Question

In mid-2005 Gunawan Wiboto (Gunawan), an ethnic Chinese Indonesian entrepreneur and founder of the Ramayana Group,...

In mid-2005 Gunawan Wiboto (Gunawan), an ethnic Chinese Indonesian entrepreneur and founder of the Ramayana Group, decided to build a steel mill incorporated as a new company: PT Hanuman Steel. His team began the search for an experienced engineering consultant for the project. The company approached several consulting firms reputed for their engineering services. The difficulty, as they quickly discovered, was finding a consultant who believed they could do it their way and be successful.

The required services fell into four stages: basic design, detailed engineering, procurement, and construction. Representatives from four selected reputable international consultants submitted their proposals. On 3 January 2006, the John Smith Engineering Consultant Corp., headquartered in Melbourne, was awarded the contract for the basic design development phase.

John Smith and the basic design development phase

The John Smith team began work quickly and efficiently. According to Hanuman Steel’s Chief Engineer, ‘The rapport was excellent. They treated us as personal guests, and we did the same when they came to Surabaya’.

The first ripples of disturbance appeared when a team of specialists from John Smith travelled to Indonesia for on-the-spot investigation. On matters related to engineering work, the relationship between the two firms remained good. It was the financial side, and specifically the construction budget and the overall cost of the project that caused the first rifts to appear. When Hanuman Steel looked at Smith’s costing, they found they were ‘way out – they were engineers, not commercial people’. If the design side went well, the commercial side proved far more contentious; the relationship finally foundered over budget disagreements concerning the three remaining phases. Smith’s estimated cost for the procurement and the construction of the mill was US$100 million. Hanuman Steel estimated it at US$50 million. Smith’s schedule for completion of the project was 36 months, Hanuman Steel’s was 18 months.

At this stage, Gunawan concluded that his interests were no longer being served, and, as the basic design phase of the project was coming to an end, he decided to opt for a different consultant for the following phases.

A failed attempt: Lars Corp

Gunawan and his Chief Engineer visited Stockholm to sound out Lars Corp, a Swedish firm that had already worked on the preliminary blueprint of the project. Lars was selected for the phases of detailed engineering, procurement, and construction. At the end of November 2006, draft contract in hand, Hanuman Steel negotiators went to Stockholm to finalize the agreement. Negotiations were difficult because Lars adopted a very legalistic approach. But finally an agreement was reached and Gunawan flew to Stockholm to sign the contract. A celebration dinner was held. The next morning, Gunawan discovered that Lars’ president had left for the USA. However, before leaving he had drawn up a letter of understanding, signed it and sent it to the hotel. Inserted in this document, Gunawan found a clause concerning performance guarantees that was ‘totally against the spirit of everything we had discussed’. The clause, which had not been previously seen or discussed by the Hanuman Steel people, had ‘turned a fixed price contract into an open contract’. Other clauses, already agreed, had also been changed. To Gunawan, the message was clear – it indicated a lack of trust in him and his company. Utterly frustrated by this development, Gunawan refused to sign the document and flew directly to Pittsburgh to meet Tom Brown, a shortlisted US consultant.

Another try: Tom Brown

Shortly after Gunawan’s visit to Brown, a meeting was held between the staff of the two companies. On Hanuman Steel’s side, concern centered on the juxtaposition of low costs and high quality, and achieving the right balance. The director of engineering at Brown’s was ‘a polished, very polite and persuasive gentleman’. He and the Hanuman Steel team discussed the project in Pittsburgh for two weeks, aided by visits from Gunawan and the Brown director’s boss. Between them, they covered all the ground in deciding who should do what; what should be Hanuman Steel’s responsibility and what Brown’s, and what they should do jointly. Shortly after, Brown’s president, Tom Brown, accompanied by the man who would be in charge of the project, flew to Surabaya to sign a letter of understanding. In February 2007, a cross-cultural seminar organized by Hanuman Steel’s two European consultants took place in Pittsburgh, attended by people from Hanuman Steel and Brown’s. The practical outcome, it was hoped, would be to resolve problems before they arose and forge a team spirit.

Despite these efforts, a feeling of uneasiness began to surface on the Hanuman Steel side during the early meetings to prepare for the supplier negotiations. Hanuman Steel found that Brown’s was ‘building in safety feature after safety feature, which gave us serious doubts about the eventual cost of the project’. The breaking point came over a much more important issue. Brown’s had agreed to give Hanuman Steel two almost unconditional bank bonds which it could cash if the project failed. However, Brown’s appeared to have second thoughts about the bank bonds, and its failure to issue them turned into a serious problem. Hanuman Steel then withdrew its team and sent Brown’s a letter noting that ‘under the circumstances, we feel we cannot work together. Thank you very much’.

Gunawan had learnt his most important lesson: ‘Even when you have everything in a written contract, it doesn’t mean you will get it’. These problems had been exacerbated by the cultural gulf between the two sides. Gunawan’s entrepreneurial approach and determination to keep his budget adjusted for local conditions, coupled with the Indonesian preference for keeping their financial plans flexible and in shades of grey, was diametrically opposed to the European and North American desire to play safe – to have everything set in concrete down to the finest detail, with every guarantee possible and every contingency allowed for. As Hanuman Steel eventually discovered, what they were asking for was outside the experience of the conservative Western consultants. It created a clash of two very different cultures.

Source: Based on author’s own work

1. How do you assess the situation?

2. Do you think Gunawan was being unreasonable?

3. Do you think the Western consultants did not understand the Indonesian context and culture?

4. How much were the clashes caused by cultural differences as opposed to commercial ones?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1. The situation here is all about the conflict of interest and concerns of gunawan and other parties that he deals with. While Gunawan wanted everything to be in budget for his project, the consultant had their own budget designed for the project.

2. No, Gunawan was just being more concerned about his project forecasting and hat he had to finance so he was looking for a perfect consultant within the reasonable budget he had.

3. No, The Western consultants did understand the Indonesian context and culture only to certain extent as there was no question of culture over here as both the partly were comfortable working together. It was just that they disagreed on financial requirements for project.

4. The cultural difference was when Gunawan could not trust one of the consultant and in other cases could not rely on their advice despite their agreement for the same

Add a comment
Know the answer?
Add Answer to:
In mid-2005 Gunawan Wiboto (Gunawan), an ethnic Chinese Indonesian entrepreneur and founder of the Ramayana Group,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • CLARK FAUCET COMPANY BACKGROUND By 1999, Clark Faucet Company had grown into the third largest supplier...

    CLARK FAUCET COMPANY BACKGROUND By 1999, Clark Faucet Company had grown into the third largest supplier of faucets for both commercial and home use. Competition was fierce. Consumers would evaluate faucets on artistic design and quality. Each faucet had to be available in at least twenty-five different colors. Commercial buyers seemed more interested in the cost than the average consumer, who viewed the faucet as an object of art, irrespective of price. Clark Faucet Company did not spend a great...

  • Entering and Contracting Contracting at Charity Medical Center Charity Medical Center (CMC), a five hundred-bed acute-care...

    Entering and Contracting Contracting at Charity Medical Center Charity Medical Center (CMC), a five hundred-bed acute-care hospital, was part of the Jefferson Hospital Corporation (JHC). JHC, which operated several long-term and acute-care facilities and was sponsored by a large religious organization, had recently been formed and was trying to establish accounting and finance, materials management, and human resources systems to manage and coordinate the different facilities of particular concern to CMC, however, was a market share that had been declining...

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

  • QUESTION 1: Why must project manager should have good technical skills but also good management skills?...

    QUESTION 1: Why must project manager should have good technical skills but also good management skills? QUESTION 2: **Communication and Communicator are related" This quote from the text suppose that the communication process is lead by the spokeperson. Do you think is it a gift" to be a good communicator or a skill to improve ( use example of your knowledge to answer)? QUESTION 3: Look at the text paragraph yellow highlighted, and do you think that in today's world...

  • Playgrounds and Performance: Results Management at KaBOOM! (A) We do this work because we want to...

    Playgrounds and Performance: Results Management at KaBOOM! (A) We do this work because we want to make a difference in the world; how can we go further faster? - Darell Hammond, CEO and co-founder, KaBOOM! Darell Hammond stepped onto the elementary school playground and took a long, slow look around. It was 8 a.m. on an unusually warm fall day in 2002 and the playground was deserted, but Hammond knew the children would start arriving soon to admire their new...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT