Operations Management Job Flow

Student Premier Painters (SPP) has six house painting jobs in a particular neighborhood. The houses vary in size, condition, and painting requirements, but each house must be prepped (cleaned, sanded, and primed) first, before it is painted. The relevant information is given. Johnson’s rule should be used to minimize makespan.

q2..PNG

q2.PNG

Calculate the mean job flow time associated with this sequence.

Calculate the average number of jobs in the system with this sequence.

(Round answer to 2 decimal places, e.g. 1.75.)

0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Operations Management Job Flow
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT