Question

Question 9 Use the following decision tree, but update the probabilities as follows: Probability of Small Demand = 20% Probab
$1.0 Do nothing Small demand (4) Expand Medium demand (.5) Large demand (1) Do nothing Expand Build Subcontract Do nothing O
0 0
Add a comment Improve this question Transcribed image text
Answer #1

As per the revise information given in the question for the probabilities values, the probability of the small demand is 20% which 0.2. the probability of the medium demand is 14% which is 0.14 and the remaining is the large demand probability which is (100 - (20 + 14) = 66% or 0.66 is the probability of the large demand.

So, we have to replace the values of the new probabilities in the given decision tree to calculate the expected value. The expected value for a project is calculated by multiplying each of the possible outcomes of that project by the likelihood each outcome will occur and then summing all of those values. As a final decision, we have to choose the higher value as the Expected Value (EV) of the project. So, now based on this understanding, let's find out the expected value of all 3 projects mentioned in the given picture.

Project A (Subcontract):-

1 x 0.2 + (1.3 x 0.14 + 1.3 x 0.14) + ( 1.5 x 0.66 + 1.6 x 0.66 + 1.8 x 0.66) = 0.2 + (0.182 + 0.182) + (0.99 + 1.056 + 1.188) = 0.2 + 0.364 + 2.244 = 2.808

So the EV of Subcontract is 2.808 $

Project B ( Expand):-

0.2 x ( 0.7 + 1.5 + 1.0) + 0.14 x 1.6 + 0.66 x ( 1.6 + 1.5 + 1.7) = 0.64 + 0.224 + 3.168 = 4.032

So the EV of Expand is 4.032 $

Project C ( Build) :-

0.2 x (0.9 + 1.4 + 1.0) + 0.14 x ( 1.0 + 1.1 + 0.9 ) + 0.66 x 2.4 = 0.66 + 0.42 + 1.584 = 2.664

So the Ev of the Build is 2.664 $.

Since the largest of all of the above three projects is, 4.032 million $ that is the Expected Value.

Add a comment
Know the answer?
Add Answer to:
Question 9 Use the following decision tree, but update the probabilities as follows: Probability of Small...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • SUI UC value OIP mine the course of action that has the highest expected payoff for...

    SUI UC value OIP mine the course of action that has the highest expected payoff for this decision tree. 5. Determine the cours $1.0 Do nothing Small demand (4) Expand Medium demand (5) Large demand (1) Do nothing Expand Build $1.8 Subcontract $0.7 Do nothing Other use #1 Other use #2 Small demand (4) Expand Medium demand (5) Large demand (1) Do nothing Subcontract Build $1.7 ($0.9) Build Do nothing Other use #1 $1.4 Other use #2 $1.0 Small demand...

  • A) Find the expected monetary value for each of the alternatives (subcontract, expand, and build)...

    a) Find the expected monetary value for each of the alternatives (subcontract, expand, and build) b) Determine the alternative that should be selected in order to maximize the expected monetary value rur uount Kubota US $1.0% Do nothing 1.3 $1.3 $1.5 $16k $1.8 Do nothing Do nothing $0.7 Other use #1 $1.5 Expand Medium demand (5) $1.6 Do nothing $1.6 Subcontract $1.5 $1.7 Do nothing $0.9 $1.4 $1.0 $1.0 $1.1 Other use #1 Small demand (.4) Do nothing nd (5)...

  • Assume that ABC Inc. has hired a marketing research firm that provided additional information regarding next year's demand. Suppose that the probabilities of low and high demand are assessed as follows: P(Low) = 0.3, P(Medium)= 0.3 and P(High) = 0.4.

                        ABC Inc. must make a decision on its current capacity for next year.  Estimated profits (in $000's) based on next year's demand are shown in the table below.Next Year's                         Demand Alternative   Low       Medium        HighExpand        $100       $200         $250Subcontract $50         $120         $125Do Nothing  $40         $50           $ 551). Assume that ABC...

  • A small building contractor has recently experienced two successive years in which work opportunities exceeded the...

    A small building contractor has recently experienced two successive years in which work opportunities exceeded the firm’s capacity. The contractor must now make a decision on capacity for next year. Estimate profits under each of the two possible states of nature are as shown in the table below. (*Profit in $ thousands) Next Year’s Demand Alternative                                          Low                             High          Do nothing                                          $50*                            $60 Expand                                                20                              80 Subcontract                                         40                              70 a. If the contractor...

  • This question refers to an example in the book Production/Operations Management by William J. Stevenson. The...

    This question refers to an example in the book Production/Operations Management by William J. Stevenson. The example involves a capacity-planning problem in which a company must choose to build a small, medium, or large production facility. The payoff obtained will depend on whether future demand is low, moderate, or high, and the payoffs are as given in the following table: Alternatives Small facility Medium facility Large facility Possible Future Demand Low Moderate High $11 $11 $11 8 13 13 -$5...

  • Suppose a manufacturing plant is considering three options for expansion. The first one is to expand...

    Suppose a manufacturing plant is considering three options for expansion. The first one is to expand into a new plant (large), the second to add on third-shift to the daily schedule (medium) and the third to do nothing (small). There are three possibilities for demand. These are high, medium, and low with the probability of .5 (H), .25 (M), .25 (L) of occurring. Suppose that the profits for the expansion plans are as follows (respective to high, medium, low demand)....

  • Suppose a manufacturing plant is considering three options for expansion. The first one is to exp...

    Suppose a manufacturing plant is considering three options for expansion. The first one is to expand into a new plant (large), the second to add on third-shift to the daily schedule (medium), and the third to do nothing (small). There are three possibilities for demand. These are high, medium, and low with the probability of .5 (H), .25 (M), .25 (L) of occurring. Suppose that the profits for the expansion plans are as follows (respective to high, medium, low demand)....

  • Use the probability distribution to find probabilities in parts​ (a) through​ (c). The probability distribution of...

    Use the probability distribution to find probabilities in parts​ (a) through​ (c). The probability distribution of number of dogs per household in a small town Dogs 0 1 2 3 4 5 Households 0.6730.673 0.2010.201 0.0760.076 0.0250.025 0.0170.017 0.0080.008 ​(a) Find the probability of randomly selecting a household that has fewer than two dogs. 0.8740.874   ​(Round to three decimal places as​ needed.) ​(b) Find the probability of randomly selecting a household that has at least one dog. nothing ​ (Round...

  • Use the probability distribution to find probabilities in parts​ (a) through​ (c). The probability distribution of numbe...

    Use the probability distribution to find probabilities in parts​ (a) through​ (c). The probability distribution of number of dogs per household in a small town Dogs 0 1 2 3 4 5 Households Use the probability distribution to find probabilities in parts​ (a) through​ (c). The probability distribution of number of dogs per household in a small town Dogs 0 1 2 3 4 5 Households 0.6780.678 0.1940.194 0.0790.079 0.0270.027 0.0170.017 0.005

  • Expando, Inc. is considering the possibility of building an additional factory that would produce a new...

    Expando, Inc. is considering the possibility of building an additional factory that would produce a new addition to its product line. The company is currently considering two options. The first is a small facility that it could build at a cost of $6 million. If demand for new products is low, the company expects to receive $10 million in discounted revenues (present value of future revenues) with the small facility. On the other hand, if demand is high, it expects...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT