Tri Star inc has the following mutually exclusive projects. Calculate the payback period for each project....
Tri-Star, Inc has the following mutually exclusive projects: Project A: Year 0; -14,900 Year 1; 9,400 Year 2; 8,000 Year 3; 2,100 Project B Year 0; -10,200 Year 1; 4,900 Year 2; 4,400; Year 3; 6,800 1. Calculate the payback period for each project. (Round to 2 decimal places) 2. If the appropriate discount rate is 13 percent, what is the NPV for each project? (Round to 2 decimal places)
Calculating Payback Perlod and NPV Tri Star, Inc., has the following mutually exclusive projects. YEAR PROJECT AT PROJECT B -$15,300 w No 8,700 -$10,700 5,300 4,300 4,800 7,400 3,100 a. Suppose the company's payback period cutoff is two years. Which of these two projects should be chosen? b. Suppose the company uses the NPV rule to rank these two projects. Which project should be chosen if the appropriate discount rate is 15 percent?
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,700 –$ 9,100 1 8,300 3,800 2 6,900 3,300 3 2,100 5,700 Calculate the payback period for each project.
Calculating Payback Period and NPV Novell, Inc., has the following mutually exclusive projects. Year Project A Project B 0 −$15,000 −$19,000 1 10,400 12,700 2 5,900 6,100 3 2,100 5,300 a.Suppose the company’s payback period cutoff is two years. Which of these two projects should be chosen? b.Suppose the company uses the NPV rule to rank these two projects. Which project should be chosen if the appropriate discount rate is 15 percent?
I need help in solving this question. Thank you Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 14,300 –$ 9,700 1 8,900 4,400 2 7,500 3,900 3 2,100 6,300 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A years Project B years Based on the payback period, which project should the company accept? Project B...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A -$13,900 8,500 7,100 2,100 Project B -$9,300 4,000 3,500 5,900 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Project A Project B Payback Period 1.76 years 2.932 years
Novell, Inc., has the following mutually exclusive projects. Year Project A Project B 0 –$21,000 –$24,000 1 12,500 13,500 2 9,000 10,000 3 3,000 9,000 a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) a-2. If the company's payback period is two years, which, if either, of these projects should be chosen? Project A Project B...
Novell, Inc., has the following mutually exclusive projects. Year Project A Project B 0 –$16,000 –$19,000 1 10,000 11,000 2 6,500 7,500 3 2,500 6,500 a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) a-2. If the company's payback period is two years, which, if either, of these projects should be chosen? Project A Project...
Maxwell Software, Inc., has the following mutually exclusive projects. Year Project A -$22,000 13,000 9,500 3,100 Project B -$25,000 14,000 10,500 9,500 نادية a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Payback period years Project A Project B years a-2. Which, if either, of these projects should be chosen? O Project A O Project B Both projects Neither project b-1. What is the NPV for...
Novell, Inc., has the following mutually exclusive projects. Year Project A Project B 0 $18,000 $21,000 11,000 12,000 2 7,500 8,500 3 2,700 7,500 1 a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Project A Project B years years a-2. If the company's payback period is two years, which, if either of these projects should be chosen? O Project A O Project B O Both...