We need to calculate the NPV's of the projects:
Year | A | B | ||
0 | $ -82,000.00 | $ -82,000.00 | ||
1 | $ 34,000.00 | $ - | ||
2 | $ 34,000.00 | $ - | ||
3 | $ 34,000.00 | $ 1,15,000.00 | ||
NPV @ 11.7 | $ 85.10 | $ 516.03 | ||
NPV @ 13.5 | $ -2,397.49 | $ -3,347.91 |
As we can see that both NPV are negative at 13.5% and B has a higher NPV at 11.7%, we shall accept B at 11.7% and neithe at 13.5%.
The excel scrrenshot is being provided for better
understanding:
Projects A and B are mutually exclusive and have an initial cost of $82,000 each. Project...
STION 25 Your company is reviewing a project with estimated labor costs of 515 per unit, estimated raw material costs of $45 a unit, and estimated fixed costs of $25,000 a month. Sales are projected at 15,000 units, 14 percent, over the one-year life of the project. Cost estimates are accurate within a range of +2 percent. What are the total variable costs for the best-case scenario? O A $864,440 OB. 5917,280 OC. $876,716 OD. $626,320 E. 5993,720 QUESTION 26...
You are comparing two mutually exclusive projects. Both projects have an initial cost of $43,500 . Project A has cash inflows of $24,500 , $21,500 , and $18,500 over the next 3 years, respectively. Project B has cash inflows of $13,500 , $16,900 and $39,500 over the next 3 years. What is the crossover rate for Projects A and B? 19.54 percent 20.56 percent 20.30 percent 18.83 percent
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. Time: 1 2 3 14,000 34,000 Project A Cash Flow 24,000 5,000 24,000 Project B Cash Flow -34,000 14,000 54,000 Use the NPV decision rule to evaluate these projects;...
Projects A and B are mutually exclusive and both have an initial cost of $3,000. Annual Cash flows are following the table. What is the crossover rate (i.e. At what discount rate would the company be indifferent between these two projects)? CFs CFs Year Project A Project B 0 -3,000 -3,000 1 500 2,000 2 500 1,000 3 1,500 600 4 2,000 500 A. 6.33 percent B. 14.25 percent C. 18.82 percent D. 7.99 percent E. 9.17 percent
We have two independent and mutually exclusive projects, A and B. Project A requires an initial investment of $1000, and will yield $500 of cash inflows for the next three years. Project B requires an initial investment of $3,500, and will yield $1,000 of cash inflows for the next five years. The required return on both projects is 10%. The NPV of Project A is 243.43 The NPV of Project B is 291.00 What is the problem with using the...
3. You are considering two mutually exclusive projects with the following cash flows. Which project(s) should you accept if the discount rate is 8.5 percent? What if the discount rate is 13 percent? Year Project A Project B -$80,000 -$80,000 31,000 31,000 0 31,000 110,000 A. accept project A as it always has the higher NPV B. accept project B as it always has the higher NPV C. accept A at 8.5 percent and B at 13 percent D. accept...
Novell, Inc., has the following mutually exclusive projects. Year Project A Project B 0 –$21,000 –$24,000 1 12,500 13,500 2 9,000 10,000 3 3,000 9,000 a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) a-2. If the company's payback period is two years, which, if either, of these projects should be chosen? Project A Project B...
Novell, Inc., has the following mutually exclusive projects. Year Project A Project B 0 –$16,000 –$19,000 1 10,000 11,000 2 6,500 7,500 3 2,500 6,500 a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) a-2. If the company's payback period is two years, which, if either, of these projects should be chosen? Project A Project...
Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 11 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively. 0 Time: 43,000 Project A 33,000 23,000 Flow Project B 43,000 23,000 33,000 63,000 Cash Flow Use the discounted payback decision rule to evaluate these projects; which one(s) should...
We have two independent and mutually exclusive projects, A and B. Project A requires an initial investment of $1000, and will yield $500 of cash inflows for the next three years. Project B requires an initial investment of $3,500, and will yield $1,000 of cash inflows for the next five years. The required return on both projects is 10% What is the real rate of return based on the exact Fisher equation? 1 + R = (1+r)x (1+h) 1+ .10...