Question

Software Engineering

Software Engineering

A freight forwarding company will develop a tracking system application that can provide convenience for consumers in sending goods to various locations. Some of the conveniences of this application are Consumers can send goods with a home pickup system so that consumers just make an order for delivery of goods, then the goods will be picked up and delivered to the destination location.Consumers can check the position of the goods that are on the way with their smartphone as well as the ease of making payments using various online payment systems. In addition, the application can also be used by companies to track vehicles used for shipping goods with real time information on the position, condition of the vehicle, driver's condition and information on the goods being transported.Based on thiscase,

Answer the following questions:

Using Function Point analysis, calculate the function points for the completion of the application development project and identify the activities carried out for the development of this application in the form of WBS (work breakdown structure).


0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

The most widely used standard software size metric throughout the industry
is Function Points.
Capers Jones of Software Productivity Research refers to the use of lines
of code for measurement as professional malpractice.
Function Points are now an ISO/IEC standard. (20926 dates: 11/03)
Function Points were first developed in 1979.
Statistical analysis has demonstrated the integrity of Function Point
counting by trained counters.
Function Point counting incorporates the following principles:
• count all the functionality provided to the customer
• count only the functionality provided to the customer
• counting must be independent of technology
A CFPS is a Certified Function Point Specialist (3-part exam) administered
by IFPUG.

According to Capers Jones, Function Point usage reduces the risk of:
• project termination,
• litigation for breach of contract,
• unstable requirements,
• poor quality, and
• cost and schedule overruns
Function Points are calculated by counting screens, reports, queries, and
files / database tables / objects. These are known in FP parlance as:
• External Inputs,
• External Outputs,
• External Inquiries,
• Internal Logical Files, and
• External Logical Files.
According to Capers Jones projects with function point analysis:
• have less scope creep
• have about 15% lower cost overruns
• have about 25% fewer schedule slips
• save between $25 and $75 per function point


answered by: Dr.E
Add a comment
Know the answer?
Add Answer to:
Software Engineering
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT