Cost of quality control system = $28,160
Maintenance fee for 5 years = $1,561 while it rises by $364 every year till year 13
Rate of Interest = 7%
Present value is calculated as: [Cash Flow / (1 + Rate of Interest) ^ Year]
Year | Cost | Present Value of Cost |
1 | 1561 | 1458.88 |
2 | 1561 | 1363.44 |
3 | 1561 | 1274.24 |
4 | 1561 | 1190.88 |
5 | 1561 | 1112.97 |
6 | 1925 | 1282.71 |
7 | 2289 | 1425.47 |
8 | 2653 | 1544.07 |
9 | 3017 | 1641.05 |
10 | 3381 | 1718.73 |
11 | 3745 | 1779.22 |
12 | 4109 | 1824.45 |
13 | 4473 | 1856.14 |
19472.24 |
Total present worth value = Cost of system - Sum of Present value Maintenance cost = $28,160 - $19,472.24 = $8,687.76
A company purchased a quality control system for $ 28,160 which requires $ 1,561 per year...
Moving to another question will save this response. Question 1 of 4 Question 1 10 points A company purchased a quality control system for $39.489 which requires $7,660 per year maintenance fees for the first 5 years, after which the maintenance fees will increase by 12% per year for the upcoming 7 years Determine the equivalent total present worth value of preached system during the 12 years operation at 15% per year Moving to another question will save this response....
A plant purchased a chemical process system for $14,404, where its operating cost per year is 53,701 for the first 6 years, there they the upcoming 8 years. Determine the equivalent total future worth of the system for 14 years operation at the interiery
A company is thinking of installing a computer-process control system in one of its plants. The plant is used about 40%of the time (or 3,500 operating hours per year) to produce a proprietary product. During the remaining 60% of the time, it is used to produce other specialty products. Annual production of the proprietary product amounts to 30,000 units and sell for $15 per unit. The proposed computer-process control system will cost $650,000 and is expected to provide the following...
A small company heats its building and will spend $8938 in year 1 on natural gas for this purpose. Cost increases of natural gas are expected to be 9% per year starting year 2. Their maintenance on the gas furnace is going to be $391 in the first year and this expense is expected to increase by 15% per year starting year 2. If the planning horizon is 13 years, what is the total annual equivalent expense for operating and...
QUESTION 15 Initial maintenance costs for a particular piece of construction equipment are $3,000 per year. These costs are expected to increase by $1,000 per year during the equipment's 5-year lifespan. Using an interest rate of 8 percent compounded annually, determine the present worth equivalent for the maintenance costs. CA. $4,650 B.$7.372 C. $11.978 D.$19.351
Question 9 8 points Save Ans A healthcare group has purchased diagnostic medical imaging systems for an annual payment of $ 80,000 at the end of each year for 8 years. For the maintenance service, starting at the end of year 2, the payment will be increased by $5000 each year. Assume an interest rate of 10%. Match the closest correct answers for the below questions: A. I$95,020 What is the present worth of base amount? B. 1580,144 # What...
10.3 You are considering constructing a luxury apartment building project that requires an investment f $15.500,000, which comprises $12,000,000 for the building and $3,500,000 for land. The building has 50 You expect the maintenance cost for the apart- ment building to be $350,000 the first year and 400.000 the second year, after which it will continue to increase by $50,000 in subsequent years. The cost o hire a manager for the building is estimated to be $85,000 per year. After...
Question 1The HalX computer system cost $194,586. It will allow the company to save $89,837 per year. It will cost $22,588 per year to run. The system has a lifespan of 6 years. Using a MARR of 5% interest, what is the annual worth of this system?Question 2 Pacific Consolidated just bought a new building for $338,064. The utilities to run the building will be $8,981 per year. The company anticipates it will be able to collect $38,155 each year by...
(6) A municipal water authority is considering the installation of a new water system. Two options are being considered. The first option is a steel pipeline with an installation cost of $225 million. Annual maintenance and pumping costs begin at $15 million and increase by $1.0 million per year. The second option is a gravity fed concrete canal with an installation cost of $400 million. Annual maintenance costs begin at $0.5 million and increase by $0.4 million per year. If...
Pittsburgh Custom Products (PCP) purchased a new machine for ram-cambering large I beams. PCP expects to bend 55 beams at S3,000 per beam in each of the first 3 years, after which it expects to bend 100 beams per year at $2,700 per beam through year 11 If the company's minimum attractive rate of return is 16% per year, what is the present worth of the expected revenue? The present worth of the expected revenue is S