Question

The table below provides the time stamps for the 8 people who called a reservation desk...

The table below provides the time stamps for the 8 people who called a reservation desk for a ferry service between 8:00 am and 8:20 am. Based on the data in the table, what is the flow rate of callers?

Caller Time in Time out
1 8:01 8:05
2 8:02 8:07
3 8:06 8:08
4 8:09 8:12
5 8:10 8:15
6 8:12 8:20
7 8:16 8:19
8 8:17 8:19
1 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1

Answer: Flow rate is 0.4 callers per minute

Explanation: flow rate = average rate of serving customers per hour= total no. of callers / time taken= 8 / 20 mins= 0.4 callers per minute or 24 callers per hour.

Add a comment
Know the answer?
Add Answer to:
The table below provides the time stamps for the 8 people who called a reservation desk...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT