Question

Under exponential smoothing, if we want forecasts to be very responsive to recent demand, the value...

Under exponential smoothing, if we want forecasts to be very responsive to recent demand, the value of alpha should be: Small Very small Large Very large Zero

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Large

Under exponential smoothing, if we want forecasts to be very responsive to recent demand, the value of alpha should be large

Thanks

Add a comment
Know the answer?
Add Answer to:
Under exponential smoothing, if we want forecasts to be very responsive to recent demand, the value...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The greek letter α ("alpha") in the The greek letter α ("alpha") in the exponential smoothing...

    The greek letter α ("alpha") in the The greek letter α ("alpha") in the exponential smoothing formula can be any value between -10 and 10 O True O False References True / False The greek letter a ("alpha' in the.. Required information 1000 points "Ft" stands for which thing? "Ft" stands for which thing? O ecast for period t ie output for period t O ecast for period 1-1 。ae response for period t-1 Exponential smoothing takes which.. Exponential smoothing...

  • In a simple exponential smoothing model the manager would prefer a large value of ɑ if...

    In a simple exponential smoothing model the manager would prefer a large value of ɑ if he/she wants to respond well to a system characterized by a low level of random behavior but often subjected to a real change in the demand? T or F ...Exponential smoothing assumes that past data is more indicative of the future than the most recent occurrence? ...T or F Subjective forecasting methods should mostly be used for long-term forecast horizons? T or F

  • Assume week 10 actual demand for each product is shown below. Create an exponential smoothing forecasts...

    Assume week 10 actual demand for each product is shown below. Create an exponential smoothing forecasts for week 11 each product. Product X Product Y Product Z Week Historical Demand Week Historical Demand Week Historical Demand 10 $      3,800 10 $      4,100 10 $      4,800 alpha = .7 Product X Product Y Product Z Week Historical Demand Week Historical Demand Week Historical Demand 1 5000 1 $      7,500 1 $      5,100 2 4800 2 $      4,800 2 $      4,700 3...

  • Exercise # 1-0M6322-week 4-Forecasting using Exponential Smoothing The first five periods of demand data are shown...

    Exercise # 1-0M6322-week 4-Forecasting using Exponential Smoothing The first five periods of demand data are shown in the following table Let the smoothing coefficient, alpha, equal 0.2.Compute the exponentially smoothed forecasts for periods one through four Initialize the procedure with a forecast value for period one of 37 Period Aggregate Demand Forecast demand 38 42 40 36 42 37 Determine the Running Sum of Forecast Errors (RSFE), the Mean Absolute Deviation, MADt Land the Tracking Signal(TS) at the end of...

  • Predict Inc., is using a simple exponential smoothing model to forecast their monthly sales but they...

    Predict Inc., is using a simple exponential smoothing model to forecast their monthly sales but they are not sure of the best alpha value to use. They ran some computerized forecasts with different alpha values and reported the following. What alpha value should they use? alpha 0.15 0.20 0.25 0.30 0.35 0.40 0.45 0.50 MAD 18.4 14.7 13.2 16.2 15.3 11.7 10.2 12.5 Group of answer choices 0.45 0.15 0.2 0.35 0.5

  • Two experienced managers at Wilson Boat Inc. are resisting the introduction of a computerized exponential smoothing...

    Two experienced managers at Wilson Boat Inc. are resisting the introduction of a computerized exponential smoothing system, claiming that their judgmental forecasts are much better than any computer could do. Their past record of predictions is as follows: Week Actual Demand Manager's Forecast 1 3,800 4,400 2 4,100 4,800 3 4,300 3,700 4 3,100 3,800 5 3,900 3,500 6 4,500 3,500 7 5,700 4,900 8 4,000 4,700 9 4,500 3,500 10 4,900 5,400 How would the manager’s forecast compare to...

  • Consider the following data. We want to monitor the forecasts. Period Demand Forecasts 1 52 --...

    Consider the following data. We want to monitor the forecasts. Period Demand Forecasts 1 52 -- 2 62 59 3 59 58 4 53 65 5 58 66 We want to calculate the UCL and the LCL for the appropriate control chart to monitor the magnitude of errors. Answer the following related questions: Below fill in the blanks (errors of periods 2 through 5). Period Errors 1 2 3 4 5 Calculate the overall MSE to determine if the errors...

  • 6.Use Exponential smoothing forecasts with alpha of 0.1, 0.2, ..., 0.9 to predict March 2019 demand....

    6.Use Exponential smoothing forecasts with alpha of 0.1, 0.2, ..., 0.9 to predict March 2019 demand. Identify the value of alpha that results in the lowest MAD. 7.Find the monthly seasonal indices for the demand values using Simple Average (SA) method. Find the de-seasonalized demand values by dividing monthly demand by corresponding seasonal indices. 8.Use regression to perform trend analysis on the de-seasonalized demand values. Is trend analysis suitable for this data? Find MAD and explain the Excel Regression output...

  • Examples 1,2,3 1. Beyond Tea Inc. wants to forecast sales of its menthol green tea. The...

    Examples 1,2,3 1. Beyond Tea Inc. wants to forecast sales of its menthol green tea. The company is considering either using a simple mean or a three-period moving average to forecast monthly sales. Given sales data for the past 10 months use both forecasting methods to forecast periods 7 to 10 and then evaluate each. Which method should they use? Use the selected method to make a forecast for month 11. (Show all calculations .... Please read Examples1, 2, 3...

  • 1. Facilities planning refers to: A. Medium-range capacity decisions B. Have no impact on other c...

    1. Facilities planning refers to: A. Medium-range capacity decisions B. Have no impact on other capacity decisions C. Are long-term in nature. D. Require planning for one year or less 2. Under exponential smoothing, if we want the forecast for the next period to be closer to current period actual demand, the value of alpha (a) should be: A. Large (close to 1.0) B. Small (close to zero) C. Zero D. The value of alpha will have no impact on...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT