Question

Group Ex #5 (Ch 10) A manufacturing company has a pool of 50 labor hours. A...

Group Ex #5 (Ch 10)

A manufacturing company has a pool of 50 labor hours. A customer has requested two products, Product A and Product B, and has requested 15 and 20 of each respectively. It requires 2 hours of labor to produce Product A and 3 hours of labor to produce Product B. The company can obtain up to 50 additional hours of labor if required. In-house labor costs $25 per hour while contracted labor costs $45 per hour.

A- Draw the network flow model that captures this problem.

B-Write out the LP formulation for this problem?

C-Solve this system – the network flow problem. [Provide a screen shot of your Solver solution and/or any Solver Reports you deem necessary.]

D-What is the company’s labor plan to develop the products, A and B, to fulfill the customer’s order?

(f) And, what is the associated cost to the company?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1) Network flow model is following

Supply (labor hours) Demand (labor hours $25 50 Inhouse Labor Product A 15x2 30 $45 $25 50 Contracted labor Product B20x3 -60

2) LP formulation is as follows

Let HA and HB be the number of inhouse labor hours used to produce products A and B respectively

and CA and CB be the number of contracted labor hours used to produce products A and B respectively

Min (HA+HB)*25 + (CA+CB)*45

s.t.

HA+HB <= 50

CA+CB <= 50

HA/2 + CA/2 = 15

HB/3 + CB/3 = 20

HA, HB, CA, CB >= 0

3) Solution of the model using Solver is as follows

F2 Q fx -SUMPRODUCT (B2:E2,$B$8:$E$8) HB св S Solver Parameters 2 3 4 5 6 Cost: Supply of Inhouse labor Supply of Contracted

Formula:

F2 =SUMPRODUCT(B2:E2,$B$8:$E$8)   copy to F2:F6

Solver Answer report is following

Objective Cell (Min Cell Name Original Value Final Value SF$2 Cost: 3050 3050 Variable Cells Cell SB$8 Labor hours to be used

4)

Company's labor plan is such that 50 inhouse labor hours should be used for producing B and 30 and 10 contracted labor hours should be used for production of A and B respectively.

Associated cost to the company = $ 3050

Add a comment
Know the answer?
Add Answer to:
Group Ex #5 (Ch 10) A manufacturing company has a pool of 50 labor hours. A...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • During April, Keenan Company accumulated 520 hours of direct labor costs on Job 50 and 580...

    During April, Keenan Company accumulated 520 hours of direct labor costs on Job 50 and 580 hours on Job 51. The total direct labor was incurred at a rate of $13 per direct labor hour for Job 50 and $17 per direct labor hour for Job 51. Journalize the entry to record the flow of labor costs into production during April.

  • Hello, I need help with the following problem: 1. Multi-period production problem. Formulate the production and...

    Hello, I need help with the following problem: 1. Multi-period production problem. Formulate the production and inventory problem at XXI Company using Excel. See narrative below Solve the problem in Excel XX1 Company Production and Inventory Problem Narrative A company named XX1 has contracted to produce products A and B, over the months of June, July and August. The total production capacity (expressed in hours) varies monthly. The following table provides the basic data for the situation. June July August...

  • Required Information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required Information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,eee Number of machine hours 73,6ee Number of design hours 71,600 Number of batches Estimated Cost Driver Be, evo 8, eae 500 Re 1. red: mpute the activity rate for each activity. 1551fy each activity as facility, product, batch, or unit level. complete this question by...

  • 5. Peter Company has the following pools, drivers and pool rates for its activity-based costing system:...

    5. Peter Company has the following pools, drivers and pool rates for its activity-based costing system: Pool Driver Rate Machining Machine Hours $60 per machine hour Ordering of Parts Number of Orders $180 per order Design Design Hours $600 per design hour Customer Customers $2,200 per customer Other n/a n/a Becca Company placed an order with Peter for 1,800 units of a custom product. The order required $90,000 worth of direct material and $36,000 worth of direct labor. The order...

  • Required: 1. Assume that the company continues to use direct labor-hours as the base for applying...

    Required: 1. Assume that the company continues to use direct labor-hours as the base for applying overhead cost to products. a. Compute the plantwide predetermined overhead rate. b. Compute the unit product cost of each model. 2. Assume that the company decides to use activity-based absorption costing to apply overhead cost to products. a. Compute the activity rate for each activity cost pool and determine the amount of overhead cost that would be applied to each model using the activity-based...

  • The problem said that it "will add 50% to direct labor cost". However, I got a...

    The problem said that it "will add 50% to direct labor cost". However, I got a negative contribution margin of victory product C in my calculation so I was confused. XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: demand for next year ..... selling price per unit ..... direct material cost per unit direct labor cost per unit .. variable...

  • ! Required information Gable Company uses three activity cost pools. Each pool has a cost driver....

    ! Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $416,700 Number of machine hours 93,100 Number of design hours 73,338 Number of batches Estimated Cost Driver 92,600 9,500 510 Required: 1. Compute the activity rate for each activity. 2. Classify each activity as facility, product, batch, or unit level. Complete this question by entering...

  • Units produced Machine-hours Direct labor-hours Direct materials costs Direct labor costs Manufacturing overhead costs Total costs...

    Units produced Machine-hours Direct labor-hours Direct materials costs Direct labor costs Manufacturing overhead costs Total costs Basic 1,100 3,800 3,600 $18,000 64,500 Dominator 360 3,200 2,100 $ 5,650 45,500 Total 1,460 7,000 5,700 $ 23,650 110,000 209,370 $343,020 Tiger Furnishings's CFO believes that a two-stage cost allocation system would give managers better cost information. She asks the company's cost accountant to analyze the accounts and assign overhead costs to two pools: overhead related to direct labor cost and overhead related...

  • Prado Company applies fixed manufacturing overhead costs to products based on direct labor hours. Information for the mo...

    Prado Company applies fixed manufacturing overhead costs to products based on direct labor hours. Information for the month of April appears below. Prado's expected to produce and sell 500 units for the month. Budgeted fixed overhead costs $240,000 Budgeted direct labor hours ÷ 12,000 Standard cost per direct labor hour $ 20 Standard direct labor hours per unit 18 Actual production 520 units Actual fixed overhead costs $210,000 Required: Calculate the fixed overhead spending variance and production volume variance. Clearly...

  • Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information...

    Required information Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Part 2 of 2 136 points Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8.000 500 Suppose that Gable Company manufactures three products, A, B, and C. Information about these products follows: Number of machine hours...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT