Pittman Framing's cost formula for its supplies cost is $1,240 per month plus $13 per frame....

Pittman Framing's cost formula for its supplies cost is $1,240 per month plus $13 per frame. For the month of November, the company planned for activity of 622 frames, but the actual level of activity was 614 frames. The actual supplies cost for the month was $8,450. The spending variance for supplies cost in November would be closest to:

Multiple Choice

  • $772 F

  • $772 U

  • $876 F

  • $876 U

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Correct answer---------$772 F

Working

Units (A) Fixed cost (B) Variable cost per unit © Flexible cost and revenue (D=(A x C) +B)
Supplies 614 $ 1,240.00 $     13.00 $    9,222.00

Actual cost - Standard cost = Cost variance

8450-9222= $772 Favorable

The variance is favorable because the actual cost is lower than standard cost.

Add a comment
Know the answer?
Add Answer to:
Pittman Framing's cost formula for its supplies cost is $1,240 per month plus $13 per frame....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Pittman Framing's cost formula for its supplies cost is $1,100 per month plus $10 per frame....

    Pittman Framing's cost formula for its supplies cost is $1,100 per month plus $10 per frame. For the month of November, the company planned for activity of 620 frames, but the actual level of activity was 610 frames. The actual supplies cost for the month was $7,000. The spending variance for supplies cost in November would be closest to: Multiple Choice $300 F $300 U $200 F $200 U

  • Pittman Framing's cost formula for its supplies cost is $1,220 per month plus $11 per frame....

    Pittman Framing's cost formula for its supplies cost is $1,220 per month plus $11 per frame. For the month of November, the company planned for activity of 620 frames, but the actual level of activity was 612 frames. The actual supplies cost for the month was $7,650. The spending varlance for supplies cost in November would be closest to: Multiple Choice $302 F $390 U $390 F $302 U

  • Pittman Framing's cost formula for its supplies cost is $1,060 per month plus $16 per frame. For the month of November,...

    Pittman Framing's cost formula for its supplies cost is $1,060 per month plus $16 per frame. For the month of November, the company planned for activity of 616 frames, but the actual level of activity was 606 frames. The actual supplies cost for the month was $10,300. The spending variance for supplies cost in November would be closest to:

  • Tysor Framing's cost formula for its supplies cost is $3,540 per month plus $24 per frame....

    Tysor Framing's cost formula for its supplies cost is $3,540 per month plus $24 per frame. For the month of July, the company planned for activity of 1240 frames, but the actual level of activity was 1247 frames. The actual supplies cost for the month was $33,268. The spending variance for supplies cost in July would be closest to $32 U $200 F $32 F $200 U O

  • Petrus Framing's cost formula for its supplies cost is $1,790 per month plus $10 per frame....

    Petrus Framing's cost formula for its supplies cost is $1,790 per month plus $10 per frame. For the month of March, the company planned for activity of 619 frames, but the actual level of activity was 624 frames. The actual supplies cost for the month was $8,500. The activity variance for supplies cost in March would be closest to: $50 F $520 U $520 F $50 U 13. Pratte Boat Wash's cost formula for its cleaning equipment and supplies is...

  • Petrus Framing's cost formula for its supplies cost is $1,920 per month plus $11 per frame....

    Petrus Framing's cost formula for its supplies cost is $1,920 per month plus $11 per frame. For the month of March, the company planned for activity of 632 frames, but the actual level of activity was 639 frames. The actual supplies cost for the month was $9,340. The activity variance for supplies cost in March would be closest to:

  • Pratte Boat Wash's cost formula for its cleaning equipment and supplies is $2,550 per month plus...

    Pratte Boat Wash's cost formula for its cleaning equipment and supplies is $2,550 per month plus $46 per boot. For the month of April, the company planned for activity of 60 boats, but the actual level of activity was 15 boats. The actual cleaning equipment and supplies for the month was $3,370. The activity variance for cleaning equipment and supplies in April would be closest to: Multiple Choice $1940 F $1940 U $2,070 U $2.070 FHirons Air uses two measures of activity, flights and passengers, in...

  • 4) Petrus Framing's cost formula for its supplies cost is $2,300 per month plus $6 per...

    (4) Petrus Framing's cost formula for its supplies cost is $2,300 per month plus $6 per frame. For the month of March, the company planned for activity of 861 frames, but the actual level of activity was 856 frames. The actual supplies cost for the month was $7,790. The activity variance for supplies cost in March would be closest to:A) $324 UB) $30 ~FC) $324 ~FD) $30 U5) Dermody Snow Removal's cost formula for its vehicle operating cost is $2,850...

  • 11) Buckson Framing's cost formula for its supplies cost is $1,350 per month plus $18 per...

    11) Buckson Framing's cost formula for its supplies cost is $1,350 per month plus $18 per frame. For the month of June, the company planned for activity of 716 frames, but the actual level of activity was 713 frames. The actual supplies cost for the month was $14,820. The supplies cost in the flexible budget for June would be closest to: A) $14,820 B) $14,184 C) $14,178 D) $14,238

  • Petrus Framing's cost formula for its supplies cost is $1760 per month plus $10 per frame....

    Petrus Framing's cost formula for its supplies cost is $1760 per month plus $10 per frame. For the month of March, the company planned for activity of 616 frames, but the actual level of activity was 624 frames. The actual supplies cost for the month was $8,420. The activity variance for supplies cost in March would be closest to: Multiple Choice $500 F $500 U $80 F $80 U Depasquale Corporation is working on its direct labor budget for the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT