Question
  1. Assume all the gates in Figure 3-18 have a propagation delay of 1 nsec, and all other delays can be ignored. How much time does it takes the AND function to produce a result? How much time does it takes the OR function to produce a result? How much time does it takes the NOT function to produce a result? How much time does it takes the ADDER function to produce a result?

Logical unit Carry in AB INVA A ENA AB -Output ENB Sum Enable lines Fo Full adder F1 Decoder Cam out

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution:

Calculation for the critical path

Logical unit Carry in AB INVA- AB A ut ENA ENB Sum Enable lines Fo Full adder F1 Decoder Cam ot OR gate critical path AND gatNumbs of ates in citical path Time peured 2 - Su - 2ns OR gate Mumber es crlical path in 2. ANDgte Numabe qate m cnicad pathLogical unit Carry in AB INVA- A+ B A Output ENA B ENB Sum Enable lines Fo Full adder F1 Decoder Cam ou carry out criticalThe complete pe sult-ofAdd leperds tout pin The mactmum fine peçiurad casby oud pin is The aduel time eprd lay The ADER ard

Add a comment
Know the answer?
Add Answer to:
Assume all the gates in Figure 3-18 have a propagation delay of 1 nsec, and all...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT