Question

A project has the following cash flows: Year Cash Flow 0 $ 66,500 1 –41,000 2...

A project has the following cash flows:

Year Cash Flow
0 $ 66,500
1 –41,000
2 –32,800

What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)

Internal rate of return             %

What is the NPV of this project if the required return is 4 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

Net present value            $

What is the NPV of the project if the required return is 0 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

Net present value            $

What is the NPV of the project if the required return is 21 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.)

Net present value            $

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1.Internal rate of return:

Internal rate of return is calculated using a financial calculator by inputting the below:

  • Press the CF button.
  • CF0= $66,500.
  • Cash flow for each year should be entered.
  • Press Enter and down arrow after inputting each cash flow.
  • After entering the last cash flow cash flow, press the IRR button and enter the interest rate to get the IRR of the project.

The IRR is 7.53%.

2.Internal rate of return when the discount rate is 4%.

This is calculated using a financial calculator by inputting the below:

  • Press the CF button.
  • CF0= $66,500.
  • Cash flow for each year should be entered.
  • Press Enter and down arrow after inputting each cash flow.
  • After entering the last cash flow cash flow, press the NPV button and enter the interest rate.
  • Press enter after that. Press the down arrow and CPT buttons to get the net present value.

The net present value is -$3,248.52.

3.Internal rate of return when the discount rate is 0%.

This is calculated using a financial calculator by inputting the below:

  • Press the CF button.
  • CF0= $66,500.
  • Cash flow for each year should be entered.
  • Press Enter and down arrow after inputting each cash flow.
  • After entering the last cash flow cash flow, press the NPV button and enter the interest rate.
  • Press enter after that. Press the down arrow and CPT buttons to get the net present value.

The net present value is -$7,300

4. Internal rate of return when the discount rate is 21%.

This is calculated using a financial calculator by inputting the below:

  • Press the CF button.
  • CF0= $66,500.
  • Cash flow for each year should be entered.
  • Press Enter and down arrow after inputting each cash flow.
  • After entering the last cash flow cash flow, press the NPV button and enter the interest rate.
  • Press enter after that. Press the down arrow and CPT buttons to get the net present value.

The net present value is -$10,212.86.

Add a comment
Know the answer?
Add Answer to:
A project has the following cash flows: Year Cash Flow 0 $ 66,500 1 –41,000 2...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A project has the following cash flows: Year Cash Flow 0 $ 69,500 1 – 47,000...

    A project has the following cash flows: Year Cash Flow 0 $ 69,500 1 – 47,000 2 – 30,400 a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 6 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer...

  • A project has the following cash flows: Year Cash Flow 65,500 165,500 0 1 39,000 -33,600...

    A project has the following cash flows: Year Cash Flow 65,500 165,500 0 1 39,000 -33,600 a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.a.. 32.16.) b. What is the NPV of this project if the required return is 5 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal...

  • A project has the following cash flows: Year Cash Flow $74,000 -56.000 -26,800 2 . a....

    A project has the following cash flows: Year Cash Flow $74,000 -56.000 -26,800 2 . a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 6 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places,...

  • A project has the following cash flows: Year Cash Flow $112,000 – 67,000 - 57,000 1...

    A project has the following cash flows: Year Cash Flow $112,000 – 67,000 - 57,000 1 N- a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 10 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) c. What is the NPV of...

  • A project has the following cash flows: Year Cash Flow $ 68,000 -44,000 - 31,600 a....

    A project has the following cash flows: Year Cash Flow $ 68,000 -44,000 - 31,600 a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 4 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places,...

  • A project has the following cash flows: Year Cash Flow $ 71,000 -50,000 -29,200 a. What...

    A project has the following cash flows: Year Cash Flow $ 71,000 -50,000 -29,200 a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 6 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g.,...

  • A project has the following cash flows: Year Cash Flow $73,000 -54,000 - 27,600 a. What...

    A project has the following cash flows: Year Cash Flow $73,000 -54,000 - 27,600 a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 5 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g.,...

  • A project has the following cash flows: Year Cash Flow $73,500 -55,000 - 27,200 a. What...

    A project has the following cash flows: Year Cash Flow $73,500 -55,000 - 27,200 a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 4 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g.,...

  • A project has the following cash flows: Year Cash Flow $112,000 - 67,000 - 57,000 N-...

    A project has the following cash flows: Year Cash Flow $112,000 - 67,000 - 57,000 N- a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 10 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) c. What is the NPV of the...

  • A project has the following cash flows: 0 $70,000 48,000 -30,000 a. What is the IRR...

    A project has the following cash flows: 0 $70,000 48,000 -30,000 a. What is the IRR for this project? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) b. What is the NPV of this project if the required return is 5 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) c. What...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT