The learning curve equation is interpreped as follows:
YN = Y1 * Nb
Where,
YN = Time required to assemble the N-th part
Y1 = Time required to assemble the first part = 89
minutes in this case.
b = Learning coefficient = LN(r) / LN(2) with r = learning rate =
0.93 in this case.
So,
b = LN(0.93) / LN(2) = -0.1047
And,
Y60 = 89 * 60-0.1047 = 57.97 minutes.
So, from the 60th unit onward, each unit will take 58 minutes to assemble.
The other consideration is the recession itself. Note that during the recession, the labor market will remain flooded with skilled personnel who will be seeking jobs. In other words, the supply of skilled labor will be abundant. In this time, the company can hire the most skilled people from the labor market at a relatively low wage rate. This will cause the learning to be conducted in a much faster rate leading to a competitive advantage for the company in the market.