Gas Heating Option: The initial equipment and installment of the natural gas system would cost $245,000 right now. The mainte

thats all the info that is given.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Gas Heating Option:

Initial cost = -$245000

Maintenance cost = -$1000

Energy Cost = -$6000 with growth rate of 5%

Hence PW of Maintenance cost = -1000(P/A, 16, 8%) = -1000*8.851 = -$8851

PW of Energy cost = A*(1-(1+g)^n/(1+r)^n)/(r-g)

=-6000*(1-(1+5%)^16/(1+8%)^16)/(8%-5%)

=-6000*(1-2.183/3.426)/3%

=-6000*(1-0.6372)/0.03

=-6000*0.3628/0.03

=-$72562.76

Hence Total PW = -245000-8851-72562.76=-$326413.76 or -$326414

AW = -326414*(A/P, 16, 8%) = -326414*0.113 = -$36884.75

Geothermal Heating Option:

Initial cost = -$205000

Maintenance cost = -$14000

Hence PW of Maintenance cost = -14000(P/A, 20, 8%) = -14000*9.818 = -$137452

Hence Total PW = -205000-137452=-$342452

AW = -342452*(A/P, 20, 8%) = -342452*0.1019 = -$34895.85

Since AW of Geothermal Option is higher it is the lower cost option

Add a comment
Know the answer?
Add Answer to:
thats all the info that is given. Save Homework: Chapter 6 HW Score: 0 of 1...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Homework: MEL Mod 3 Ch 5 HW Save Score: 0 of 5 pts 1 of 18...

    Homework: MEL Mod 3 Ch 5 HW Save Score: 0 of 5 pts 1 of 18 (0 complete) HW Score: 0%, 0 of 100 p Problem 5-3 (book/static) 5 Question Help Josh Ritchey has just been hired as a cost engineer by a large airlines company. Josh's first idea is to quit giving complimentary cocktails, wine, and beer to the international flying public. He calculates this will save 5,000,000 drinks per year, and each drink costs $0.50 for a total...

  • Problem 4-88 (algorithmic) 3 Question Help A small company heats its building and spends $8,500 per...

    Problem 4-88 (algorithmic) 3 Question Help A small company heats its building and spends $8,500 per year on natural gas for this purpose. Cost increases of natural gas are expected to be 10% per year starting one year from now (i.e., the first cash flow is $9,350 at EOY one). Their maintenance on the gas furnace is $345 per year, and this expense is expected to increase by 12% per year starting one year from now (i.e., the first cash...

  • CLOUnD2082088810468/13a96602f99dd IENG 301 Spring 2019 (1) Homework: Ch. 2 HW Probs Score: 0 of 10 pts...

    CLOUnD2082088810468/13a96602f99dd IENG 301 Spring 2019 (1) Homework: Ch. 2 HW Probs Score: 0 of 10 pts Problem 2-14 (book/static) 3 of 12 (3 complete) What is the present worth of these future payments? (a) $25,500 eight years from now at 12% compounded annually (b) $58,000 twelve years from now at 4% compounded annually (c) $25,000 nine years from now at 6% compounded annually (d) $35,000 four years from now at 9% compounded annually Click the icon to view the interest...

  • Your company is environmentally conscious and is considering two heating options for a new research building....

    Your company is environmentally conscious and is considering two heating options for a new research building. What you know about each option is below, and your company will use an annual interest rate (MARR) of 8% for this decision. Which is the lower cost option for the company? Click the icon to view the additional information about the options. 2 Click the icon to view the interest and annuity table for discrete compounding when the MARR is 5% per year....

  • your company is environmentally conscious and is considering two heating options for a new research building....

    your company is environmentally conscious and is considering two heating options for a new research building. What you know about each option is below, and your company will use and annual interest rate (MARR) of 6% for this decision. Which is the lower cost option for the company? I need the PW of both options Your company is environmentally conscious and is considering two heating options for a new research building. What you know about each option is below, and...

  • Homework: HW #1 -Chapter 2 Save Score: 0 of 1 pt E2-26A (similar to) Compute the...

    Homework: HW #1 -Chapter 2 Save Score: 0 of 1 pt E2-26A (similar to) Compute the Cost of Goods Manufactured and Cost of Goods Sold for South Marine Company for the most recent year using the amounts described next. Assume that Raw Materials Inventory contains only direct materials. 7 of 10 (0 complete) HW Score: 0%, 0 of 10 pts Question Help EEE (Click the icon to view the data.) Start the calculation for cost of goods manufactured by calculating...

  • Score: 0 of 1 pt < 2 of 6 (5 complete) HW Score: 53.89%, 3.23 of...

    Score: 0 of 1 pt < 2 of 6 (5 complete) HW Score: 53.89%, 3.23 of 6 pts X S12A-15 (similar to) Question Help Liam is entering high school and is determined to save money for college. Liam feels he can save $1,000 each year for the next four years from his part-time job. If Liam is able to invest at 4%, how much will he have when he starts college? (Click the icon to view Present Value of $1...

  • Homework: HW #2-Chapter 3 Save Score: 0 of 1 pt 5 of 10 (0 complete) HW...

    Homework: HW #2-Chapter 3 Save Score: 0 of 1 pt 5 of 10 (0 complete) HW Score: 0%, 0 of 10 pts E3-20A (similar to) Question Help Richmond Heating & Cooling installs and services commercial heating and cooling In August, Richmond started and completed the following two jobs: systems. Richmond uses job costing to calculate the cost of its jobs. Overhead is (Click the icon to view the jobs.) allocated to each job based on the number of direct labor...

  • Homework: Chapter 8 Homework Save Score: 0 of 1 pt 6 of 7 (5 complete) HW...

    Homework: Chapter 8 Homework Save Score: 0 of 1 pt 6 of 7 (5 complete) HW Score: 50%, 5 of 10 pts E8-29A (similar to) * Question Help o GlobalSystems manufactures an optical switch that it uses in its final product. (Click the icon to view the outsourcing decision analysis.) GlobalSystems incurred the following manufacturing costs when it produced 69,000 units last year: GlobalSystems needs 79,000 optical switches next year (assume same relevant B (Click the icon to view the...

  • Homework: Chapter 8 Homework Save Score: 0 of 1 pt 6 of 7 (5 complete) HW...

    Homework: Chapter 8 Homework Save Score: 0 of 1 pt 6 of 7 (5 complete) HW Score: 50%, 5 of 10 pts E8-29A (similar to) * Question Help o GlobalSystems manufactures an optical switch that it uses in its final product. (Click the icon to view the outsourcing decision analysis.) GlobalSystems incurred the following manufacturing costs when it produced 69,000 units last year: GlobalSystems needs 79,000 optical switches next year (assume same relevant B (Click the icon to view the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT