Question

A project has the following expected cash flows: Year 0 Year 1 Year 2 Year 3...

A project has the following expected cash flows:

Year 0

Year 1

Year 2

Year 3

($1,480)

$640

$250

$300

Assume the risk-adjusted discount rate (k)(k) is 7.8%. Based on the IRR rule, should you accept or reject this project? Use Excel or a financial calculator.

  1. Cannot be determined.
  2. No, the project should be rejected.
  3. Yes, the project should be accepted.
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Internal rate of return is calculated using a financial calculator by inputting the below:

  • Press the CF button.
  • CF0= -$480. It is entered with a negative sign since it is a cash outflow.
  • Cash flow for each year should be entered.
  • Press Enter and down arrow after inputting each cash flow.
  • After entering the last cash flow cash flow, press the IRR and CPT button to get the IRR of the project.

The IRR of the project is -11.66%.

Therefore, the project should be rejected since it has a negative internal rate of return.

Hence, the answer is option b.

In case of any query, kindly comment on the solution.

Add a comment
Know the answer?
Add Answer to:
A project has the following expected cash flows: Year 0 Year 1 Year 2 Year 3...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Suppose your firm is considering investing in a project with the cash flows shown below, that...

    Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 14 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively. Time Cash Flow 0 -960 1 160 2 440 3 640 4 640 5 240 6 640 Use the payback decision rule to evaluate this project; should it be accepted or...

  • Suppose your firm is considering investing in a project with the cash flows shown below, that...

    Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively Time Cash Flow 0 1 2 3 4 5 6 -1,150 30570770770 370770 Use the NPV decision rule to evaluate this project, should it be accepted or rejected? Multiple Choice 0...

  • Suppose your firm is considering investing in a project with the cash flows shown below, that...

    Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively Time 0 1 4 5 6 Cash Flow -1,150 30 570 770 770 370 770 Use the discounted payback decision rule to evaluate this project; should it be accepted or rejected?...

  • Suppose your firm is considering investing in a project with the cash flows shown below, that...

    Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 10 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively. Time 0 1 2 3 4 5 6 Cash Flow -1,050 150 450 650 650 250 650 Use the discounted payback decision rule to evaluate this project; should it be accepted...

  • Suppose your firm is considering investing in a project with the cash flows shown below, that...

    Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 10 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively.   Time 0 1 2 3 4 5 6   Cash Flow -1,070 100 500 700 700 300 700 Use the discounted payback decision rule to evaluate this project; should it be accepted...

  • 4. Lepton Industries has a project with the following projected cash flows: Initial Cost, Year 0:...

    4. Lepton Industries has a project with the following projected cash flows: Initial Cost, Year 0: $468,000 Cash flow year one: $135,000 Cash flow year two: $240,000 Cash flow year three: $185,000 Cash flow year four: $135,000 Plot the NPV profile of this project in Excel. Start with discount rate equal to zero and increase the discount rate by 2% increments until discount rate equal to 30%. For what discount rates would Lepton accept this project? For what discount rates...

  • 3. You are considering two mutually exclusive projects with the following cash flows. Which project(s) should...

    3. You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent? Year Project A Project B -$80,000 -$80,000 31,000 31,000 0 31,000 110,000 A. accept project A as it always has the higher NPV B. accept project B as it always has the higher NPV C. accept A at 8.5 percent and B at 13 percent D. accept...

  • An investment has the following cash flows. Should the project be accepted if it has been...

    An investment has the following cash flows. Should the project be accepted if it has been assigned a required return of 14 percent? why or why not? Financial calculator is appropriate here. Year Cash flows -$30,000 $8400 $13,900 $18,600 0 1 2 3 A. No, the IRR exceeds the required return by about 1.08 percent OB. No the IRR is less that the required return by about 0.97 percent C. Yes, the IRR exceeds the required return by about 1.08...

  • Vital Silence, Inc., has a project with the following cash flows:     Year Cash Flow 0...

    Vital Silence, Inc., has a project with the following cash flows:     Year Cash Flow 0 –$ 27,400 1 11,400 2 14,400 3 10,400    The required return is 16 percent. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)   IRR % Should the firm accept the project? Accept Reject

  • Your company has a project available with the following cash flows: Year. Cash Flow 0. $80,200...

    Your company has a project available with the following cash flows: Year. Cash Flow 0. $80,200 1 21,950 2. 25,900 3. 31,700 4. 26,450 5. 20,700 If the required return is 16 percent, should the project be accepted based on the IRR? A. No, because the IRR is 17.75 Percent B. Yes, because the IRR is 18.90 Percent C. No, because the IRR is 18.90 Percent D. Yes, because the IRR is 17.45 Percent E. Yes, because the IRR is...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT