Created a network diagram (activity on node) as per given dependencies and task's expected completion time.
During the forward pass, the Early start value of dependent activity is the highest value of its predecessor activities.
Early Finish = early start + Duration
During the backward pass, the Late finish value of predecessor activity is the lowest value of its dependent activities.
Late start = Late finish - Duration
Since a different format is asked in the question, recreated the same network diagram as follows.
2. Delay on the critical path leads to delay in the project. Critical path have zero slack where slack = ES-LS
Slack is observed to be zero on activities 1, 2, 4, 6, 7, 8 as activity 3 has slack of 2 (6-4) days and activity 5 has slack of 6 (19-13) days.
Hence Critical path is 1-2-4-6-7-8
The same is highlighted with thicker arrow width in diagram below.