Question

Can you please help with the following? PART 4 Process Costing - Weighted Average General Information...

Can you please help with the following?

PART 4
Process Costing - Weighted Average
General Information
The I See The Light Company has a related company that produces the figurines. They use process costing
in the molding department. The factory overhead is applied at a rate of 50% of direct labor dollars.
The material is added at the beginning of the process. The labor and overhead costs are assumed
to be added uniformly throughout.
Month of January
Selected information for January is presented below. Note that the applied overhead rate was
50% of direct labor costs in the molding department.
Molding Department
Goods in-process as of January 1 were 3,100 figurines at a cost of $33,926.00. Of this amount, $4,526.00 was from
raw materials added, $19,600.00 for labor and $9,800.00 for overhead. These 3,100 figurines were assumed to be
40.00% complete as to labor and overhead.
During January, 24,500 units were started, $39,634.00 of materials and $49,700.00 of labor costs were incurred.
The 7,500 figurines that were in-process at the end of January were assumed to be 40.00% complete to
labor and overhead.
All figurines in January passed inspection.
January
Physical Flow of Units
Work-in-Process - Beginning
Units Started this Period
Units to Account for
Total transferred out {12.01}
Work-in-Process - Ending {12.02}
Total Accounted for
Equivalent Units Material (Round to two places, ##,###.##) {12.03}
Equivalent Units Conversion (Round to two places, ##,###.##) {12.04}
Total cost of Material (Round to two places, ##.###.##) {12.05}
Total cost of Conversion (Round to two places, ##.###.##) {12.06}
Total cost to account for (Round to two places, ##.###.##) {12.07}
Cost per equivalent unit of Material (Round to two places, ###.##) {12.08}
Cost per equivalent unit of Conversion (Round to two places, ###.##) {12.09}
Cost of the ending inventory, material and convesion (Round to two places, $###,###.## ) {12.10}
Cost of the units transferred, material and convesion (Round to two places, $###,###.## ) {12.11}
PART 5
Job Order Costing
To keep records of the actual cost of a special order job, a Job Order Cost System has been developed.
Overhead is applied at the rate of 50% of the direct labor cost.
Job Order Costing Section
On January 1, 20x2, Division S began Job 2407 for the Client, THE BIG CHILDREN STORE. The
job called for 4,000 customized lamps. The following set of transactions occurred from
January 5 until the job was completed:
5-Jan Purchased 4,000 Lamp Kits @ $16.40 per kit.
9-Jan 4,025 sets of Lamp Kits were requisitioned.
17-Jan Payroll of 620 Direct Labor Hours @ $9.55 per hour.
30-Jan Payroll of 670 Direct Labor Hours @ $9.80 per hour.
30-Jan 3,990 lamps were completed and shipped. All materials requisitioned were
used or scrapped, and are a cost of normal processing.
Month End Overhead Information
Actual Variable Manufacturing Overhead $1,161.00
Actual Fixed Manufacturing Overhead $40,873.45
Round to two places, $##.##
Cost of Direct Material Incurred in Manufacturing Job 2407
{13.01}
Cost of Direct Labor Incurred in Manufacturing Job 2407
{13.02}
Cost of Manufacturing Overhead Applied to Job 2407
{13.03}
Cost of manufacturing one lamp
{13.04}
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution Part 4:

Reconciliation of Physical units
Particulars Physical Units Particulars Physical Units
Beginning units 3100 Unit Completed 20100
Unit started 24500 Ending Units 7500
Total Units 27600 Total Units 27600
Computation of Equivalent unit of Production - Weighted Average (Molding Department)
Particulars Physical Units Material Conversion (Labor + Overhead)
Unit completed & Transferred out 20100 20100 20100
Closing WIP: 7500
Material (100%) 7500
Conversion (40%) 3000
Equivalent units of production 27600 27600 23100
Computation of Cost per equivalent unit of Production - Weighted Average (Molding Department)
Particulars Material Conversion (Labor + Overhead)
Opening WIP $4,526.00 $29,400.00
Cost Added during June $39,634.00 $74,550.00
Total cost to be accounted for $44,160.00 $103,950.00
Equivalent units of production 27600 23100
Cost per Equivalent unit $1.60 $4.50
Computation of Cost of ending WIP and units completed & transferred out - Weighted Average (Molding Department)
Particulars Material Conversion (Labor + Overhead) Total
Equivalent unit of Ending WIP 7500 3000
Cost per equivalent unit $1.60 $4.50
Cost of Ending WIP (Equivalent unit * Cost per equivalent unit) $12,000 $13,500 $25,500
Units completed and transferred 20100 20100
Cost of units completed & Transferred (Unit completed * cost per equivalent unit) $32,160 $90,450 $122,610
Cost reconciliation - Weighted Average - Molding Department
Particulars Amount
Costs to be accounted for:
Cost of beginning WIP inventory $33,926.00
Cost added to production $114,184.00
Total Cost to be accounted for $148,110.00
Costs accounted for as follows:
Cost of unit transferred out $122,610
Ending WIP:
Material $12,000
Converison $13,500
Total cost accounted for $148,110

Note: As multiple questions are posted, i have answered first question as per HomeworkLib policy, kindly post separate question for answer of remaining.

Add a comment
Know the answer?
Add Answer to:
Can you please help with the following? PART 4 Process Costing - Weighted Average General Information...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • PART 5 Job Order Costing To keep records of the actual cost of a special order...

    PART 5 Job Order Costing To keep records of the actual cost of a special order icb, a Job Order Cost System has been developed Overhead is applied at the rate of 50% of the direct labor cost. Job Order Costing Section On January 1, 20x2. Division S began Job 2407 for the client. THE BIG CHILDREN STORE. The job called for 4,000 customized lamps. The following set of transactions occurred from January 5 until the job was completed: 5-Jan...

  • Job Order Costing To keep records of the actual cost of a special order job, a...

    Job Order Costing To keep records of the actual cost of a special order job, a Job Order Cost System has been developed. Overhead is applied at the rate of 50% of the direct labor cost. Job Order Costing Section On January 1, 20x2, Division S began Job 2407 for the Client, THE BIG CHILDREN STORE. The job called for 4,000 customized lamps. The following set of transactions occurred from January 5 until the job was completed: 5-Jan Purchased 4,200...

  • To keep records of the actual cost of a special order job, a Job Order Cost...

    To keep records of the actual cost of a special order job, a Job Order Cost System has been developed. Overhead is applied at the rate of 50% of the direct labor cost. Job Order Costing Section On January 1, 20x2, Division S began Job 2407 for the Client, THE BIG CHILDREN STORE. The job called for 4,000 customized lamps. The following set of transactions occurred from January 5 until the job was completed: 5-Jan Purchased 4,225 Lamp Kits @...

  • Answer the yellow boxes pay attention to correct rounding: to 4 PART 4 Process Costing -...

    Answer the yellow boxes pay attention to correct rounding: to 4 PART 4 Process Costing - Weighted Average 8 General Information 10 19 20 21 The See The Light Company has a related company that produces the figurines. They use process costing in the molding department. The factory overhead is applied at a rate of 50% of direct labor dollars. The material is added at the beginning of the process. The labor and overhead costs are assumed to be added...

  • PART 6 Standard Job Order Costing Variance Analys is Special order lamps are manufactured in division S. Because of the...

    PART 6 Standard Job Order Costing Variance Analys is Special order lamps are manufactured in division S. Because of the precise nature of the process a standard cost system has been developed. The following standards are used for the special orders: Standards $16.000000 per lamp 2.400000 per lamp (4 lamps/hr.) 0.250000 per lamp (4 lamps/hr.) 10.000000 per lamp S 28.650000 Lamp Kits Direct Labor Variable Overhead *Fixed Overhead Total *Fixed overhead is based on expected production of 4,014 customized each...

  • F G H Variance Analysis 12 Special order lamps are manufactured in division S. Because of...

    F G H Variance Analysis 12 Special order lamps are manufactured in division S. Because of the precise nature of the process a 19 standard cost system has been developed. The following standards are used for the special orders: 20 21 . Standards Lamp Kits Direct Labor Variable Overhead * Fixed Overhead Total $ 16.000000 per lamp 2.400000 per lamp (4 lamps/hr.) 0.250000 per lamp (4 lamps/hr.) 10.000000 per lamp $ 28.650000 33 34 41 42 ** Fixed overhead is...

  • Note: Show favorable variances as negative numbers What was the variable overhead efficiency variance ? What...

    Note: Show favorable variances as negative numbers What was the variable overhead efficiency variance ? What was the variable OH spending variance ? What is the fixed OH volume (denominator) variance? What is the fixed OH spending variance? F G H Variance Analysis 12 Special order lamps are manufactured in division S. Because of the precise nature of the process a 19 standard cost system has been developed. The following standards are used for the special orders: 20 21 ....

  • Wyle Company uses the weighted-average method in its process costing system. The following information was available...

    Wyle Company uses the weighted-average method in its process costing system. The following information was available for one of its processing departments: • The beginning work in process inventory consisted of 16,000 units, which were 75% complete with respect to conversion costs. • The department converted the equivalent of 59,000 units of production during the current month. • A total of 50,000 units were completed and transferred out of that department during the current month. • The ending work in...

  • Kansas Supplies is a manufacturer of plastic parts that uses the weighted-average process costing method to...

    Kansas Supplies is a manufacturer of plastic parts that uses the weighted-average process costing method to account for costs of production. It produces parts in three separate departments: Molding, Assembling, and Packaging. The following information was obtained for the Assembling Department for the month of April. Work in process on April 1 had 115,000 units made up of the following: Amount Degree of Completion Prior department costs transferred in from the Molding Department $ 165,600 100 % Costs added by...

  • Kansas Supplies is a manufacturer of plastic parts that uses the weighted-average process costing method to...

    Kansas Supplies is a manufacturer of plastic parts that uses the weighted-average process costing method to account for costs of production. It produces parts in three separate departments: Molding, Assembling, and Packaging. The following information was obtained for the Assembling Department for the month of April. Work in process on April 1 had 103,000 units made up of the following. Amount Degree of Completion Prior department costs transferred in from the Molding Department $ 135,960 100 % Costs added by...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT