Question

Use below information for Questions 1 to 4: The smelting department of Company X has following...

Use below information for Questions 1 to 4:

The smelting department of Company X has following production and cost data for September:

  • Production: Beginning work in process 200 units that are 100% complete as to materials and 87% complete as to conversion costs; units started into production 1,000 units; units transferred out to next department

970 units; ending work in process are 100% complete as to materials and 43% complete as to conversion costs.

    • Manufacturing costs: Beginning work in process TL8,300 materials, TL9,260 labor and TL2,300 manufacturing overhead costs. In current period, TL50,700 worth of materials, TL25,600 worth of labor and TL37,000 worth of manufacturing overhead costs are incurred.
  • Compute the material cost portion of the ending inventory if the company uses WA method to compute equivalent units.
  • Compute the conversion cost portion of the ending inventory if the company uses FIFO method to compute equivalent units. method to compute equivalent units.
  • Compute the material cost portion of the transferred out inventory if the company uses FIFO method to compute equivalent units.
  • Compute the conversion cost portion of the transferred out inventory if the company uses WA method to compute equivalent units.
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Compute the material cost portion of the ending inventory if the company uses WA method to compute equivalent units. $        11,308
Compute the conversion cost portion of the ending inventory if the company uses FIFO method to compute equivalent units. method to compute equivalent units. $          6,918
Compute the material cost portion of the transferred out inventory if the company uses FIFO method to compute equivalent units. (8300+39039) $        47,339
Compute the conversion cost portion of the transferred out inventory if the company uses WA method to compute equivalent units. $        67,298

Calculation

Conversion Cost is sum of the direct labor cost and overhead
Company X
Smelting Department production Report
Weighted average Method
Month ended September 30
Summary of Physical units
Units in beginning WIP inventory 200
Units started during month 1000
Total unit to be accounted for 1200
Units completed and transferred out 970
Units in ending WIP inventory (1200-970) 230
Total unit accounted for 1200
Equivalent Units of production
Particulars Physical units Direct material Conversion Cost
% units % units
units in beginning WIP inventory 200 100%              200.00 100%       200.00
Units in Started and completed (970-200) 770 100%              770.00 100%       770.00
units in ending WIP inventory 230 100%              230.00 43%          98.90
Equivalent Units of production           1,200.00    1,068.90
Summary of cost to be accounted
Direct material Conversion Cost Total
Cost in beginning WIP $           8,300 $         11,560 $          19,860
Cost incurred during Month (Add) $         50,700 $         62,600 $        113,300
total cost to be accounted for $         59,000 $         74,160 $        133,160
cost per Equivalent Unit
total cost to be accounted for $         59,000 $         74,160
Divided by: Equivalent Units of production         1,200.00         1,068.90
Cost per Equivalent Unit $    49.16667 $    69.37974 $   118.54640
Assign costs to units transferred out and units in ending WIP inventory
cost assigned to units transferred out
units completed and transferred out                   970                   970
Cost per Equivalent Unit $    49.16667 $    69.37974
cost assigned to units transferred out $         47,692 $         67,298 $        114,990
cost assigned to units ending work in progress
equivalent units in ending WIP inventory             230.00               98.90
Cost per Equivalent Unit $    49.16667 $    69.37974
cost assigned to units ending work in progress $         11,308 $           6,862              18,170
Total cost assigned            133,160
Company X
Smelting Department production Report
First in First out (FIFO) Method
Month ended September 30
Summary of Physical units
Units in beginning WIP inventory 200
Units started during month 1000
Total unit to be accounted for 1200
Units completed and transferred out 970
Units in ending WIP inventory (1200-970) 230
Total unit accounted for 1200
Equivalent Units of production
Particulars Physical units Direct material Conversion Cost
% units % units
units in beginning WIP inventory 200 0%                        -   13%         26.00
Units in Started and completed (970-200) 770 100%              770.00 100%      770.00
units in ending WIP inventory 230 100%              230.00 43%         98.90
Equivalent Units of production           1,000.00      894.90
Summary of cost to be accounted
Direct material Conversion Cost Total
Cost in beginning WIP $            8,300 $          11,560 $          19,860
Cost incurred during Month (Add) $         50,700 $          62,600 $        113,300
total cost to be accounted for $         59,000 $          74,160 $        133,160
cost per Equivalent Unit
Cost incurred during Month $         50,700 $          62,600
Equivalent Units of production          1,000.00              894.90
Cost per Equivalent Unit $     50.70000 $     69.95195 $   120.65195
Assign costs to units transferred out and units in ending WIP inventory
cost assigned to units transferred out
Direct material $            8,300
Conversion Cost $         11,560
Cost in beginning WIP $          19,860
Direct material (0*50.7) $                   -  
Conversion Cost (26*69.95195) $            1,819
Cost incurred for complete beginning WIP $            1,819
Direct material (770*50.7) $         39,039
Conversion Cost (770*69.95195) $         53,863
Cost of units in Started and completed $          92,902
cost assigned to units transferred out $        114,581
cost assigned to units ending work in progress
Direct material (230*50.7) $         11,661
Conversion Cost (98.9*69.95195) $            6,918
cost assigned to units ending work in progress $          18,579
Total cost assigned $        133,160
For direct material 100% unit completed in the previous period. It means the remaining 0% completed in this month.
For conversion cost 87% unit completed in the previous period. It means the remaining 13% completed in this month.
Add a comment
Know the answer?
Add Answer to:
Use below information for Questions 1 to 4: The smelting department of Company X has following...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Use below information for Questions 10 to 13: The smelting department of Company X has following...

    Use below information for Questions 10 to 13: The smelting department of Company X has following production and cost data for September: • Production: Beginning work in process 200 units that are 100% complete as to materials and 76% complete as to conversion costs; units started into production 1,000 units; ending work in process 260 in units that are 100% complete as to materials and 54% complete as to conversion costs. Manufacturing costs: Beginning work in process TL8,600 materials, TL9,240...

  • The smelting department of Company X has the following production and cost data for September: •...

    The smelting department of Company X has the following production and cost data for September: • Production: Beginning work in process 200 units that are 100% complete as to materials and 82% complete as to conversion costs; units started into production 1,000 units; units transferred out to next department 950 units; ending work in process are 100% complete as to materials and 42% complete as to conversion costs. • Manufacturing costs: Beginning work in process TL8,200 materials, TL9,270 labor, and...

  • The Smelting Department of Polzin Company has the following production and cost data for September. Production:...

    The Smelting Department of Polzin Company has the following production and cost data for September. Production: Beginning work in process 2,100 units that are 100% complete as to materials and 20% complete as to conversion costs; units started and finished 8,900 units; and ending work in process 900 units that are 100% complete as to materials and 40% complete as to conversion costs. Manufacturing costs: Work in process, September 1, $16,000; materials added $59,780; labor and overhead $140,032. Polzin uses...

  • The Smelting Department of Polzin Company has the following production and cost data for September. Production:...

    The Smelting Department of Polzin Company has the following production and cost data for September. Production: Beginning work in process 2,100 units that are 100% complete as to materials and 20% complete as to conversion costs; units started and finished 8,900 units; and ending work in process 900 units that are 100% complete as to materials and 40% complete as to conversion costs. Manufacturing costs: Work in process, September 1, $16,000; materials added $59,780; labor and overhead $140,032. Polzin uses...

  • The Smelting Department of Kiner Company has the following production and cost data for November. Production:...

    The Smelting Department of Kiner Company has the following production and cost data for November. Production: Beginning work in process 3,700 units that are 100% complete as to materials and 29% complete as to conversion costs; units transferred out 9,300 units; and ending work in process 9,100 units that are 100% complete as to materials and 40% complete as to conversion costs. Compute the equivalent units of production for (a) materials and (b) conversion costs for the month of November....

  • The Smelting Department of Kiner Company has the following production and cost data for November.Production: Beginning...

    The Smelting Department of Kiner Company has the following production and cost data for November.Production: Beginning work in process 2,800 units that are 100% complete as to materials and 29% complete as to conversion costs; units transferred out 9,700 units; and ending work in process 8,200 units that are 100% complete as to materials and 44% complete as to conversion costs.Compute the equivalent units of production for (a) materials and (b) conversion costs for the month of November.    ...

  • Brief Exercise 17-5 The Smelting Department of Kiner Company has the following production and cost data...

    Brief Exercise 17-5 The Smelting Department of Kiner Company has the following production and cost data for November. Production: Beginning work in process 3,700 units that are 100% complete as to materials and 29% complete as to conversion costs; units transferred out 9,300 units; and ending work in process 9,100 units that are 100% complete as to materials and 40% complete as to conversion costs. Compute the equivalent units of production for (a) materials and (b) conversion costs for the...

  • 1. 2. Required information [The following information applies to the questions displayed below.) Fields Company has tw...

    1. 2. Required information [The following information applies to the questions displayed below.) Fields Company has two manufacturing departments, forming and painting. The company uses the weighted average method of process costing. At the beginning of the month, the forming department has 27,000 units in inventory, 70% complete as to materials and 30% complete as to conversion costs. The beginning inventory cost of $56,100 consisted of $40,000 of direct materials costs and $16,100 of conversion costs. During the month, the...

  • LALLIRATOR PRINTER VERSION BACK Brief Exercise 16-5 The Smelting Department of Kiner Company has the following...

    LALLIRATOR PRINTER VERSION BACK Brief Exercise 16-5 The Smelting Department of Kiner Company has the following production and cost data for November Production: Beginning work in process 3.900 units that are 100% complete as to materials and 29% complete as to conversion costs units transferred out 9,100 units and ending work in process 7.700 units that are 100% complete as to materials and 50% complete as to conversion costs. Compute the equivalent units of production for (a) materials and (b)...

  • BE3.5 Compute equivalent units of production. (LO 3), AP The Smelting Department of Kiner Company has...

    BE3.5 Compute equivalent units of production. (LO 3), AP The Smelting Department of Kiner Company has the following production data for November. Beginning work in process 2,000 units that are 100% complete as to materials and 20% complete as to conversion costs; units transferred out 9,000 units; and ending work in process 7,000 units that are 100% complete as to materials and 40% complete as to conversion costs. Compute the equivalent units of production for (a) materials and (b) conversion...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT