the 95% significance level to conclude that new process will save PLE money.

_____________________________________________________

Add a comment
Know the answer?
Add Answer to:
Performance Lawn Equipment (PLE) is considering changing their process to make mower blades. They conducted seven...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. Engineering has collected data on alternative process costs for building transmissions in the worksheet Transmission...

    1. Engineering has collected data on alternative process costs for building transmissions in the worksheet Transmission costs. Can you determine whether one of the proposed processes is better than the current process? Unit Tractor Transmission Costs Current Process A Process B $242.00 $242.00 $292.00 $176.00 $275.00 $321.00 $286.00 $199.00 $314.00 $269.00 $219.00 $242.00 $327.00 $273.00 $278.00 $264.00 $265.00 $300.00 $296.00 $435.00 $301.00 $333.00 $285.00 $286.00 $242.00 $384.00 $315.00 $288.00 $387.00 $300.00 $314.00 $299.00 $304.00 $302.00 $145.00 $300.00 $335.00 $266.00 $351.00...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT