Question

Lydia Company planned to produce 12,000 units. Processing required 16,000 machine hours at a cost of...

Lydia Company planned to produce 12,000 units. Processing required 16,000 machine hours at a cost of $43,000 + $12 per machine hour. Actual sales were 15,000 units requiring 20,000 machine hours. Actual processing cost was $253,000.

_____ is the flexible-budget variance for processing.

Group of answer choices

$18,000 favorable

$30,000 unfavorable

$18,000 unfavorable

$30,000 favorable

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Flexible budget variance = Standard cost - Actual cost

= (20,000 × 12) + 43,000 - 253,000

= 283,000 - 253,000

= 30,000 favourable

Add a comment
Know the answer?
Add Answer to:
Lydia Company planned to produce 12,000 units. Processing required 16,000 machine hours at a cost of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Elixer Corporation planned to produce 10,000 units. Processing required 15,000 machine hours at a cost of...

    Elixer Corporation planned to produce 10,000 units. Processing required 15,000 machine hours at a cost of $14,000 + $10.00 per machine hour. Actual sales were 14,000 units requiring 20,000 machine hours. Actual processing cost was $222,000. _____ is the static-budget variance for processing. Group of answer choices $39,000 unfavorable $58,000 favorable $39,000 favorable $58,000 unfavorable The following data for the Alpha Beta Company pertain to the produc­tion of 3,000 clay pigeons during July: Standard variable-overhead cost was $5.00 per pound...

  • During March, the company worked 16,000 machine-hours and produced 10,000 units. The company had originally planned...

    During March, the company worked 16,000 machine-hours and produced 10,000 units. The company had originally planned to work 18,000 machine-hours during March Chapter 9 Assessment Saved Help 6 You have just been hired by FAB Corporation, the manufacturer of a revolutionary new garage door opening device. The president has asked that you review the company's costing system and "do what you can to help us get better control of our manufacturing overhead costs." You find that the company has never...

  • Standard machine hours per unit of output 4 hours Standard variable-overhead rate per machine hour 8.00...

    Standard machine hours per unit of output 4 hours Standard variable-overhead rate per machine hour 8.00 Actual variable-overhead rate per machine hour Actual machine hours per unit of output Budgeted fixed overhead |Actual fixed overhead Budgeted production in units Actual production in units Variable-overhead spending variance Variable-overhead efficiency variance Fixed-overhead budget variance Fixed-overhead volume variance Total actual overhead Total budgeted overhead (flexible budget) Total budgeted overhead (static budget) Total applied overhead 9.00 3 S 50,000 25,000 24,000 72,000 Unfavorable 192,000...

  • please help 2. Wyoming division is responsible for manufacturing costs, and bases its budget on machine-hours....

    please help 2. Wyoming division is responsible for manufacturing costs, and bases its budget on machine-hours. The static planning budget (i.e., the master budget) and the actual results for May appear below: Budgeted number of machine-hours.......... Supplies (a $8.80 per machine-hour)....... Power (@ $5.10 per machine-hour)......... Salaries Equipment depreciation ............. Total... 3,000 $26.400 15,300 31.800 16.500 $90,000 Actual results for the month were: Actual number of machine-hours. Supplies.... Power........................... Salaries Equipment depreciation 3.100 $27.740 $16.120 $32.740 $16,510 a. Determine the...

  • "You work at a manufacturing plant and your supervisor has requested that you review the company’s...

    "You work at a manufacturing plant and your supervisor has requested that you review the company’s costing system because the company trying to better understand and control their costs. The schedules below include the cost formulas your company uses to create their flexible budget and the schedule of March's actual cost data:" Cost Formulas: Actual Costs in March   Utilities $16,600 plus $0.18 per machine-hour   Utilities $22,360   Maintenance $38,800 plus $2.00 per machine-hour   Maintenance $76,600   Supplies $0.30 per machine-hour   Supplies $6,400...

  • The condensed form of Nordstrop Company’s flexible budget for manufacturing overhead follows: Cost Machine-Hours Formula Overhead...

    The condensed form of Nordstrop Company’s flexible budget for manufacturing overhead follows: Cost Machine-Hours Formula Overhead Costs (per machine-hour) 7,500 8,500 9,500   Variable cost $ 1.35 $ 10,125   $ 11,475   $ 12,825     Fixed cost 15,000   15,000   15,000     Total overhead cost $ 25,125   $ 26,475   $ 27,825   The following information is available for a recent period: The denominator activity of 7,500 machine-hours was chosen to compute the predetermined overhead rate. At the 7,500 standard machine-hours level of activity, the company should...

  • Lancelot Corporation manufactures tennis gear and uses budgeted machine - hours to allocate variable manufacturing over...

    Lancelot Corporation manufactures tennis gear and uses budgeted machine - hours to allocate variable manufacturing overhead. The following information relates to the company's manufacturing overhead data: Budgeted output units Budgeted machine - hours Budgeted variable manufacturing overhead costs for 3,000 units 3,000 units 15,000 hours $172,500 Actual output units produced Actual machine - hours used Actual variable manufacturing overhead costs 3,250 units 14,500 hours $230,000 What is the flexible - budget variance for variable manufacturing overhead? O A. $43,125 favorable...

  • Blaze Corp. applies overhead on the basis of direct labor hours. For the month of March, the company planned production...

    Blaze Corp. applies overhead on the basis of direct labor hours. For the month of March, the company planned production of 10,000 units (80% of its production capacity of 12,500 units) and prepared the following budget: Operating Levels Overhead Budget 80% Production in units 10,000 Standard direct labor hours 30,000 Budgeted overhead Variable overhead costs Indirect materials $ 30,000 Indirect labor 40,000 Power 8,000 Maintenance 3,000 Total variable costs 81,000 Fixed overhead costs Rent of factory building 31,000 Depreciation—Machinery 45,000...

  • Required 2 Required 1 Required 3 Compute the overhead volume variance. Classify as favorable or unfavorable....

    Required 2 Required 1 Required 3 Compute the overhead volume variance. Classify as favorable or unfavorable. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no variance. Do not round intermediate calculations.) Volume Variance Volume variance Required 1 Required 3 Required 1 Required 2 Required 3 Prepare an overhead variance report at the actual activity level of 9,000 units. Classify as favorable or unfavorable. (Indicate the effect of each variance by selecting for favorable, unfavorable, and no...

  • Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units Practical...

    Walkenhorst Company's machining department prepared its 2019 budget based on the following data: 40,000 units Practical capacity Standard machine hours per unit Standard variable factory overhead Budgeted fixed factory overhead $3.00 per machine hour $368,000 The department uses machine hours to apply factory overhead to production. In 2019, the department used 88,000 machine hours and incurred $636,000 in total manufacturing overhead cost to manufacture 43,000 units. Actual fixed overhead cost for the year was $380,000. Required: Determine for the year:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT