Question

Madtack Company uses a job-order costing system and started the month of March with three jobs...

Madtack Company uses a job-order costing system and started the month of
March with three jobs in process. The cost of beginning work in process
plus the costs added during March are shown below:

                                  Job #359      Job #360      Job #361
beginning work in process .....    $4,800        $3,500        $6,300

COSTS ADDED DURING MARCH:
direct materials ..............    $4,100        $3,900        $6,400
direct labor ..................     5,000         3,000         4,000

Madtack applies overhead to jobs at a rate of 85% of direct materials
used. During March, Madtack completed and sold Job #361. Job #359 was
also completed but was not sold by the end of March. Job #360 was not
completed by the end of March. Madtack's actual overhead cost for the
month of March totaled $11,500.

Calculate Madtack's cost of goods sold for March after the overhead
variance is closed.
0 0
Add a comment Improve this question Transcribed image text
Answer #1
The only job sold during March was job #361. Thus the un-adjusted
cost of goods sold will be the costs of job #361
Job #361
Beginning work in process $6,300
Direct Material $6,400
Direct Labor $4,000
Overhead $5,440
($6,400 x 85%)
Cost of Job #361 $22,140
Adjusted cost of goods sold = $22,140 - $740 = $21,400
Actual overhead $11,500
Total applied overhead $12,240
(4,100 + 3,900 + 6,400) x 85%
Over applied $740
Add a comment
Know the answer?
Add Answer to:
Madtack Company uses a job-order costing system and started the month of March with three jobs...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Madtack Company uses a job-order costing system and started the month of March with three jobs...

    Madtack Company uses a job-order costing system and started the month of March with three jobs in process. The cost of beginning work in process plus the costs added during March are shown below: Job #359 Job #360 Job #361 beginning work in process ..... $4,800 $6,300 $3,500 COSTS ADDED DURING MARCH direct materials .............. $3,300 $4,100 $4,600 direct labor .................. 5,000 3,000 4,000 Madtack applies overhead to jobs at a rate of 70% of direct materials used. During March,...

  • Madtack Company uses a job-order costing system and started the month of March with only one...

    Madtack Company uses a job-order costing system and started the month of March with only one job in process (Job #359). This job had $5,000 of total cost assigned to it at the beginning of March. Madtack applies overhead to jobs at a rate of 175% of direct labor cost. During March, Madtack assigned production costs as follows to the jobs worked on during the month: Job #359 Job #360 Job #361 direct materials .......... $1,000 $5,000 $3,000 direct labor...

  • QUESTION 2 Leija Manufacturing Company uses a job-order costing system and started the month of March...

    QUESTION 2 Leija Manufacturing Company uses a job-order costing system and started the month of March with one job in process (Job #359). This job had $500 of cost assigned to it at this time. During March, Leija assigned production costs as follows to the jobs worked on during the month: - Job #359 $6,000 Job #360 $8,100 Job #361 $2,400 Total cost assigned to jobs during March .... During March, Leija completed and sold Job #359. Job #360 was...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: beginning work in process Job #1-A $3,250 Job #3-G $2,690 Job #7-L $3,720 COSTS ADDED DURING JUNE: direct materials direct labor ..... $4,680 3,530 $3,950 4,180 $2,870 2,410 During June,...

  • Question 5 Moor Company uses a job-order costing system and applies overhead costs to jobs at...

    Question 5 Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job Job #1-A $3,250 Job #3-G $2,690 beginning work in process .. $3,720 COSTS ADDED DURING JUNE: direct materials ... direct labor ........ $4,680 3,530 $3,950 $2,870 2,410...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started the month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1-A Job #3-G Job #7-L beginning work in process ..... $3,250 $2,690 $3,720 COSTS ADDED DURING JUNE: direct materials .............. $4,680 $3,950 $2,870 direct labor .................. 3,530 4,180 2,410...

  • Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor...

    Moor Company uses a job-order costing system and applies overhead costs to jobs at a rate of 120% of direct labor cost. Moor Company started th e month of June with three jobs in process. The cost of beginning work in process plus the costs added during June are shown below: Job #1 - A $3,250 Job #3-G $2,690 Job #7-L $3,720 beginning work in process COSTS ADDED DURING JUNE: $3,950 4,180 $4,680 3,530 $2,870 2,410 direct materials direct labor...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT