Question

Let's cost a job. Here is some data. What is the total cost on this job?...

Let's cost a job. Here is some data. What is the total cost on this job?

Direct Materials $2779

Direct Labor hours incurred to complete job 107

hours Hourly wage rate for DL workers $25.00

Predetermined Overhead Rate $65 per DL hour

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Let's cost a job. Here is some data. What is the total cost on this job?...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Let's cost a job. Here is some data. What is the total cost on this job?...

    Let's cost a job. Here is some data. What is the total cost on this job? Direct Materials Direct Labor hours incurred to complete job Hourly wage rate for DL workers Predetermined Overhead Rate $1,373 178 hours $25.00 $62 per DL hour

  • Job 243 was recently completed. The following data have been recorded on its job cost sheet...

    Job 243 was recently completed. The following data have been recorded on its job cost sheet $57,870 Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed 495 labor-hours 11 per labor-hour 576 machine-hours 4,500 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $13 per machine- hour Required Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...

  • Job 910 was recently completed. The following data have been recorded on its job cost sheet:...

    Job 910 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours $2,429 71 labor-hours $ 20 per labor-hour 134 machine-hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $21 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 910 would be:

  • 10. The following data have been recorded for recently completed Job 323 on its job cost...

    10. The following data have been recorded for recently completed Job 323 on its job cost sheet. Direct materials cost was $2,057. A total of 32 direct labor-hours and 216 machine-hours were worked on the job. The direct labor wage rate is $21 per labor-hour. The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $29 per machine-hour. The total cost for the job on its job cost sheet would be:

  • 9. Job 593 was recently completed. The following data have been recorded on its job cost...

    9. Job 593 was recently completed. The following data have been recorded on its job cost sheet:      Direct materials $2,412   Direct labor-hours 74 labor-hours   Direct labor wage rate $    21 per labor-hour   Machine-hours 137 machine-hours     The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $22 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 593 would be:

  • Job 910 was recently completed. The following data have been recorded on its job cost sheet:...

    Job 910 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours $2,474 73 labor-hours $ 19 per labor-hour 134 machine-hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $20 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 910 would be: $3,865 $7,381 $3,861

  • Job 910 was recently completed. The following data have been recorded on its job cost sheet:...

    Job 910 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $2,418 Direct labor-hours 74 labor-hours Direct labor wage rate $ 13 per labor-hour Machine-hours 137 machine-hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $14 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 910 would be: Multiple Choice $2,622 $6,138 $5,298 $3,380

  • Job 456 was recently completed. The following data have been recorded on its job cost sheet:...

    Job 456 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 2,463 Direct labor-hours 79 labor-hours Direct labor wage rate $ 16 per labor-hour Machine-hours 137 machine-hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $17 per machine-hour. The total cost that would be recorded on the job cost sheet for Job 456 would be: Multiple Choice $3,727 $6,056 $3,380 $6,896

  • Job 910 was recently completed. The following data have been recorded on its Job cost sheet:...

    Job 910 was recently completed. The following data have been recorded on its Job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours $2,412 74 labor-hours $ 21 per labor-hour 137 machine - hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $22 per machine-hour The total cost that would be recorded on the job cost sheet for Job 910 would be: Multiple Choice $3.966 $6,980 $4,304 $7,820

  • Job 910 was recently completed. The following data have been recorded on its Job cost sheet:...

    Job 910 was recently completed. The following data have been recorded on its Job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours $2,412 74 labor-hours $ 21 per labor-hour 137 machine - hours The Corporation applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $22 per machine-hour The total cost that would be recorded on the job cost sheet for Job 910 would be: Multiple Choice $3.966 $6,980 $4,304 $7,820

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT