Question

16. As the cost of capital increases A fewer projects are accepted B. more projects are accepted. C. project selection remain
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer 16:
Fewer projects are accepted because NPV of fewer projects will be positive when we discount future values of projects using higher cost of capital

Answer 17:
Perpetuity

Answer 18:
Less risky the firm's financial position

Answer 19:
Relate balance sheet assets to income statement sales

Answer 20:
Have long term effects on a firm

Add a comment
Know the answer?
Add Answer to:
16. As the cost of capital increases A fewer projects are accepted B. more projects are...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 29. If a firm applies its overall cost of capital to all its proposed projects, then...

    29. If a firm applies its overall cost of capital to all its proposed projects, then the divisions within the firm will tend to A) receive more B) avoid risky projects so that they will receive more funding. C) become less risky over time based on the projects that are accepted. D) have equal probabilities of receiving funding for their projects. . E) propose less risky projects than if separate discount rates were applied funding if they represent the riskiest...

  • If the projects were independent, which project(s) would be accepted? a) Neither b) Project A c)...

    If the projects were independent, which project(s) would be accepted? a) Neither b) Project A c) Project B d) Project A and B If the projects were mutually exclusive, which project(s) would be accepted? a)Neither b) Project A c) Project B d) Project A and B Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line...

  • Апаlysis OPTIMAL CAPITAL BUDGET Marble Construction estimates that its WACC is 10 % if equity comes...

    Апаlysis OPTIMAL CAPITAL BUDGET Marble Construction estimates that its WACC is 10 % if equity comes from retained earnings. However, if the company issues new stock to raise new equity, it estimates that its WACC will rise to 10.8%. The company believes that it will exhaust its retained earnings at $2,500,000 of capital due to the number of highly profitable projects available to the firm and its limited earmings. The company is considering the following seven investment projects: Project Size...

  • Ch 12: End-of-Chapter Problems - Cash Flow Estimation and Risk Analysis OPTIMAL CAPITAL BUDGET Marble Construction...

    Ch 12: End-of-Chapter Problems - Cash Flow Estimation and Risk Analysis OPTIMAL CAPITAL BUDGET Marble Construction estimates that its WACC is 10% if equity comes from retained earnings. However, if the company issues new stock to raise new equity, it estimates that its WACC will rise to 10.8%. The company believes that it will exhaust its retained earnings at $2,500,000 of capital due to the number of highly profitable projects available to the firm and its limited earnings. The company...

  • Hampton Manufacturing estimates that its WACC is 12%. The company is considering the following seven investment...

    Hampton Manufacturing estimates that its WACC is 12%. The company is considering the following seven investment projects: Project Size IRR $650,000 13.6% 13.1 В 1,050,000 12,5 1,050,000 C D. 1,200,000 12.3 600,000 E 12.2 F 600,000 11.6 650,000 11.5 a. Assume that each of these projects is independent and that each is just as risky as the firm's existing assets. Which set of projects should be accepted? -Select Project A -Select Project B -Select Project C Project D -Select Project...

  • 10-7: Composite, or Weighted Average, Cost of Capital, WACC WACC Midwest Electric Company (MEC) uses only...

    10-7: Composite, or Weighted Average, Cost of Capital, WACC WACC Midwest Electric Company (MEC) uses only debt and common equity. It can borrow unlimited amounts at an interest rate of rd-11% as long as it financ at its target capital structure, which calls for 35% debt and 65% common equity. Its last dividend (Do) was $2.20, its expected constant growth rate is 396, and its common stock sells for $21. MEC's tax rate is 40%. Two projects are available: Project...

  • ______  16.  Each of the following is a typical source of long-term capital for a firm EXCEPT                        &n

    ______  16.  Each of the following is a typical source of long-term capital for a firm EXCEPT                                                 A.  Accounts Receivable.                                                 B. long-term debt.                                                 C.  preferred stock.                                                 D.  common stock. ______  17.  ____________________________ is the process of evaluating and selecting long-term                                                 investments that are consistent with the firm’s goal of maximizing owners’ wealth. A. Compounding B. Capital budgeting C. Normalizing D. Underwriting ______  18.  ________________________ are projects whose cash flows in a capital budgeting analysis are                                                 unrelated to one another.  I.e., accepting one project does not prevent the firm from doing...

  • Suppose Acme Industries correctly estimates its WACC at a given point in time and then uses that same cost of capital to...

    Suppose Acme Industries correctly estimates its WACC at a given point in time and then uses that same cost of capital to evaluate all projects of various risks for the next 10 years. ACME will most likely a)become less risky over time, because it will tend to accept more low risk projects that high risk projects. b)become more risky over time, because it will tend to accept more high risk projects that low risk projects. c)continue at the same risk,...

  • 5. Risk analysis in capital budgeting Projects differ in risk, and risk analysis is a critical...

    5. Risk analysis in capital budgeting Projects differ in risk, and risk analysis is a critical component of the capital budgeting process. Consider the case of United Recycling Inc.: United Recycling Inc. is one of the largest recyclers of glass and paper products in the United States. The company is looking into expanding into the cardboard recycling business. The company's CFO has performed a detailed analysis of the proposed expansion. The company's CFO used sophisticated software to analyze a large...

  • Marble Construction estimates that its WACC is 9% if equity comes from retained earnings. However, if...

    Marble Construction estimates that its WACC is 9% if equity comes from retained earnings. However, if the company issues new stock to raise new equity, it estimates that its WACC will rise to 9.6%. The company believes that it will exhaust its retained earnings at $2,400,000 of capital due to the number of highly profitable projects available to the firm and its limited earnings. The company is considering the following seven investment projects: Project IRR 13.7% 13.3 10.1 Size $...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT