Option (b) is correct
Since pre determined overhead rate is based on estimated machine hours, so,
Pre determined overhead rate = Total estimated factory overheads / Estimated machine hours
First we will calculate total factory overheads as below:
Total estimated factory overheads = Estimated Variable manufacturing overhead + Estimated Fixed manufacturing overhead
Total estimated factory overhead = ($5.77 * 38300) + $1028738
Total estimated factory overhead = $220991 + $1028738 = $1249729
Now,
Pre determined overhead rate = Total estimated factory overheads / Estimated machine hours
putting the values in the above formula, we get,
Pre determined overhead rate = $1249729 / 38300 = $32.63 per machine hour
Brothern Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. Data...
Brothern Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. Data for the most recently completed year appear below: Estimates made at the beginning of the year: Estimated machine-hours 33,100 Estimated variable manufacturing overhead $5.72 per machine-hour Estimated total fixed manufacturing overhead $770,568 Actual machine-hours for the year 30,800 The predetermined overhead rate for the recently completed year was closest to: $28.60 per machine-hour $29.00 per machine-hour 0 0 $5.72 per machine-hour $23.28 per machine-hour
Brothern Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. Data for the most recently completed year appear below: Estimates made at the beginning of the year: Estimated machine-hours 39,700 Estimated variable manufacturing overhead $ 6.32 per machine-hour Estimated total fixed manufacturing overhead $ 1,159,637 Actual machine-hours for the year 37,500 The predetermined overhead rate for the recently completed year was closest to: A. 35.18 B. 35.53 C. 6.32 D. 29.21
Giannitti Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. Data for the upcoming year appear below Estimated machine-hours Estimated variable manufacturing overhead Estimated total fixed manufacturing overhead 72,500 $ 3.20 per machine-hour $838,750 A The predetermined overhead rate for the recently completed year was closest to The predetermined overhead rate for the recently completed year was closest to: Multiple Choice $8.64 per machine-hour $6.77 per machine-hour O $14.77 per machine-hour $9.60 per machine-hour
Gilchrist Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. At the beginning of the most recently completed year, the Corporation estimated the machine-hours for the upcoming year at 45.900 machine-hours. The estimated variable manufacturing overhead was $7.53 per machine-hour and the estimated total fed manufacturing overhead was $1290,708. The predetermined overhead rate for the recently completed year was closest to: Multiple Choice $35.65 per machine-hour $7.53 per machine-hour $34.65 per machine-hour O $28.12 per...
Giannitti Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. Data for the upcoming year appear below: Estimated machine-hours 72,500 Estimated variable manufacturing overhead $ 3.00 per machine-hour Estimated total fixed manufacturing overhead $ 838,760 The predetermined overhead rate for the recently completed year was closest to:
Giannitti Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. Data for the upcoming year appear below: Estimated machine-hours Estimated variable manufacturing overhead Estimated total fixed manufacturing overhead 72,100 $ 3.10 per machine-hour $838,780 The predetermined overhead rate for the recently completed year was closest to: Multiple Choice $8.60 per machine-hour $9.30 per machine-hour $14.73 per machine-hour $6.79 per machine-hour
Moore Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. Data for the most recently completed year appear below: Estimates made at the beginning of the year: Estimated machine-hours 20,200 Estimated variable manufacturing overhead $ 9.00 per machine-hour Estimated total fixed manufacturing overhead $ 496,920 Actual machine-hours for the year 21,400 The predetermined overhead rate for the recently completed year was closest to: $33.60. $9.00. $24.60. $32.22.
6. Buker Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. Data for the upcoming year appear below: Estimated machine-hours 72,800 Estimated variable manufacturing overhead $3.40 per machine-hour Estimated total fixed manufacturing overhead $838,790 The predetermined overhead rate for the recently completed year was closest to:
Brother Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year Data for the most recently completed year appear below Estimates made at the beginning of the year Estimated machine-hours Estimated variable manufacturing overhead Estimated total fixed manufacturing overhead Actual machine-hours for the year 49,30 $ 6.37 per machine-hour $997,832 45,800 The predetermined overhead rate for the recently completed year was closest to Multiple Choice 526 16 permaneno 526.6 por machine 56 37 pat machine hou...
TB MC Qu. 2-39 (Algo) Brothern Corporation bases its predetermined... Brother Corporation bases its predetermined overhead rate on the estimated machine-hours for the upcoming year. Data for the most recently completed year appear below. Estimates made at the beginning of the year, Estimated machine-hours 31,400 Estimated variable manufacturing overhead $5.66 per machine-hour Estimated total fixed manufacturing overhead $639,618 Actual machine-hours for the year 27,500 The predetermined overhead rate for the recently completed year was closest to: Multiple Choice $20.37 per...