Question

jects NPV at various costs of capital. A projects NPV profile is shown as follows. Identify An NPV profile plots a pro the range of costs of capital that a firm would use to accept and reject this project. NPV (Dollars) 400 300 200 Accept 100 Reject -100 -200 0 2 4 68 10 12 14 16 18 20 COST OF CAPITAL [Percent) The point at which the NPV profile intersects the horizontal axis represents the
media%2F191%2F19174020-b5de-4270-b2ff-f3
0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) As per the NPV rule, all projects with postive NPV should be accepted. In the given diagram, NPV is positive in green portion and negative in the purple portion. Therefore, green portion should be accepted and purple portion should be rejected.

The point at which NPV profile intersects the horizontal axis represents the IRR. IRR is the rate at which NPV is zero.

2) Payback period is the period within which the intial cash outflow or initial investment is recovered by the cash inflows of the project.

Conventional payback period

The initial outflow of (-)$6,000,000 is recovered or becomes positive in year 2. So, payback period is beyond year 1 but before the end of year 2 since cumulative cash flow is not zero in year 2 but actually more than that. So, initial cash flow in year 2 is more than required for the payback.

Payback period = 1 year + 1 year x (Cash flow required in Year 2 / Total cash flow in year 2)

or, Payback period = 1 year + 1 year x ($3,600,000 / $5,100,000) = 1.70588 year or 1.71 years

Discounted payback period

Similarly, in this case, payback period is beyond year 1 but before the end of year 2. Only difference between this method and the conventional method is that we use discounted cash flows instead of normal cash flows -

Payback period = 1 year + 1 year x (Discounted cash flow required in year 2 / Total discounted cash flow in year 2)

or, Payback period = 1 year + 1 year x ($3,798,165 / $4,292,568) = 1.8848235 years or 1.88 years

Discounted payback period should be used by the CFO because it takes into account the time value of money by considering discounted cash flows and gives a more accurate measure of the payback period.

Add a comment
Know the answer?
Add Answer to:
ject's NPV at various costs of capital. A project's NPV profile is shown as follows. Identify...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled "A" and "B" in the graph. A p...

    5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled "A" and "B" in the graph. A project's NPV profile is shown as follows. Identify the range of costs (ranges labeled "A" and "B") of capital that a firm would use to accept and reject this project. NPV (Dollars) 400 А -200 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) The point at which the NPV profile...

  • 5. NPV profiles An NPV profile plots a project's NPV at various costs of capital. A...

    5. NPV profiles An NPV profile plots a project's NPV at various costs of capital. A project's NPV profile is shown in the graph. Identify the range of costs of capital that a firm would use to accept and reject this project by responding to the drop-down choices below the graph. NPV (Dollars) в -200 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) Reject The pe Accept Thich the NPV profile intersects the...

  • An NPV profile plots a project's NPV at various costs of capital. A project's NPV profile...

    An NPV profile plots a project's NPV at various costs of capital. A project's NPV profile is shown as follows. Identify the range of costs of capital that a firm would use to accept and reject this project. NPV (Dollars) 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) This NPV profile demonstrates that as the cost of capital increases, the project's NPV

  • An NPV profile plots a project's NPV at various costs of capital. A project's NPV profile...

    An NPV profile plots a project's NPV at various costs of capital. A project's NPV profile is shown as follows. Identify the range of costs of capital that a firm would use to accept and reject this project. NPV (Dollars) 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) This NPV profile demonstrates that as the cost of capital increases, the project's NPV decreases increases

  • Dropdown options: (accept, reject), (accept, reject), (IRR, WACC) An NPV profile plots a project's NPV at...

    Dropdown options: (accept, reject), (accept, reject), (IRR, WACC) An NPV profile plots a project's NPV at various costs of capital. A project's NPV profile is shown in the graph. Identify the range of costs of capital that a firm would use to accept and reject this project by responding to the drop-down choices below the graph. NPV (Dollars) A -200 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) B The point at which...

  • An NPV profile plots a project's NPV at various costs of capital. A project's NPV profile...

    An NPV profile plots a project's NPV at various costs of capital. A project's NPV profile is shown as follows. Identify the range of costs of capital that a firm would use to accept and reject this project. NPV (Dollars) 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) True or False: The NPV and IRR methods can lead to conflicting decisions for mutually exclusive projects. O True False

  • Ch 11: Assignment - The Basics of Capital Budgeting 5. NPV profiles An NPV profile plots...

    Ch 11: Assignment - The Basics of Capital Budgeting 5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled "A" and "B" in the graph. A project's NPV profile is shown as follows. Identify the range of costs (ranges labeled "A" and "B") of capital that a firm would use to accept and reject this project. NPV Dollars -200 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL I...

  • 5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled...

    5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled "A" and "B" in the graph. A project's NPV profile is shown as follows. Identify the range of costs (ranges labeled "A" and "B") of capital that a firm would use to accept and reject this project. NPV Dollars 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) This NPV profile demonstrates that as the cost of capital...

  • 5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled...

    5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled "A" and "B" in the graph. A project's NPV profile is shown as follows. Identify the range of costs (ranges labeled "A" and "B") of capital that a firm would use to accept and reject this project. NPV (Dollars) -200 0 2 4 6 8 10 12 14 16 18 20 COST OF CAPITAL (Percent) True or False: The NPV and IRR methods can...

  • < Back to Assignment Do No Harm: /2 Attempts: 5. NPV profiles An NPV profile plots...

    < Back to Assignment Do No Harm: /2 Attempts: 5. NPV profiles An NPV profile plots a project's NPV at various costs of capital, labeled "A" and "B" in the graph. A project's NPV profile is shown as follows. Identify the range of costs (ranges labeled "A" and "B") of capital that a firm would use to accept and reject this project NPV (Dollars) 400 300 A 200 100 0 -100 200 0 2 4 6 8 10 12 14...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT