Question

Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $547,200 is estimated to result in $182,400 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $79,800. The press also requires an initial investment in spare parts inventory of $22,800, along with an additional $3,420 in inventory for each succeeding year of the project.

  

Required :

If the shop's tax rate is 32 percent and its discount rate is 13 percent, what is the NPV for this project? (Do not round your intermediate calculations.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Step 1 calculate the depreciation schedule:

Depreciation Schedule as Per MACRS 5 year rates
Year Opening Balance Investment Depreciation Closing Balance
0 547200 547200
1 547200 0.2*547200=109440 437760
2 437760 0.32*547200=175104 262656
3 262656 0.192*547200=105062.4 157593.6
4 157593.6 0.1152*547200=63037.44 94556.16
5 94556.16 0.1152*547200=63037.44 31518.72
6 31518.72 0.0576*547200=31518.72 0
  • Opening balance = previous year's closing balance
  • Closing balance = opening balance+investment-depreciation

Step 2 CF schdule and NPV calculation:

CF schedule
Year Remark 0 1 2 3 4
Pretax savings Given 182400 182400 182400 182400
Depreciation Calculated above 109440 175104 105062.4 63037.44
EBIT Pretax savings-Depreciation 72960 7296 77337.6 119362.56
Tax 32% x EBIT 23347.2 2334.72 24748.032 38196.0192
EAT EBIT-Tax 49612.8 4961.28 52589.568 81166.5408
Depreciation Added back as non cash expense 109440 175104 105062.4 63037.44
Initial investment Given -547200
WCINV Given -22800 -3420 -3420 -3420 -3420
WCINV Recovery As per convention 36480
Salvage Value Given 79800
Tax on profit 32% x (salvage value-book value at the end of year 4) -4426.848
CF EAT+Depreciation+Investment+WCINV+WCINV recovery+Salvage value+Tax on profit -570000 155632.8 176645.28 154231.968 252637.1328
Discount factor formula 1/1.13^0 1/1.13^1 1/1.13^2 1/1.13^3 1/1.13^4
Discount factor 1 0.884955752 0.783146683 0.693050162 0.613318728
DCF CF x Discount factor -570000 137728.1416 138339.1652 106890.4905 154947.0849
NPV = Sum of all Discounted CF -32095.11794

NPV = -32095.12, as it is negative, the project is not worth investing.

Add a comment
Know the answer?
Add Answer to:
Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $710,400 is estimated to result in $236,800 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $103,600. The press also requires an initial investment in spare parts inventory of $29,600, along with an additional $4,440 in inventory for each succeeding year...

  • Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,027,200 is estimated to result in $342,400 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $149,800. The press also requires an initial investment in spare parts inventory of $42,800, along with an additional $6,420 in inventory for each succeeding year...

  • Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $710,400 is estimated to result in $236,800 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $103,600. The press also requires an initial investment in spare parts inventory of $29,600, along with an additional $4,440 in inventory for each succeeding year...

  • Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $595,200 is estimated to result in $198,400 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $86,800. The press also requires an initial investment in spare parts inventory of $24,800, along with an additional $3,720 in inventory for each succeeding year...

  • Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,104,000 is estimated to result in $368,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $161,000. The press also requires an initial investment in spare parts inventory of $46,000, along with an additional $6,900 in inventory for each succeeding year...

  • Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Geary Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,104,000 is estimated to result in $368,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $161,000. The press also requires an initial investment in spare parts inventory of $46,000, along with an additional $6,900 in inventory for each succeeding year...

  • Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $796800 is estimated to result in $265600 in annual pretax cost savings. The press falls in the MACRS (MACRS Table) five-year class and it will have a salvage value at the end of the project of $116200. The press also requires an initial investment in spare parts inventory of $33200, along with an additional $4980 in inventory for each succeeding year...

  • Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $556,800 is estimated to result in $185,600 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $81,200. The press also requires an initial investment in spare parts inventory of $23,200, along with an additional $3,480 in inventory for each succeeding year...

  • Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $787,200 is estimated to result in $262,400 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $114,800. The press also requires an initial investment in spare parts inventory of $32,800, along with an additional $4,920 in inventory for each succeeding year...

  • CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new...

    CSM Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $415,000 is estimated to result in $154,000 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table) and it will have a salvage value at the end of the project of $55,000. The press also requires an initial investment in spare parts inventory of $16,000, along with an additional $3,000 in inventory for each succeeding year...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT