Interest rate per annum = 14 %
Interest rate per month = 14/12 = 1.17 %
NPV = Total cash inflows - Initial investment
NPV =R*(1-(1+i)-n)/i - Investment
where R = cash inflow per month = 30000 $
i = Interest Rate per month = 1.17 %
n = Number of months
NPV = 30000*(1-(1+0.0117)-12)/0.0117 - 255000 = 79275 $ (approx)
Calculate the net present value of a project which requires an initial investment of $243,000 and it is expected to generate a cash inflow of $50,000 each month for 12 months. Assume that the salvage value of the project is zero. The target rate of return is 12% per annum
Calculate the Net Present Value of a project which requires an initial investment of $255000 and...
Calculate the net present value of a project which requires an initial investment of $243,000 and it is expected to generate a cash inflow of $50,000 each month for 12 months. Assume that the salvage value of the project is zero. The target rate of return is 12% per annum. Note: Initial Investment = $243,000 Net Cash Inflow per Period = $50,000 Number of Periods = 12 Discount Rate per Period = 12% + 12 = 1%
Calculate the net present value (NPV) for a 20-year project with an initial investment of $10 comma 000 and a cash inflow of $2 comma 000 per year. Assume that the firm has an opportunity cost of 14%. Comment on the acceptability of the project The project's net present value is ____
NPV Calculate the net present value (NPV) for a 20-year project with an initial investment of $10,000 and a cash inflow of $2,000 per year. Assume that the firm has an opportunity cost of 16%. Comment on the acceptability of the project. The project's net present value is $ (Round to the nearest cent.)
1. Calculate the net present value (NPV) for a 10-year project with an initial investment of $25,000 and a cash inflow of $7,000 per year. Assume that the firm has an opportunity cost of 17%. The project's net present value is $_____.
NPV Calculate the net present value (NPV) for a 30-year project with an initial investment of $25,000 and a cash inflow of $4,000 per year. Assume that the firm has an opportunity cost of 18% Comment on the acceptability of the project. The project's net present value is S□ (Round to the nearest cent ) Enter your answer in the answer box and then click Check Answer part remainin Clear All javascriptdoExercise(3);
A project requires an initial investment of $4,000. The project is expected to generate positive cash flows of $2,500 a year for next three years and additional $300 in the last year (i.e., third year) of the project’s life. The required rate of return is 12%. What is the project’s net present value (NPV)? Based on the calculated NPV, should the project be accepted or rejected?
If the present value (PV) of an investment project that requires an initial investment of $2,000,000 is $500,000, its net present value (NPV) is -$1,500,000 True False QUESTION 7 30-day forward rates are the same as spot exchange rates. True False
Calculate the net present value for a 15-year project with an initial investment of $ 0 and a cash inflow of $2,000 per year. Assume that the firm has an opportunity cost of 13%. Comment on the acceptability of the project. The project's net present value is $____ .
A project that requires an initial investment of $850,000 has a profitability index of 1.78. Calculate the project's net present value (NPV). The required return of the project is 10 percent. A. $592,500 B. $772,727 C. $663,000 D. $1,513,000
A project requires an initial investment (or you may say, ‘cash outflow’) of $225,000 and is expected to generate the following net cash inflows: Year 1: $125,000 Year 2: $120,000 What is Net Present Value (NPV) of the project if the minimum required rate of return (or, you may say firm’s cost of capital) is 5%? 3012.42 2312.23 3201.21 2891.16