Data for a new product that is very labor intensive introduced by Hicks Brothers in the operation in Hendersonville, TN is given below. The average labor cost including overhead expenses is about $20 per hour.

Time for the very first unit = 9 hours

Time for the second unit = 8.462 hours.

What is the labor cost for the 1000-th unit ?

A.

$62.30

B.

$55.85

C.

69.94

D.

$75.23

0 0
Add a comment Improve this question Transcribed image text
Know the answer?
Add Answer to:
Data for a new product that is very labor intensive introduced by Hicks Brothers in the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 3) A product has an average labor cost of $10/hr. The overhead expenses are 100% of labor cost. Time for the first...

    3) A product has an average labor cost of $10/hr. The overhead expenses are 100% of labor cost. Time for the first unit-10 hours. Time for the fourth unit= 8.1 hours. Answer the following questions: (10 Points) a) Find the learning curve percentage for the production of this product b) What is the labor cost and overhead cost for the 500-th unit? 3) A product has an average labor cost of $10/hr. The overhead expenses are 100% of labor cost....

  • Current Designs has two main product lines- composite kayaks, which are handmade and very labor intensive,...

    Current Designs has two main product lines- composite kayaks, which are handmade and very labor intensive, and rotomolded kayaks, which require less labor but employ more expensive equipment. Current Designs’ controller, Diane Buswell, is now evaluating several different methods of assigning overhead to these products. It is important to ensure that costs are appropriately assigned to the company’s products. At the same time, the system that is used must not be so complex that its costs are greater than its...

  • Tutoria As you learned in the previous chapters, Curren very labor-intensive, and rotomolded which controller, Diane...

    Tutoria As you learned in the previous chapters, Curren very labor-intensive, and rotomolded which controller, Diane Buswell, is now evaluating et Designs has two main product lines- composite kayaks, which are handmade and ed kayaks, which require less labor but employ more expensive complex that its costs are greater than its bene the same time, the system that is used must not be so that itsstppropriateleral different methods of assigning overhead to these products. It is important to fits Diane...

  • Part IV-Problems (55 points) A. Highestec, Inc is beginning the production of a new product. Management...

    Part IV-Problems (55 points) A. Highestec, Inc is beginning the production of a new product. Management believes that 500 labor hours will be required to complete the new unit. A 90 percent cumulative average-time learning curve model for direct labor hours is assumed to be valid. Data on costs are as follows: S50,000 per unit s20 per direct labor hour $30 per direct labor hour Direct materials Direct labor Variable manufacturing overhead Required: a. Set up a table with columns...

  • 28. A weekly factory production report shows the following data: Product units produced Standard Direct Labor...

    28. A weekly factory production report shows the following data: Product units produced Standard Direct Labor (DL) time for 18,000 units 20,000 hours Standard DL rate per hour Actual DL time used in production: 20,800 hours Actual DL rate per hour Standard Direct Materials (DM) cost per unit Standard Factory Overhead (FO) rate: 40% of DL cost 18.00 Instructions (a, b, c): Calculate the following variances: please indicate (unfavorable) with your answer: 521.00 520.00 a) DL rate variance averable) er...

  • For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...

    For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.80 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.60 hours of direct labor...

  • Plantwide versus Departmental Rates, Product-Costing Accuracy: Activity-Based Costing Ramsey Company produces speakers (Model A and Model...

    Plantwide versus Departmental Rates, Product-Costing Accuracy: Activity-Based Costing Ramsey Company produces speakers (Model A and Model B). Both products pass through two producing departments, Model A's production is much more labor-intensive than that of Model B. Model B is also the more popular of the two speakers. The following data has been gathered for the two products Product Data Product Data Model A Model B Units produced per year 10,000 100,000 Prime costs $150,000 $1,500,000 Direct labor hours 140,000 300,000...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.40 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.60 pounds. Materials cost $2 per pound, but Stefani always takes the 2.00% cash discount all of its suppliers offer. Freight costs average $0.25 per pound. Direct labor. Each unit requires 1.00 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly...

  • For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago,...

    For many years, Thomson Company manufactured a single product called LEC 40. Then three years ago, the company automated a portion of its plant and at the same time introduced a second product called LEC 90 that has become increasingly popular. The LEC 90 is a more complex product, requiring 0.80 hours of direct labor time per unit to manufacture and extensive machining in the automated portion of the plant. The LEC 40 requires only 0.60 hours of direct labor...

  • Stefani Company has gathered the following information about its product. Direct materials: Each unit of product...

    Stefani Company has gathered the following information about its product. Direct materials: Each unit of product contains 3.10 pounds of materials. The average waste and spoilage per unit produced under normal conditions is 0.90 pounds. Materials cost $2 per pound, but Stefani always takes the 4.00% cash discount all of its suppliers offer. Freight costs average $0.45 per pound. Direct labor. Each unit requires 1.30 hours of labor. Setup, cleanup, and downtime average 0.20 hours per unit. The average hourly...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT