Question

Draw the corresponding PERT or Network Diagram. Estimated Times Preceding Activities 6 1 Activity ACTIIVITY 1. Interviews 2.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Created a network diagram (activity on node) as per given dependencies and task's expected completion time.

During the forward pass, the Early start value of dependent activity is the highest value of its predecessor activities.

Early Finish = early start + Duration

During the backward pass, the Late finish value of predecessor activity is the lowest value of its dependent activities.

Late start = Late finish - Duration

Early Start Duration Early finish Activity Namel ID Late start Duration Late Finish | 5 5 | 18 1933 46 195 24 24933 1 044 14

Since a different format is asked in the question, recreated the same network diagram as follows.

Late Finish Activity Name/ ID Expected time Early start 24 5 10 2 5 13 9 24 6 4 20 7 13

2. Delay on the critical path leads to delay in the project. Critical path have zero slack where slack = ES-LS

Slack is observed to be zero on activities 1, 2, 4, 6, 7, 8 as activity 3 has slack of 2 (6-4) days and activity 5 has slack of 6 (19-13) days.

Hence Critical path is 1-2-4-6-7-8

The same is highlighted with thicker arrow width in diagram below.

Late Finish Activity Name/ ID Expected time Early start 24 5 | 8133 9 | 24 | 5 13 | 10 | 77 17 20 7 |

Add a comment
Know the answer?
Add Answer to:
Draw the corresponding PERT or Network Diagram. Estimated Times Preceding Activities 6 1 Activity ACTIIVITY 1....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT