1. Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period.
Direct labor standard (4 hrs. @ $7/hr.) | $ | 28 | per unit |
Actual hours worked | 12,250 | ||
Actual rate per hour | $ | 7.50 | |
Multiple Choice
$6,125 unfavorable.
$7,000 unfavorable.
$7,000 favorable.
$12,250 favorable.
$6,125 favorable.
2.
Ratchet Manufacturing anticipates total sales for August, September, and October of $200,000, $210,000, and $220,500 respectively. Cash sales are normally 25% of total sales and the remaining sales are on credit. All credit sales are collected in the first month after the sale. Compute the amount of accounts receivable to be reported on the company's budgeted balance sheet for August.
Multiple Choice
$150,000.
$50,000.
$157,500.
$52,500.
$200,000.
3.
In preparing a budgeted balance sheet, the amount for Accounts Receivable data can be derived from:
Multiple Choice
The purchases budget and schedule of cash payments.
The sales budget and the schedule of cash receipts.
The capital expenditures budget and purchases budget.
The budgeted income statement and budgeted balance sheet.
The selling expenses budget and the schedule of cash receipts.
4.
A plan that lists the types and amounts of operating expenses expected that are not included in the selling expenses budget is a:
Multiple Choice
General and administrative expense budget.
Sales budget.
Cash payments budget.
Overhead budget.
Selling expense budget.
5.
Cameroon Corp. manufactures and sells electric staplers for $16 each. If 10,000 units were sold in December, and management forecasts 4% growth in sales each month, the number of electric stapler sales budgeted for March should be:
Multiple Choice
10,000
11,249
10,400
10,816
11,000
Aloan Co. provides the following sales forecast for the next
three months:
January | February | March | ||||
Sales units | 3,000 | 4,200 | 5,000 | |||
The company wants to end each month with ending finished goods
inventory equal to 10% of the next month’s sales. Finished goods
inventory on December 31 is 300 units. The budgeted production
units for February are:
Multiple Choice
5,000 units.
4,200 units.
4,700 units.
4,120 units.
4,280 units.
6.
Zhang Industries is preparing a cash budget for June. The company has $25,000 cash at the beginning of June and anticipates $95,000 in cash receipts and $111,290 in cash disbursements during June. The company has no loans outstanding on June 1. Compute the amount the company must borrow, if any, to maintain a $20,000 cash balance.
Multiple Choice
$28,710.
$12,290.
$16,290.
$11,290.
$6,290.
Geneva Company manufactures dolls that are sold to various
customers. The company works at full capacity for half the year to
meet peak demand, and operates at 80% capacity for the other half
of the year. The following information is provided:
Units produced and sold | 600,000 | units | ||
Selling price | $ | 35 | / | unit |
Variable manufacturing costs | $ | 20 | / | unit |
Fixed manufacturing costs | $ | 1,200,000 | / | yr. |
Variable selling and administrative costs | $ | 6 | / | unit |
Fixed selling and administrative costs | $ | 950,000 | / | yr. |
Geneva receives a purchase order to make 5,000 dolls as a one-time
event. The good news is that this order is during a period when
Geneva does have excess capacity. What is the lowest selling price
Geneva should accept for this purchase order?
rev: 04_24_2018_QC_CS-125342, 07_09_2018_QC_CS-130916
Multiple Choice
$35.00
$26.00
$29.50
$23.50
Solution 1:
Direct labor cost variance = Standard direct labor cost - Actual direct labor cost = (3500*4*$7) - (12250*$7.50)
= $6,125 favorable
Hence last option is correct.
Solution 2:
amount of accounts receivable to be reported on the company's budgeted balance sheet for August = Credit sales for august
= $200,000*75% = $150,000
Solution 3:
In preparing a budgeted balance sheet, the amount for Accounts Receivable data can be derived from "The sales budget and the schedule of cash receipts."
Hence 2nd option is correct.
Solution 4:
A plan that lists the types and amounts of operating expenses expected that are not included in the selling expenses budget is a "General and administrative expense budget."
Hence first option is correct.
Note: As multiple questions are posted, i have answered more than required questions as per HomeworkLib policy, kindly post separate question for answer of remaining questions.
1. Use the following data to find the total direct labor cost variance if the company...
Use the following data to find the direct labor efficiency variance if the company produced 3,500 units during the period. Direct labor standard (4 hrs. @ $12/hr.) Actual hours worked Actual rate per hour $ 48 per unit 12,250 $ 12.50 - Ο $21,000 favorable. Ο $6,125 unfavorable. Ο $6,125 favorable. Ο $7,000 unfavorable. Ο $7,000 favorable.
Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period. Direct labor standard (4.00 hrs. @ $6.70/hr.) $ 26.80 per unit Actual hours worked 12,300 Actual rate per hour $ 7.30 Multiple Choice $4,010 favorable. $12,300 favorable. $4,010 unfavorable. $8,400 favorable. $8,400 unfavorable.
Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period. Direct labor standard (4.00 hrs. @ $6.70/hr.) $ 26.80 per unit Actual hours worked 12,300 Actual rate per hour $ 7.30 Multiple Choice $12,300 favorable. $8,400 favorable. $4,010 unfavorable. $8,400 unfavorable. $4,010 favorable.
Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period. Direct labor standard (4.00 hrs. @ $6.20/hr.) $ 24.80 per unit Actual hours worked 12,050 Actual rate per hour $ 6.30 Multiple Choice $12,050 favorable. $1,400 favorable. $1,400 unfavorable. $10,885 unfavorable. $10,885 favorable.
A company provided the following direct materials cost information. Compute the total direct materials cost variance. Standard costs assigned: Direct materials standard cost (419,000 units @ $4.00 / unit) $ 1,676,000 Actual costs: Direct Materials costs incurred (417,750 units @ $4.20 / unit) $ 1,754,550 Multiple Choice $78,550 Unfavorable. $78,550 Favorable. $5,000 Favorable. $83,550 Unfavorable. $83,550 Favorable.
Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period. Direct labor standard (4 hrs. @ $12/hr.) $ 48 per unit Actual hours worked 12,250 Actual rate per hour $ 12.50
Use the following data to find the direct labor rate variance if the company produced 6,200 units of product during the period. Standard: Direct labor (3.5 hrs. per unit @ $7/hr.) $ 24.50 per unit Actual cost incurred: Direct labor (22,800 hrs. @ $7.7/hr.) $ 175,560 Multiple Choice $15,960 unfavorable. $7,700 unfavorable. $7,700 favorable. $15,960 favorable. $23,660 favorable.
Use the following data to find the direct labor efficiency variance if the company produced 3,500 units during the period. Direct labor standard (4 hrs. @ $6.95/hr.) $ 27.80 per unit Actual hours worked 12,100 Actual rate per hour $ 7.40 Multiple Choice $5,445 unfavorable. $6,300 unfavorable. $6,300 favorable. $13,205 favorable. $5,445 favorable
Use the following data to find the total direct labor cost variance if the company produced 3,500 units during the period. Direct labor standard (4.00 hrs. @ $7.00/hr.) $ 28.00 per unit Actual hours worked 12,650 Actual rate per hour 7.40 $4,390 favorable. $5,600 favorable. $12,650 favorable. $4,390 unfavorable. $5,600 unfavorable.
Zhang Industries is preparing a cash budget for June. The company has $31.000 cash at the beginning of June and anticipates $101.000 in cash receipts and $126,290 in cash disbursements during June. The company has no loans outstanding on June 1. Compute the amount the company must borrow, if any, to maintain a $23.000 cash balance. Multiple Choice o О $25,290. o $18,290. o О $9,290. o О $17,290. o $28,710. The sales budget for Modesto Corp. shows that 21.400...