Question

Use the 'Solver' add in on excel to formulate the constraints The Clarke Special Parts Company...

Use the 'Solver' add in on excel to formulate the constraints

The Clarke Special Parts Company manufactures three products: A, B, and C. Three manufacturing centers are necessary for the production process. Product A only passes through Centers 1 and 2; Products B and C must pass through all three manufacturing centers. The time required in each center to produce one unit of each of the three products is noted as follows:

X1 X2 X3 Z
Profit
Constraints
Center 1
Center 2
Center 3

So a unit of Product A takes three hours at Center 1, two hours at Center 2, and zero hours at Center 3. Each center is on a 40-hour week. The time available for production must be decreased by the necessary cleanup time. Center 1 requires four hours of cleanup, Center 2 requires seven hours, and Center 3 requires five hours. It is estimated that the profit contribution is $60 per unit of Product A, $40 per unit of Product B, and $30 per unit of Product C. How many units of each of these special parts should the company produce to obtain the maximum profit?

Formulation, by steps:

1. Determine the type of problem—The problem only mentions profit, so it has to be a maximization problem.

2. Define the decision variables—The profit coefficients are attached to Products A, B, and C and have a weekly stated time horizon, so

X1 = number of units of Product A to produce per week

X2 = number of units of Product B to produce per week

X3 = number of units of Product C to produce per week

3. Formulate the objective function:

Maximize: Z = 60X1 + 40X2 + 30X3

4. Formulate the constraints—This problem illustrates that some arithmetic may be needed to derive model parameters. In this case, the right-hand-side b values need to be adjusted for the cleanup time. In a week, each department starts with 40 hours for production purposes. They then have to be decreased for the cleanup time, as stated in the problem sentences, “The time available for production must be decreased by the necessary cleanup time. Center 1 requires four hours of cleanup, Center 2 requires seven hours, and Center 3 requires five hours.” So, for Center 1 we have 36 hours (40 − 4), for Center 2 we have 33 hours (40 − 7), and so on to formulate the right-hand-side values in each constraint. This problem also illustrates the use of the left-hand-side strategy for formulating constraints. Note how the tabled values are the technology coefficients listed by columns in the constraints that follow:
Image

5. Interpret the results

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Use the 'Solver' add in on excel to formulate the constraints The Clarke Special Parts Company...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Use the 'Solver' add in on excel to formulate the constraints The Clarke Special Parts Company manufactures thre...

    Use the 'Solver' add in on excel to formulate the constraints The Clarke Special Parts Company manufactures three products: A, B, and C. Three manufacturing centers are necessary for the production process. Product A only passes through Centers 1 and 2; Products B and C must pass through all three manufacturing centers. The time required in each center to produce one unit of each of the three products is noted as follows: X1 X2 X3 Z Profit Constraints Center 1...

  • Formulate but do not solve the following exercise as a linear programming problem A company manufactures...

    Formulate but do not solve the following exercise as a linear programming problem A company manufactures x units of product A, y units of product, and units of product C Each product is processed in three departments: I, I, and TIL The total available labor hours per week for Departments I, II, and I are 920, 2000, and 310, respectively. The time requirements in hours per unit and profit per unit for each product are as follows. Product Product Product...

  • A company is attempting to decide the mix of products which it should produce next week....

    A company is attempting to decide the mix of products which it should produce next week. It has six products, each with a unit profit (unit profit =selling price –variable cost per unit) and a unit production time as shown below: Product Profit ($/unit) Production time (hours/unit) 1 10 1 2 22 2 3 35 1.7 4 19 2.4 5 55 4.5 6 115 9.5 The company has 720 hours available next week. The company has the following additional linear...

  • Use Excel/Solver add in for accurate answers. Problem 3-19 (Algorithmic) Better Products, Inc., manufactures three products...

    Use Excel/Solver add in for accurate answers. Problem 3-19 (Algorithmic) Better Products, Inc., manufactures three products on two machines. In a typical week, 40 hours are available on each machine. The profit contribution and production time in hours per unit are as follows: Category Product 1 Product 2 Product 3 Profit/unit $39 $51 $18 Machine 1 time/unit 1.5 Machine 2 time/unit Two operators are required for machine 1; thus, 2 hours of labor must be scheduled for each hour of...

  • Hello, I need help with the following problem: 1. Multi-period production problem. Formulate the production and...

    Hello, I need help with the following problem: 1. Multi-period production problem. Formulate the production and inventory problem at XXI Company using Excel. See narrative below Solve the problem in Excel XX1 Company Production and Inventory Problem Narrative A company named XX1 has contracted to produce products A and B, over the months of June, July and August. The total production capacity (expressed in hours) varies monthly. The following table provides the basic data for the situation. June July August...

  • Formulate linear programming model

    Hart Manufacturing makes three products. Each product requires manufacturing operations in three departments: A, B, and C. The labor-hour requirements, by department, are as follows:Department.       Product 1.      Product 2.       Product 3.A                            1.50                3.00                2.00B                            2.00                1.00                2.50C                            0.25                 0.25               0.25During the next production period, the labor-hours available are 450 in department A, 350 in department B, and 50 in department C. The profit contributions per unit are $25 for product 1, $28 for product 2, and $30 for product 3.Formulate a linear...

  • Question 3 Not yet answered Marked out of 4.00 A company manufactures products A, B and...

    Question 3 Not yet answered Marked out of 4.00 A company manufactures products A, B and C. Each product is processed in three departments I, II and III. The total available labour-hours per week for departments I, II and III are 900, 1080 and 840, respectively. The time required (in hours per unit) and profit per unit for each product are as follows: 1 A B C 2 2 II 3 2 2 2 1 Profit $ 18 $ 12...

  • SOLVE IT BY HAND, NO EXCEL Back Savers is a company that produces backpacks primarily for...

    SOLVE IT BY HAND, NO EXCEL Back Savers is a company that produces backpacks primarily for students. They are considering offering some combination of two different models—the Collegiate and the Mini. Both are made out of the same rip-resistant nylon fabric. Back Savers has a long-term contract with a supplier of the nylon and receives a 3600 square-foot shipment of the material each week. Each Collegiate requires 2.5 square feet while each Mini requires 1.5 square feet. The sales forecasts...

  • PLEASE HELP!!!!! A product Using excel solver and LP formulate the model and find the least...

    PLEASE HELP!!!!! A product Using excel solver and LP formulate the model and find the least cost schedule on the machines for the productior Be sure to have solver produce the sensitivity report. Then discuss the reduced cost for each decision variable and the shadow price for each constraint. can be produced on four different machines. Each Machine has a production cost per unit processed and a production capacity (Cap) 2984 units/day. Cost/unit Cap/day Machine1 24 1066 Machine2 Machine3 Machine4...

  • A company makes two products, P and Q. They use two machines, A and B to make these two products. Each unit of P requir...

    A company makes two products, P and Q. They use two machines, A and B to make these two products. Each unit of P require of processing time on machine A and processing time on machine A and machine B is available for To have the most CM, how much of each product should be made per week. Formulate and solve by hand. You can take a picture of your work and upload it or type it all out in...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT