13. . Aircraft engine driven hydraulic pumps have an established mean time to failure of 5,500 hours. A sample of 53, from a different vendor, gave a mean life of 6,823 hours and a standard deviation of 564 hours. Using a 5% significance level, test the claim that the new vendor has significantly improved MTBF of hydraulic pumps.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

H0: <= 5500

HA: > 5500

Test statistics

t = (​​​​​​ - ) / (S / sqrt(n))

= (6823 - 5500) - ( 564 / sqrt(53) )

= 17.08

Critical value at 0.05 significance level with 52 = 1.675

Since test statistics > 1.675, Reject H0.

We conclude at 0.05 level that we have sufficient evidence to support the claim that the new vendor has

significantly improved MTBF of hydraulic pumps.

Add a comment
Know the answer?
Add Answer to:
13. . Aircraft engine driven hydraulic pumps have an established mean time to failure of 5,500...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1. A type of roller bearing has an established mean time to failure of 6000 hours....

    1. A type of roller bearing has an established mean time to failure of 6000 hours. A sample of 45, using a changed lubricant, gave a mean life of 6400 hours and a standard deviation of 450 hours. Using a 1% significance level, test the claim that the new lubricant has resulted in a significant change in mean life.

  • 1. A type of roller bearing has an established mean time to failure of 6000 hours....

    1. A type of roller bearing has an established mean time to failure of 6000 hours. A sample of 45, using a changed lubricant, gave a mean life of 6400 hours and a standard deviation of 450 hours. Using a 1% significance level, test the claim that the new lubricant has resulted in a significant change in mean life.

  • How can we assess whether a project is a success or a failure? This case presents...

    How can we assess whether a project is a success or a failure? This case presents two phases of a large business transformation project involving the implementation of an ERP system with the aim of creating an integrated company. The case illustrates some of the challenges associated with integration. It also presents the obstacles facing companies that undertake projects involving large information technology projects. Bombardier and Its Environment Joseph-Armand Bombardier was 15 years old when he built his first snowmobile...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT