Triangle Corp is planning to buy a new computer for $750,000 with a useful life of six years. At the end of six years, the system will have no value. Over the six years the system will save them $250,000 each year for the first three years and $100,000 each year for the last three years.
a. What is the NPV of the project if Triangle Corp requires a return of 15%?
b. What is the IRR for this project?
c. At what required rate of return is the project’s NPV = 0?
d. How are NPV and IRR related?
e. At a required rate of return of 15%, is the project acceptable?
Triangle Corp is planning to buy a new computer for $750,000 with a useful life of...
Hardware Corp. is planning to buy production machinery. This machinery's expected useful life is 5 years, with a $10,000 salvage value. They require a minimum rate of return of 12%, and have calculated the following data pertaining to the purchase and operation of this machinery: Year Estimated annual cash inflows $ 60,000 80,000 95,000 115,000 140,000 Estimated annual cash outflows $ 10,000 20,000 25,000 35,000 50,000 Depreciation $30,000 $30,000 $30,000 $30,000 $30,000 Determine the Payback Period, Accounting Rate of Return....
Capital Budgeting Analysis: The MCSL Corp. is planning a new investment project which is expected to yield cash inflows of $180,000 per year in Years 1 through 3, $225,000 per year in Years 4 through 7, and $185,000 in Years 8 through 10. This investment will cost the company $880,000 today (initial outlay). We assume that the firm's cost of capital is 7.8%. (1) Draw a time line to show the cash flows of the project. 2) Compute the project’s...
Problem 10 Intro Better Tires Corp. is planning to buy a new tire making machine for $80,000 that would save it $80,000 per year in production costs. The savings would be constant over the project's 3-year life. The machine is to be linearly depreciated to zero and will have no resale value after 3 years. The appropriate cost of capital for this project is 15% and the tax rate is 21%. Part 1 18 - Attempt 1/5 for 10 pts....
no 3! need the working according to formula! not excel sheet. 2) Which of the following statements is MOST correct? A) It a project's internal rate of return (IRR) exceeds the required return, then the project's net present value (NPV) must be negative. B) If Project A has a higher IRR than Project B, then Project A must also have a higher NPV. (C) The IRR calculation implicitly assumes that all cash flows are reinvested at a rate of return...
DYI Construction Co. is considering a new inventory system that will cost $750,000. The system is expected to generate positive cash flows over the next four years in the amounts of $350,000 in year one, $325,000 in year two, $250,000 in year three, and $180,000 in year four. DYI's required rate of return is 8%. What is the net present value of this project? $87,417 $96,320 $104,089 $183,472
Capital Budgeting Analysis : A firm is planning a new project that is projected to yield cash flows of - $595,000 in Year 1, $586,000 per year in Years 2 through 5, and $578,000 in Years 6 through 11. This investment will cost the company $2,580,000 today (initial outlay). We assume that the firm's cost of capital is 11%. (1) Draw a timeline to show the cash flows of the project. (2) Compute the project’s payback period, net present value...
8) Project A has an internal rate of return (IRR) of 15 percent. Project B has an IRR of 14 percent. Both projects have a required retum of 12 percent. Which of the following statements is MOST correct? A) Project A must have a higher NPV than Project B. B) Both projects have a positive net present value (NPV) C) Project B has a higher profitability index than Project A. D) If the required return were less than 12 percent,...
10 points Question 8 Save Answer Siegmeyer Corp. is considering a new inventory system that will cost $750,000. The system is expected to generate positive cash flows over the next four years in the amounts of $350,000 in year one, $325,000 in year two, $150,000 in year three, and $180,000 in year four. Siegmeyer's required rate of return is 8%. Based on the NPV calculated previously, Siegmeyer should the project because its NPV is greater than Accept; zero Reject; zero...
Riggs Corp. management is planning to spend $650,000 on a new marketing campaign. They believe that this action will result in additional cash flows of $300,070 over the next three years. If the discount rate is 17.5 percent, what is the NPV on this project?
Sunland Corp. management is planning to spend $650,000 on a new marketing campaign. They believe that this action will result in additional cash flows of $309,000 each year for three years. If the discount rate is 17.5 percent, what is the NPV on this project? (Enter negative amounts using negative sign e.g. -45.25. Do not round discount factors. Round other intermediate calculations and final answer to 0 decimal places, e.g. 1,525.)