Question

The Pullman​ Mfg., Inc.​ three-station work cell illustrated in the figure below has two machines at...

The Pullman​ Mfg., Inc.​ three-station work cell illustrated in the figure below has two machines at station 1 in parallel.​ (The product needs to go through only one of the two machines before proceeding to station​ 2.)

Station 1Machine AStation 1Machine BStation 2Station 320 min/unit20 min/unit12 min/unit3 min/unit

The​ manager, Ms.​ Hartley, has asked you to evaluate the system if she adds a parallel machine at station

2.

​a) The throughput time of the new work cell is

35

minutes ​(enter your response as a whole​ number).

​b) The bottleneck time of the new work cell is

10

minutes per unit ​(enter your response as a whole​ number).

​c) If the firm operates

9

hours per​ day, 6 days per​ week, the weekly capacity of the work cell with the second machine at workstation

2

is

324

units​ (enter your response as a whole​ number).

​d) If the firm operates

9

hours per​ day, 6 days per​ week, the weekly capacity of the work cell without the second machine at workstation

2

is

units​ (enter your response as a whole​ number

0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Station 1:Machine A

20 min/unit

Station 2

Station 3

Station 1:Machine B

12 min/unit

3 min/unit

20 min/unit

2. The​ manager, Ms.​ Hartley, has asked you to evaluate the system if she adds a parallel machine at station

​a) The throughput time of the new work cell is 35 minutes ​(enter your response as a whole​ number).

Throughput Time = 20Min+12Min+3Min = 35Min

​b) The bottleneck time of the new work cell is 10 minutes per unit ​(enter your response as a whole​ number).

Bottleneck Time = 20Min/2 = 10Min at station 1

​c) If the firm operates 9 hours per​ day, 6 days per​ week, the weekly capacity of the work cell with the second machine at workstation 2 is 324 units​ (enter your response as a whole​ number).

Weekly capacity = (54hours*60Min/Hr)/10Min per units(Bottleneck time) = 324 Units

​d) If the firm operates 9 hours per​ day, 6 days per​ week, the weekly capacity of the work cell without the second machine at workstation 2 is units​ (enter your response as a whole​ number

Weekly capacity = (54hours*60Min/Hr)/12Min per units(Bottleneck time) = 270 Units

Add a comment
Know the answer?
Add Answer to:
The Pullman​ Mfg., Inc.​ three-station work cell illustrated in the figure below has two machines at...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT