Use below information for Questions 1 to 4:
The smelting department of Company X has following production and cost data for September:
970 units; ending work in process are 100% complete as to materials and 43% complete as to conversion costs.
Compute the material cost portion of the ending inventory if the company uses WA method to compute equivalent units. | $ 11,308 |
Compute the conversion cost portion of the ending inventory if the company uses FIFO method to compute equivalent units. method to compute equivalent units. | $ 6,918 |
Compute the material cost portion of the transferred out inventory if the company uses FIFO method to compute equivalent units. (8300+39039) | $ 47,339 |
Compute the conversion cost portion of the transferred out inventory if the company uses WA method to compute equivalent units. | $ 67,298 |
Calculation
Conversion Cost is sum of the direct labor cost and overhead |
Company X | |||||
Smelting Department production Report | |||||
Weighted average Method | |||||
Month ended September 30 | |||||
Summary of Physical units | |||||
Units in beginning WIP inventory | 200 | ||||
Units started during month | 1000 | ||||
Total unit to be accounted for | 1200 | ||||
Units completed and transferred out | 970 | ||||
Units in ending WIP inventory (1200-970) | 230 | ||||
Total unit accounted for | 1200 | ||||
Equivalent Units of production | |||||
Particulars | Physical units | Direct material | Conversion Cost | ||
% | units | % | units | ||
units in beginning WIP inventory | 200 | 100% | 200.00 | 100% | 200.00 |
Units in Started and completed (970-200) | 770 | 100% | 770.00 | 100% | 770.00 |
units in ending WIP inventory | 230 | 100% | 230.00 | 43% | 98.90 |
Equivalent Units of production | 1,200.00 | 1,068.90 | |||
Summary of cost to be accounted | |||||
Direct material | Conversion Cost | Total | |||
Cost in beginning WIP | $ 8,300 | $ 11,560 | $ 19,860 | ||
Cost incurred during Month (Add) | $ 50,700 | $ 62,600 | $ 113,300 | ||
total cost to be accounted for | $ 59,000 | $ 74,160 | $ 133,160 | ||
cost per Equivalent Unit | |||||
total cost to be accounted for | $ 59,000 | $ 74,160 | |||
Divided by: Equivalent Units of production | 1,200.00 | 1,068.90 | |||
Cost per Equivalent Unit | $ 49.16667 | $ 69.37974 | $ 118.54640 | ||
Assign costs to units transferred out and units in ending WIP inventory | |||||
cost assigned to units transferred out | |||||
units completed and transferred out | 970 | 970 | |||
Cost per Equivalent Unit | $ 49.16667 | $ 69.37974 | |||
cost assigned to units transferred out | $ 47,692 | $ 67,298 | $ 114,990 | ||
cost assigned to units ending work in progress | |||||
equivalent units in ending WIP inventory | 230.00 | 98.90 | |||
Cost per Equivalent Unit | $ 49.16667 | $ 69.37974 | |||
cost assigned to units ending work in progress | $ 11,308 | $ 6,862 | 18,170 | ||
Total cost assigned | 133,160 |
Company X | ||||||
Smelting Department production Report | ||||||
First in First out (FIFO) Method | ||||||
Month ended September 30 | ||||||
Summary of Physical units | ||||||
Units in beginning WIP inventory | 200 | |||||
Units started during month | 1000 | |||||
Total unit to be accounted for | 1200 | |||||
Units completed and transferred out | 970 | |||||
Units in ending WIP inventory (1200-970) | 230 | |||||
Total unit accounted for | 1200 | |||||
Equivalent Units of production | ||||||
Particulars | Physical units | Direct material | Conversion Cost | |||
% | units | % | units | |||
units in beginning WIP inventory | 200 | 0% | - | 13% | 26.00 | |
Units in Started and completed (970-200) | 770 | 100% | 770.00 | 100% | 770.00 | |
units in ending WIP inventory | 230 | 100% | 230.00 | 43% | 98.90 | |
Equivalent Units of production | 1,000.00 | 894.90 | ||||
Summary of cost to be accounted | ||||||
Direct material | Conversion Cost | Total | ||||
Cost in beginning WIP | $ 8,300 | $ 11,560 | $ 19,860 | |||
Cost incurred during Month (Add) | $ 50,700 | $ 62,600 | $ 113,300 | |||
total cost to be accounted for | $ 59,000 | $ 74,160 | $ 133,160 | |||
cost per Equivalent Unit | ||||||
Cost incurred during Month | $ 50,700 | $ 62,600 | ||||
Equivalent Units of production | 1,000.00 | 894.90 | ||||
Cost per Equivalent Unit | $ 50.70000 | $ 69.95195 | $ 120.65195 | |||
Assign costs to units transferred out and units in ending WIP inventory | ||||||
cost assigned to units transferred out | ||||||
Direct material | $ 8,300 | |||||
Conversion Cost | $ 11,560 | |||||
Cost in beginning WIP | $ 19,860 | |||||
Direct material (0*50.7) | $ - | |||||
Conversion Cost (26*69.95195) | $ 1,819 | |||||
Cost incurred for complete beginning WIP | $ 1,819 | |||||
Direct material (770*50.7) | $ 39,039 | |||||
Conversion Cost (770*69.95195) | $ 53,863 | |||||
Cost of units in Started and completed | $ 92,902 | |||||
cost assigned to units transferred out | $ 114,581 | |||||
cost assigned to units ending work in progress | ||||||
Direct material (230*50.7) | $ 11,661 | |||||
Conversion Cost (98.9*69.95195) | $ 6,918 | |||||
cost assigned to units ending work in progress | $ 18,579 | |||||
Total cost assigned | $ 133,160 |
For direct material 100% unit completed in the previous period. It means the remaining 0% completed in this month. |
For conversion cost 87% unit completed in the previous period. It means the remaining 13% completed in this month. |
Use below information for Questions 1 to 4: The smelting department of Company X has following...
Use below information for Questions 10 to 13: The smelting department of Company X has following production and cost data for September: • Production: Beginning work in process 200 units that are 100% complete as to materials and 76% complete as to conversion costs; units started into production 1,000 units; ending work in process 260 in units that are 100% complete as to materials and 54% complete as to conversion costs. Manufacturing costs: Beginning work in process TL8,600 materials, TL9,240...
The smelting department of Company X has the following production and cost data for September: • Production: Beginning work in process 200 units that are 100% complete as to materials and 82% complete as to conversion costs; units started into production 1,000 units; units transferred out to next department 950 units; ending work in process are 100% complete as to materials and 42% complete as to conversion costs. • Manufacturing costs: Beginning work in process TL8,200 materials, TL9,270 labor, and...
The Smelting Department of Polzin Company has the following production and cost data for September. Production: Beginning work in process 2,100 units that are 100% complete as to materials and 20% complete as to conversion costs; units started and finished 8,900 units; and ending work in process 900 units that are 100% complete as to materials and 40% complete as to conversion costs. Manufacturing costs: Work in process, September 1, $16,000; materials added $59,780; labor and overhead $140,032. Polzin uses...
The Smelting Department of Polzin Company has the following production and cost data for September. Production: Beginning work in process 2,100 units that are 100% complete as to materials and 20% complete as to conversion costs; units started and finished 8,900 units; and ending work in process 900 units that are 100% complete as to materials and 40% complete as to conversion costs. Manufacturing costs: Work in process, September 1, $16,000; materials added $59,780; labor and overhead $140,032. Polzin uses...
The Smelting Department of Kiner Company has the following production and cost data for November. Production: Beginning work in process 3,700 units that are 100% complete as to materials and 29% complete as to conversion costs; units transferred out 9,300 units; and ending work in process 9,100 units that are 100% complete as to materials and 40% complete as to conversion costs. Compute the equivalent units of production for (a) materials and (b) conversion costs for the month of November....
The Smelting Department of Kiner Company has the following production and cost data for November.Production: Beginning work in process 2,800 units that are 100% complete as to materials and 29% complete as to conversion costs; units transferred out 9,700 units; and ending work in process 8,200 units that are 100% complete as to materials and 44% complete as to conversion costs.Compute the equivalent units of production for (a) materials and (b) conversion costs for the month of November. ...
Brief Exercise 17-5 The Smelting Department of Kiner Company has the following production and cost data for November. Production: Beginning work in process 3,700 units that are 100% complete as to materials and 29% complete as to conversion costs; units transferred out 9,300 units; and ending work in process 9,100 units that are 100% complete as to materials and 40% complete as to conversion costs. Compute the equivalent units of production for (a) materials and (b) conversion costs for the...
1. 2. Required information [The following information applies to the questions displayed below.) Fields Company has two manufacturing departments, forming and painting. The company uses the weighted average method of process costing. At the beginning of the month, the forming department has 27,000 units in inventory, 70% complete as to materials and 30% complete as to conversion costs. The beginning inventory cost of $56,100 consisted of $40,000 of direct materials costs and $16,100 of conversion costs. During the month, the...
LALLIRATOR PRINTER VERSION BACK Brief Exercise 16-5 The Smelting Department of Kiner Company has the following production and cost data for November Production: Beginning work in process 3.900 units that are 100% complete as to materials and 29% complete as to conversion costs units transferred out 9,100 units and ending work in process 7.700 units that are 100% complete as to materials and 50% complete as to conversion costs. Compute the equivalent units of production for (a) materials and (b)...
BE3.5 Compute equivalent units of production. (LO 3), AP The Smelting Department of Kiner Company has the following production data for November. Beginning work in process 2,000 units that are 100% complete as to materials and 20% complete as to conversion costs; units transferred out 9,000 units; and ending work in process 7,000 units that are 100% complete as to materials and 40% complete as to conversion costs. Compute the equivalent units of production for (a) materials and (b) conversion...