Question

Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the...

Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the company produced 27,600 units. Each unit took several pounds of direct materials and 1.6 standard hours of direct labor at a standard hourly rate of $13.00. Normal capacity was 49,700 direct labor hours. During the year, 130,800 pounds of raw materials were purchased at $0.91 per pound. All materials purchased were used during the year. (a) Your answer is correct. If the materials price variance was $5,232 favorable, what was the standard materials price per pound? (Round answer to 2 decimal places, e.g. 2.75.) Standard materials price per pound $ Click if you would like to Show Work for this question: Open Show Work Show Solution Show Answer Link to Text Link to Text Attempts: 1 of 3 used (b) Your answer is correct. If the materials quantity variance was $14,136 unfavorable, what was the standard materials quantity per unit? (Round answer to 1 decimal place, e.g. 1.5.) Standard materials quantity per unit Click if you would like to Show Work for this question: Open Show Work Show Solution Show Answer Link to Text Link to Text Attempts: 2 of 3 used (c) Your answer is correct. What were the standard hours allowed for the units produced? Standard hours allowed Click if you would like to Show Work for this question: Open Show Work Show Solution Show Answer Link to Text Link to Text Attempts: 1 of 3 used (d) Your answer is correct. If the labor quantity variance was $5,200 unfavorable, what were the actual direct labor hours worked? Actual hours worked Click if you would like to Show Work for this question: Open Show Work Show Solution Show Answer Link to Text Link to Text Attempts: 1 of 3 used (e) Your answer is correct. If the labor price variance was $8,912 favorable, what was the actual rate per hour? (Round answer to 2 decimal places, e.g. 2.75.) Actual rate per hour $ Click if you would like to Show Work for this question: Open Show Work Show Solution Show Answer Link to Text Link to Text Attempts: 1 of 3 used (f) Your answer is correct. If total budgeted manufacturing overhead was $323,050 at normal capacity, what was the predetermined overhead rate? (Round answer to 2 decimal places, e.g. 2.75.) Predetermined overhead rate $ Click if you would like to Show Work for this question: Open Show Work Show Solution Show Answer Link to Text Link to Text Attempts: 1 of 3 used (g) What was the standard cost per unit of product? (Round answer to 2 decimal places, e.g. 2.75.) Standard cost per unit $

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1) If the materials price variance was $5,232 favorable, what was the standard materials price per pound? (Round answer to 2 decimal places, e.g. 2.75.)
(Actual price - Standard price) x Actual quantity used = Material price variance
($0.91 - SP ) x 130800 pounds = - $5232
(130800 x $.91 +$5232 )/130800
Standard materials price per pound $           0.95
2) If the materials quantity variance was $14,136 unfavorable, what was the standard materials quantity per unit? (Round answer to 1 decimal place, e.g. 1.5.)
Standard Usage in Units = $14136/$.95)      14,880.00 Pounds
Standard Quantity for 27600 units = (130,800 - 14880)pounds 1,15,920.00 Pounds
Standard materials quantity per unit = (115920/27600 units)               4.20 Pounds per unit
3) What were the standard hours allowed for the units produced?
Standard hours allowed = standard hours of direct labor x units produced
Standard hours allowed = 1.6 x 27,600 units      44,160.00 Hours
4) If the labor quantity variance was $5,200 unfavorable, what were the actual direct labor hours worked?
DL Efficiency Variance = ( SH − AH ) × SR
-$5200 = (44,160 - AH) x $13
Actual hours worked = (44160 x $13 + 5200)$13      44,560.00 Hours
5) If the labor price variance was $8,912 favorable, what was the actual rate per hour? (Round answer to 2 decimal places, e.g. 2.75.)
(Actual rate - Standard rate) x Actual hours worked = Labor rate variance
(AR - $13) x 44560 = $8912
Actual rate per hour = (($13 x 44560)-8912)/44560 $         12.80
6)
If total budgeted manufacturing overhead was $323,050 at normal capacity, what was the predetermined overhead rate?
Predetermined overhead rate = 323050/49700 DL 6.5 Per direct labour hour
7)
What was the standard cost per unit of product?
Direct Material = 4.20 pound per unit x $.95 3.99
Direct Labour = 1.6 x $13 20.8
Manufacturing Overhead = 1.6 x $6.5 10.4
Standard cost per unit $         35.19
Add a comment
Know the answer?
Add Answer to:
Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the...

    Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the company produced 27,600 units. Each unit took several pounds of direct materials and 1.6 standard hours of direct labor at a standard hourly rate of $13.00. Normal capacity was 49,700 direct labor hours. During the year, 130,800 pounds of raw materials were purchased at $0.91 per pound. All materials purchased were used during the year. (a) Your answer is correct. If the materials price...

  • Kansas Company uses a standard cost accounting system. In 2017, the company produced 28,500 units. Each...

    Kansas Company uses a standard cost accounting system. In 2017, the company produced 28,500 units. Each unit took several pounds of direct materials and 1.6 standard hours of direct labor at a standard hourly rate of $13.00. Normal capacity was 49,900 direct labor hours. During the year, 131,300 pounds of raw materials were purchased at $0.91 per pound. All materials purchased were used during the year. (a) Your answer is correct. If the materials price variance was $5,252 favorable, what...

  • Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the...

    Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the company produced 28,400 units. Each unit took several pounds of direct materials and 1.6 standard hours of direct labor at a standard hourly rate of $11.00. Normal capacity was 50,300 direct labor hours. During the year, 130,700 pounds of raw materials were purchased at $0.95 per pound. All materials purchased were used during the year. (d) X Your answer is incorrect. Try again. If...

  • CALCULATOR PRINTER VERSION BACK Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting...

    CALCULATOR PRINTER VERSION BACK Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the company produced 28,500 units. Each unit took several pounds of direct materials and 1.6 standard hours of direct labor at a standard hourly rate of $13.00. Normal capacity was 49,900 direct labor hours. During the year, 131,300 pounds of raw materials were purchased at $0.91 per pound. All materials purchased were used during the year. (a) x Your answer is...

  • Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the...

    Problem 23-4A (Part Level Submission) Kansas Company uses a standard cost accounting system. In 2017, the company produced 27,600 units. Each unit took several pounds of direct materials and 1.6 standard hours of direct labor at a standard hourly rate of $13.00. Normal capacity was 49,700 direct labor hours. During the year, 130,800 pounds of raw materials were purchased at $0.91 per pound. All materials purchased were used during the year. (a) If the materials price variance was $5,232 favorable,...

  • Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of...

    Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $854,000 $1,500,000 $1,020,000 Direct labor costs $1,220,000 $1,875,000 $675,000 Direct...

  • Problem 23-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and...

    Problem 23-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.40 $2.20 Raw materials units used 11,000 10,300 Direct labor payroll $162,800 $159,600 Direct labor hours worked 14,800 15,200 Manufacturing overhead incurred $217,464 Manufacturing overhead applied $221,464 Machine hours expected to be used at normal capacity 41,500 Budgeted fixed overhead for June $66,400 Variable overhead rate per...

  • Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of...

    Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department Manufacturing overhead Direct labor costs Direct labor hours Machine hours $1,179,000 $1,684,286 150,000 600,000 $1,750,000...

  • Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of...

    Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $854,000 $1,500,000 $1,020,000 Direct labor costs $1,220,000 $1,875,000 $675,000 Direct...

  • Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of...

    Problem 15-4A (Part Level Submission) Agassi Company uses a job order cost system in each of its three manufacturing departments. Manufacturing overhead is applied to jobs on the basis of direct labor cost in Department D, direct labor hours in Department E, and machine hours in Department K. In establishing the predetermined overhead rates for 2017, the following estimates were made for the year. Department D E K Manufacturing overhead $854,000 $1,500,000 $1,020,000 Direct labor costs $1,220,000 $1,875,000 $675,000 Direct...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT