Question

Hawkins Corporation began construction of a motel on March 31, 2016. The project was completed on April 31, 2017. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period:

  

$ 4,800,000, 6% note
$21,920,000, 10% bonds

  

Construction expenditures incurred were as follows:
  March 31, 2016 $4,720,000
  June 30, 2016 6,720,000
  November 30, 2016 1,944,000
  February 28, 2017 3,720,000

  

The company’s fiscal year-end is December 31.

Required: Calculate the amount of interest capitalized for 2016 and 2017. (Round weighted average interest rate to 2 decimal

0 0
Add a comment Improve this question Transcribed image text
Answer #1

answel Schedule o weiahted ug accumulaked Depaiaehon-2016 30-Jan 30- Weighted Porg accunulaked Depnikidio Dake amamt CSrent C

Add a comment
Know the answer?
Add Answer to:
Hawkins Corporation began construction of a motel on March 31, 2016. The project was completed on...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Hawkins Corporation began construction of a motel on March 31, 2016. The project was completed on...

    Hawkins Corporation began construction of a motel on March 31, 2016. The project was completed on April 31, 2017. No new loans were required to fund construction. Hawkins does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $ 4,500,000, 6% note $19,700,000, 10% bonds Construction expenditures incurred were as follows: March 31, 2016 $4,450,000 June 30, 2016 6,450,000 November 30, 1,890,000 2016 February 28, 2017 3,450,000 The company's fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 6% note $5,000,000, 2% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 540,000 September 30, 2018 750,000 November 30, 2018 750,000 January 30, 2019 690,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $5,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 $ 660,000 September 30, 2018 930,000 November 30, 2018 930,000 January 30, 2019 870,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 8% note $9,000, 800, 4% bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 48e, eae 720,899 720.99 660,800 120,00€ The company's fiscal year-end is December...

  • Keiron Industries began construction of a warehouse on July 1, year 1. The project was completed...

    Keiron Industries began construction of a warehouse on July 1, year 1. The project was completed on March 31, year 2. No new loans were required to fund construction. Keiron does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 10% note $7,000,000, 5% bonds Construction expenditures incurred were as follows: July 1, year 1 September 30, year 1 November 30, year 1 January 30, year 2 $500,000 600,000 400,000 550,000 The company's fiscal year-end...

  • Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2018. The project was completed on March 31, 2019. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 7% note $8,000,000, 34 bonds Construction expenditures incurred were as follows: July 1, 2018 September 30, 2018 November 30, 2018 January 30, 2019 $ 340,000 690,000 690,000 630,000 The company's fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $3,000,000, 12% note $7,000,000, 7% bonds Construction expenditures incurred were as follows: July 1, 2021 $ 700,000 September 30, 2021 990,000 November 30, 2021 990,000 January 30, 2022 930,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 9% note $6,000,000, 6% bonds Construction expenditures incurred were as follows: July 1, 2021 $ 430,000 September 30, 2021 630,000 November 30, 2021 630,000 January 30, 2022 570,000 The company’s fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $4,000,000, 10% note $6,000,000, 5* bonds Construction expenditures incurred were as follows: July 1, 2021 September 30, 2021 November 30, 2021 $ 640,000 960,000 960,000 900,000 January 30, 2022 The company's fiscal year-end is December 31. Required: Calculate...

  • Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on...

    Thornton Industries began construction of a warehouse on July 1, 2021. The project was completed on March 31, 2022. No new loans were required to fund construction. Thornton does have the following two interest-bearing liabilities that were outstanding throughout the construction period: $2,000,000, 8% note $8,000,000, 4% bonds Construction expenditures incurred were as follows: July 1, 2021 September 30, 2021 November 30, 2021 January 30, 2022 $ 400,000 600,000 600,000 540,000 The company's fiscal year-end is December 31. Required: Calculate...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT