Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $3,500 $6,300 COSTS ADDED DURING MARCH: direct materials .............. $4,100 $3,900 $6,400 direct labor .................. 5,000 3,000 4,000 Madtack applies overhead to jobs at a rate of 85% of direct materials used. During March, Madtack completed and sold Job #361. Job #359 was also completed but was not sold by the end of March. Job #360 was not completed by the end of March. Madtack's actual overhead cost for the month of March totaled $11,500. Calculate Madtack's cost of goods sold for March after the overhead variance is closed.
The only job sold during March was job #361. Thus the un-adjusted | ||
cost of goods sold will be the costs of job #361 | ||
Job #361 | ||
Beginning work in process | $6,300 | |
Direct Material | $6,400 | |
Direct Labor | $4,000 | |
Overhead | $5,440 | |
($6,400 x 85%) | ||
Cost of Job #361 | $22,140 | |
Adjusted cost of goods sold = $22,140 - $740 = $21,400 | ||
Actual overhead | $11,500 | |
Total applied overhead | $12,240 | |
(4,100 + 3,900 + 6,400) x 85% | ||
Over applied | $740 |
Madtack Company uses a job-order costing system and started the month of March with three jobs...
Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $6,300 $3,500 COSTS ADDED DURING MARCH direct materials .............. $3,300 $4,100 $4,600 direct labor .................. 5,000 3,000 4,000 Madtack applies overhead to jobs at a rate of 70% of direct materials used. During March,...
Madtack Company uses a job-order costing system and started the month of March with only one job in process (Job #359). This job had $5,000 of total cost assigned to it at the beginning of March. Madtack applies overhead to jobs at a rate of 175% of direct labor cost. During March, Madtack assigned production costs as follows to the jobs worked on during the month: Job #359 Job #360 Job #361 direct materials .......... $1,000 $5,000 $3,000 direct labor...
QUESTION 2 Leija Manufacturing Company uses a job-order costing system and started the month of March with one job in process (Job #359). This job had $500 of cost assigned to it at this time. During March, Leija assigned production costs as follows to the jobs worked on during the month: - Job #359 $6,000 Job #360 $8,100 Job #361 $2,400 Total cost assigned to jobs during March .... During March, Leija completed and sold Job #359. Job #360 was...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: beginning work in process Job #1-A $3,250 Job #3-G $2,690 Job #7-L $3,720 COSTS ADDED DURING JUNE: direct materials direct labor ..... $4,680 3,530 $3,950 4,180 $2,870 2,410 During June,...
Question 5 Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job Job #1-A $3,250 Job #3-G $2,690 beginning work in process .. $3,720 COSTS ADDED DURING JUNE: direct materials ... direct labor ........ $4,680 3,530 $3,950 $2,870 2,410...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...
Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started th e month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1 - A $3,250 Job #3-G $2,690 Job #7-L $3,720 beginning work in process COSTS ADDED DURING JUNE: $3,950 4,180 $4,680 3,530 $2,870 2,410 direct materials direct labor...