Question

In 2018, the Marion Company purchased land containing a mineral mine for $1,640,000. Additional costs of...

In 2018, the Marion Company purchased land containing a mineral mine for $1,640,000. Additional costs of $564,000 were incurred to develop the mine. Geologists estimated that 600,000 tons of ore would be extracted. After the ore is removed, the land will have a resale value of $104,000.

To aid in the extraction, Marion built various structures and small storage buildings on the site at a cost of $252,000. These structures have a useful life of 10 years. The structures cannot be moved after the ore has been removed and will be left at the site. In addition, new equipment costing $91,000 was purchased and installed at the site. Marion does not plan to move the equipment to another site, but estimates that it can be sold at auction for $7,000 after the mining project is completed.

In 2018, 55,000 tons of ore were extracted and sold. In 2019, the estimate of total tons of ore in the mine was revised from 600,000 to 818,000. During 2019, 91,000 tons were extracted.

Required:
1. Compute depletion and depreciation of the mine and the mining facilities and equipment for 2018 and 2019. Marion uses the units-of-production method to determine depreciation on mining facilities and equipment.
2. Compute the book value of the mineral mine, structures, and equipment as of December 31, 2019.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution 1&2:

Mine:

Cost to depleted for mine = $1,640,000 + $564,000 - $104,000 = $2,100,000

Depletion expense for 2018 = $2,100,000 * 55000/600000 = $192,500

Book value at the end of 2018 = $2,204,000 - $192,500 = $2,011,500

Remaining cost to be depreciated at beginning of 2019 = $2,100,000 - $192,500 = $1,907,500

Depletion expense for 2019 = $1,907,500 * 91000/(818000-55000) = $227,500

Book value at the end of 2019 = $2,011,500 - $227,500 = $1,784,000

Mining facilities:

Cost to depreciated = $252,000

Depreciation expense for 2018 = $252,000 * 55000/600000 = $23,100

Book value at the end of 2018 = $252,000 - $23,100 = $228,900

Remaining cost to be depreciated at beginning of 2019 = $228,900

Depreciation expense for 2019 = $228,900 * 91000/(818000-55000) = $27,300

Book value at the end of 2019 = $228,900 - $27,300 = $201,600

Mining facilities:

Cost to depreciated = $252,000

Depreciation expense for 2018 = $252,000 * 55000/600000 = $23,100

Book value at the end of 2018 = $252,000 - $23,100 = $228,900

Remaining cost to be depreciated at beginning of 2019 = $228,900

Depreciation expense for 2019 = $228,900 * 91000/(818000-55000) = $27,300

Book value at the end of 2019 = $228,900 - $27,300 = $201,600

Equipment:

Cost to depreciated = $91,000 - $7,000 = $84,000

Depreciation expense for 2018 = $84,000 * 55000/600000 = $7,700

Book value at the end of 2018 = $91,000 - $7,700 = $83,300

Remaining cost to be depreciated at beginning of 2019 = $83,300 -$7,000 = $76,300

Depreciation expense for 2019 = $76,300 * 91000/(818000-55000) = $9,100

Book value at the end of 2019 = $83,300 - $9,100 = $74,200

Add a comment
Know the answer?
Add Answer to:
In 2018, the Marion Company purchased land containing a mineral mine for $1,640,000. Additional costs of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2018, the Marion Company purchased land containing a mineral mine for $1,660,000. Additional costs of...

    In 2018, the Marion Company purchased land containing a mineral mine for $1,660,000. Additional costs of $723,000 were incurred to develop the mine. Geologists estimated that 700,000 tons of ore would be extracted. After the ore is removed, the land will have a resale value of $108,000. To aid in the extraction, Marion built various structures and small storage buildings on the site at a cost of $455,000. These structures have a useful life of 10 years. The structures cannot...

  • In 2021, the Marion Company purchased land containing a mineral mine for $1,740,000. Additional costs of...

    In 2021, the Marion Company purchased land containing a mineral mine for $1,740,000. Additional costs of $676,000 were incurred to develop the mine. Geologists estimated that 400,000 tons of ore would be extracted. After the ore is removed, the land will have a resale value of $116,000. To aid in the extraction, Marion built various structures and small storage buildings on the site at a cost of $184,000. These structures have a useful life of 10 years. The structures cannot...

  • In 2021, the Marion Company purchased land containing a mineral mine for $1,450,000. Additional costs of...

    In 2021, the Marion Company purchased land containing a mineral mine for $1,450,000. Additional costs of $547,000 were incurred to develop the mine. Geologists estimated that 370,000 tons of ore would be extracted. After the ore is removed, the land will have a resale value of $110,000. To aid in the extraction, Marion built various structures and small storage buildings on the site at a cost of $133,200. These structures have a useful life of 10 years. The structures cannot...

  • In 2021, the Marion Company purchased land containing a mineral mine for $2,050,000. Additional costs of...

    In 2021, the Marion Company purchased land containing a mineral mine for $2,050,000. Additional costs of $843,000 were incurred to develop the mine. Geologists estimated that 490,000 tons of ore would be extracted. After the ore is removed, the land will have a resale value of $100,000. To aid in the extraction, Marion built various structures and small storage buildings on the site at a cost of $205,800. These structures have a useful life of 10 years. The structures cannot...

  • Problem 11-7 Depletion; change in estimate (L011-3. 11-5) In 2018, the Marion Company purchased and containing...

    Problem 11-7 Depletion; change in estimate (L011-3. 11-5) In 2018, the Marion Company purchased and containing a mineral mine for $1,300,000. Additional costs of $493.000 were incurred to develop the mine Geologists estimated that 340.000 tons of ore would be extracted. After the one is removed, the land will have a Tesale value of $110.000 To aid in the extraction Marion built various structures and small storage buildings on the site at a cost of $117300. These structures have a...

  • Problem 11-13 Depreciation and depletion; change in useful life; asset retirement obligation; Chapters 10 and 11...

    Problem 11-13 Depreciation and depletion; change in useful life; asset retirement obligation; Chapters 10 and 11 [LO11-2, 11-3, 11-5] On May 1, 2018, Hecala Mining entered into an agreement with the state of New Mexico to obtain the rights to operate a mineral mine in New Mexico for $9 million. Additional costs and purchases included the following (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from...

  • On May 1, 2021, Hecala Mining entered into an agreement with the state of New Mexico...

    On May 1, 2021, Hecala Mining entered into an agreement with the state of New Mexico to obtain the rights to operate a mineral mine in New Mexico for $9.2 million. Additional costs and purchases included the following (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Development costs in preparing the mine Mining equipment Construction of various structures on site $2,400,000 146,800...

  • On May 1, 2021, Hecala Mining entered into an agreement with the state of New Mexico...

    On May 1, 2021, Hecala Mining entered into an agreement with the state of New Mexico to obtain the rights to operate a mineral mine in New Mexico for $10.6 million. Additional costs and purchases included the following (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Development costs in preparing the mine $ 3,800,000 Mining equipment 156,200 Construction of various structures on...

  • On May 1, 2021, Hecala Mining entered into an agreement with the state of New Mexico...

    On May 1, 2021, Hecala Mining entered into an agreement with the state of New Mexico to obtain the rights to operate a mineral mine in New Mexico for $11.0 million. Additional costs and purchases included the following (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Development costs in preparing the mine $ 4,200,000 Mining equipment 146,000 Construction of various structures on...

  • On May 1, 2021, Hecala Mining entered into an agreement with the state of New Mexico...

    On May 1, 2021, Hecala Mining entered into an agreement with the state of New Mexico to obtain the rights to operate a mineral mine in New Mexico for $9.5 million. Additional costs and purchases included the following (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Development costs in preparing the mine $ 2,700,000 Mining equipment 122,500 Construction of various structures on...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT