Question

Kindly help me to solve this and show me full working. Godzilla, Inc. expects to manufacture...

Kindly help me to solve this and show me full working.

Godzilla, Inc. expects to manufacture 1,000 mini homes in 2020 to meet the housing demand in City X. Monthly production is expected to range from 60 at the low end to 100 units at the high end. Additional budget information is as follows:

  • Direct materials per unit (variable cost) - $50,000
  • Direct labor per unit (variable cost) - $30,000
  • Manufacturing overhead per unit (variable) - $10,000
  • Depreciation (fixed cost) - $520,000

Prepare a monthly flexible manufacturing budget for the relevant range, using 20 unit increments.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Flexible budget Budget

No of units manufactured 60 80 100
Variable cost
Direct material 3000000 4000000 5000000
Direct labor 1800000 2400000 3000000
Manufacturing overhead 600000 800000 1000000
Total Variable cost 5400000 7200000 9000000
fixed cost
Depreciation 520000 520000 520000
Total Fixed cost 520000 520000 520000
Total Cost 5920000 7720000 9520000
Add a comment
Know the answer?
Add Answer to:
Kindly help me to solve this and show me full working. Godzilla, Inc. expects to manufacture...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Gundy Company expects to produce 1,207,200 units of Product XX in 2020. Monthly production is expected...

    Gundy Company expects to produce 1,207,200 units of Product XX in 2020. Monthly production is expected to range from 76,000 to 118,000 units. Budgeted variable manufacturing costs per unit are direct materials $3, direct labor $7, and overhead $10. Budgeted fixed manufacturing costs per unit for depreciation are $4 and for supervision are $1 Prepare a flexible manufacturing budget for the relevant range value using 21,000 unit increments. (List variable costs before fixed costs.) GUNDY COMPANY Monthly Flexible Manufacturing Budget...

  • Gundy Company expects to produce 1,299,600 units of Product XX in 2017. Monthly production is expected to range from 73...

    Gundy Company expects to produce 1,299,600 units of Product XX in 2017. Monthly production is expected to range from 73,600 to 118,800 units. Budgeted variable manufacturing costs per unit are direct materials $3, direct labor $6, and overhead $9. Budgeted fixed manufacturing costs per unit for depreciation are $6 and for supervision are $2. Prepare a flexible manufacturing budget for the relevant range value using 22,600 unit increments. (List variable costs before fixed costs.) GUNDY COMPANY Monthly Flexible Manufacturing Budget...

  • Gundy Company expects to produce 1,222,800 units of Product XX in 2020. Monthly production is expected to range from 78,...

    Gundy Company expects to produce 1,222,800 units of Product XX in 2020. Monthly production is expected to range from 78,000 to 114,000 units. Budgeted variable manufacturing costs per unit are direct materials $5, direct labor $6, and overhead $9. Budgeted fixed manufacturing costs per unit for depreciation are $6 and for supervision are $3. Prepare a flexible manufacturing budget for the relevant range value using 18,000 unit increments. (List variable costs before fixed costs.) GUNDY COMPANY Monthly Flexible Manufacturing Budget...

  • Gundy Company expects to produce 1,238,400 units of Product XX in 2020. Monthly production is expected...

    Gundy Company expects to produce 1,238,400 units of Product XX in 2020. Monthly production is expected to range from 70,000 to 110,000 units. Budgeted variable manufacturing costs per unit are direct materials $5, direct labor $6, and overhead $9.Budgeted fixed manufacturing costs per unit for depreciation are $6 and for supervision are $2. Prepare a flexible manufacturing budget for the relevant range value using 20,000 unit increments. (List variable costs before fixed costs.) GUNDY COMPANY Monthly Flexible Manufacturing Budget For...

  • Brief Exercise 10-4 Gundy Company expects to produce 1,251,600 units of Product XX in 2020. Monthly...

    Brief Exercise 10-4 Gundy Company expects to produce 1,251,600 units of Product XX in 2020. Monthly production is expected to range from 79,000 to 117,000 units. Budgeted variable manufacturing costs per unit are direct materials $5, direct labor $7, and overhead $11. Budgeted fixed manufacturing costs per unit for depreciation are $6 and for supervision are $1. Prepare a flexible manufacturing budget for the relevant range value using 19,000 unit increments. (List variable costs before fixed costs.) GUNDY COMPANY Monthly...

  • M9-5 (Algo) Preparing a Flexible Budget [LO 9-2] Evanson Company expects to produce 520,000 units of...

    M9-5 (Algo) Preparing a Flexible Budget [LO 9-2] Evanson Company expects to produce 520,000 units of their product during the year. Monthly production is expected to range from 40,000 to 80,000 units. The company has budgeted manufacturing costs per unit to be as follows: $ 9 Direct materials Direct labor Variable manufacturing overhead Fixed manufacturing overhead Prepare a flexible manufacturing budget using 20,000 unit increments. -nces 80,000 Evanson Company Monthly Flexible Manufacturing Budget Activity level Finished units 20,000 40,000 Variable...

  • Gundy Company expects to produce 1,238,400 units of Product XX in 2020. Monthly production is expected...

    Gundy Company expects to produce 1,238,400 units of Product XX in 2020. Monthly production is expected to range from 70,000 to 110,000 units. Budgeted variable manufacturing costs per unit are direct materials $5, direct labor $6, and overhead $9. Budgeted fixed manufacturing costs per unit for depreciation are $6 and for supervision are $2. Prepare a flexible manufacturing budget for the relevant range value using 20,000 unit increments. (List variable costs before fixed costs.)

  • Bridgeport Company expects to produce 1,299,600 units of Product XX in 2017. Monthly production is expected...

    Bridgeport Company expects to produce 1,299,600 units of Product XX in 2017. Monthly production is expected to range from 76,300 to 124,900 units. Budgeted variable manufacturing costs per unit are direct materials $3, direct labor $7, and overhead $10. Budgeted fixed manufacturing costs per unit for depreciation are $4 and for supervision are $2. Prepare a flexible manufacturing budget for the relevant range value using 24,300 unit increments. (List variable costs before fixed costs.)

  • Question 2 View Policies Current Attempt in Progress Gundy Company expects to produce 1.272,000 units of...

    Question 2 View Policies Current Attempt in Progress Gundy Company expects to produce 1.272,000 units of Product XX in 2020. Monthly production is expected to range from 85,000 to 129.000 units. Budgeted variable manufacturing costs per unitare direct materials $3, direct labor $6, and overhead 59. Budgeted fixed manufacturing costs per unit for depreciation are $6 and for supervision are $1 Prepare a flexible manufacturing budget for the relevant range value using 22,000 unit increments. (List variable costs before fixed...

  • Gundy Company expects to produce 1,292,400 units of Product XX in 2020. Monthly production is expected...

    Gundy Company expects to produce 1,292,400 units of Product XX in 2020. Monthly production is expected to range from 70,000 to 110,000 units. Budgeted variable manufacturing costs per unit are direct materials $5, direct labor $7, and overhead $9. Budgeted fixed manufacturing costs per unit for depreciation are $5 and for supervision are $3. Prepare a flexible manufacturing budget for the relevant range value using 20,000 unit increments. (List variable costs before fixed costs.) GUNDY COMPANY Monthly Flexible Manufacturing Budget...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT