Calculator At the end of April, Cavy Company had completed Job 766 and 765. According to the individual job cost sheets the i
0 0
Add a comment Improve this question Transcribed image text
Answer #1

a.  

Job Direct material Direct labor Overhead Total job costs
Job 765 $6,160 $1,848

$3,102

(22 * $141)

$11,110
Job 766 $13,851 $4,374

$11,421

(81 * $141)

$29,646

Job 765 = $11,110

Job 766 = $29,646

b.

Cost per unit = Total job cost / Number of units

Job 765 = $11,110 / 132 = $84.17

Job 766 = $29,646 / 405 = $73.20

Add a comment
Know the answer?
Add Answer to:
Calculator At the end of April, Cavy Company had completed Job 766 and 765. According to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • At the end of April, Cavy Company had completed Jobs 766 and 765. According to the...

    At the end of April, Cavy Company had completed Jobs 766 and 765. According to the individual job cost sheets the information is as follows: Job Direct Materials Direct Labor Machine Hours Job 765 $10,080 $3,024 36 Job 766 $14,877 $4,698 87 Job 765 consisted of 216 units, and Job 766 consisted of 261 units. Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $137 per hour. a. Determine the balance on the...

  • At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job...

    At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job cost sheets reveal the following information: Job Direct Materials Direct Labor Machine Hours Job 765 $5,600 20 $1,680 3,834 Job 766 12,141 71 Job 765 produced 120 units, and Job 766 consisted of 284 units. Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $130 per hour. a. Determine the balance on the job cost sheets for...

  • At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job...

    At the end of April, Cavy Company had completed Jobs 766 and 765. The individual job cost sheets reveal the following information: Job Direct Labor Direct Materials $10,920 Job 765 $3,276 Machine Hours 39 80 Job 766 13,680 4,320 Job 765 produced 234 units, and Job 766 consisted of 400 units. Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $110 per hour. a. Determine the balance on the job cost sheets for...

  • At the end of the month, the M&M Company had completed Job Red and Job Yellow....

    At the end of the month, the M&M Company had completed Job Red and Job Yellow. The individual job cost sheets reveal the following information: Job    Direct Materials Direct Labor                  Machine Hours Job Red                  $6,720                               $2,016    24 Job Yellow                12,966    4,104 76 ​ Job Red produced 144 units, and Job Yellow consisted of 228 units. Assuming that the predetermined overhead rate is applied by using machine hours at a rate of $142 per hour, determine the (a)...

  • 1) 2) 3) 4) 5) Mocha Company manufactures a single product by a continuous process, involving...

    1) 2) 3) 4) 5) Mocha Company manufactures a single product by a continuous process, involving three production departments. The records indicate that direct materials, direct labor, and applied factory overhead for Department 1 were $100,000, $125,000, and $150,000, respectively. Work in process at the beginning of the period for Department 1 was $75,000, and work in process at the end of the period totaled $60,000. The records indicate that direct materials, direct labor, and applied factory overhead for Department...

  • Job Costs At the end of April, Prichard Company had completed Jobs 50 and 51. Job...

    Job Costs At the end of April, Prichard Company had completed Jobs 50 and 51. Job 50 is for 200 units, and Job 51 is for 500 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 200 units for Job 50 at $12 per unit and 1,200 units for Job 51 at $12 per unit. During April, Prichard Company accumulated 500 hours of direct labor costs on Job 50...

  • Job Costs At the end of April, Kaye Company had completed Jobs 50 and 51. Job...

    Job Costs At the end of April, Kaye Company had completed Jobs 50 and 51. Job 50 is for 1,000 units, and Job 51 is for 500 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 300 units for Job 50 at $24 per unit and 1,100 units for Job 51 at $12 per unit. During April, Kaye Company accumulated 700 hours of direct labor costs on Job 50...

  • Job Costs At the end of April, Kaye Company had completed Jobs 50 and 51. Job...

    Job Costs At the end of April, Kaye Company had completed Jobs 50 and 51. Job 50 is for 500 units, and Job 51 is for 200 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 500 units for Job 50 at $10 per unit and 1,400 units for Job 51 at $24 per unit. During April, Kaye Company accumulated 200 hours of direct labor costs on Job 50...

  • Job Costs At the end of April, Kaye Company had completed Jobs 50 and 51. Job...

    Job Costs At the end of April, Kaye Company had completed Jobs 50 and 51. Job 50 is for 500 units, and Job 51 is for 200 units. The following data relate to these two jobs: On April 20, raw materials were requisitioned for production as follows: 500 units for Job 50 at $10 per unit and 1,400 units for Job 51 at $24 per unit. During April, Kaye Company accumulated 200 hours of direct labor costs on Job 50...

  • Job Costs At the end of April, Prichard Company had completed Jobs 50 and 51. Job...

    Job Costs At the end of April, Prichard Company had completed Jobs 50 and 51. Job 50 is for 1,000 units, and Job 51 is for 200 units The following data relate to these two jobs: Job at $20 per unit and 1,400 units for Job 51 On April 20, raw materials were requisitioned for production as follows: 500 units for at $22 per unit. During April, Prichard Company accumulated 700 hours of direct labor costs on Job 50 and...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT