Rauth Inc. uses a job-order costing in which any underapplied or overapplied overhead is closed out to cost of goods sold at the end of the month. The company's cost of goods manufactured for August was $186,000; its beginning finished goods inventory was $60,250; its ending finished goods inventory was $39,600; its manufacturing overhead was underapplied by $3,500. Required: Determine the cost of goods sold that would appear on the income statement for August; in other words, determine the cost of goods sold after adjustment for any underapplied or overapplied overhead.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
cost of goods manufactured 186,000
add:beginning finished goods inventory 60,250
less:ending finished goods inventory (39,600)
add :under applied overhead 3,500
adjusted cost of goods sold 210,150
Add a comment
Know the answer?
Add Answer to:
Rauth Inc. uses a job-order costing in which any underapplied or overapplied overhead is closed out...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. Warden Inc. uses a job-order costing system in which any underapplied or overapplied overhead is...

    2. Warden Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed out to cost of goods sold at the end of the month. The company's cost of goods manufactured for March was $152,000 and its beginning and ending inventories were: Inventories: Beginning Ending Work in process ..... $20,000 $14,000 Finished goods ....... $45,000 $29,000 During the month, the manufacturing overhead cost incurred was $59,000 and the manufacturing overhead cost applied was $63,000. Required: Determine...

  • Abramov Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed...

    Abramov Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed to cost of goods sold at the end of the month. In May the company completed job N29W that consisted of 37,625 units of one of the company's standard products. No other jobs were in process during the month. The job cost sheet for job N29W shows that the job's total cost was $1,640,450. During the month, the actual manufacturing overhead cost incurred was...

  • Hubley Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed...

    Hubley Inc. uses a job-order costing system in which any underapplied or overapplied overhead is closed out to cost of goods sold at the end of the month. The company has provided the following data for August: Direct materials $ 78,750 Direct labor cost S 94,000 Manufacturing overhead cost incurred $ 61,275 Manufacturing overhead cost applied $ 65,800 Inventories: Beginning Ending Work in process $17,500 $19,850 Finished goods $61,500 $38,250 The cost of goods sold that appears on the income...

  • Dreckman Inc, uses a job order costing system in which any underappiled or overapplied overhead is...

    Dreckman Inc, uses a job order costing system in which any underappiled or overapplied overhead is closed to cost of goods sold at the end of the month. In August the company completed job M27K that consisted of 17000 units of one of the company's standard products. No other jobs were in process during the month The total manufacturing cost for job M27K according to its job cost sheet was 51118.600,hence the per unit product cost is $65.80. During the...

  • 1a) Compute the underapplied or overapplied overhead. b) Assume that the company closes any underapplied or...

    1a) Compute the underapplied or overapplied overhead. b) Assume that the company closes any underapplied or overapplied overhead to Cost of Goods Sold. Prepare the appropriate journal entry. c) Assume that the company allocates any underapplied or overapplied overhead proportionally to Work in Process, Finished Goods, and Cost of Goods Sold. Prepare the appropriate journal entry. d)  How much higher or lower will net operating income be if the underapplied or overapplied overhead is allocated to Work in Process, Finished Goods,...

  • 7) Molzahn Corporation is a manufacturer that uses job-order costing. The company closes out any overapplied...

    7) Molzahn Corporation is a manufacturer that uses job-order costing. The company closes out any overapplied or underapplied overhead to Cost of Goods Sold at the end of the year. The company has supplied the following data for the just completed year: Estimated total manufacturing overhead at the beginning 5481,250 of the year Estimated direct labor-hours at the beginning of the year 35.000 direct labor hours Results of operations: Actual direct labor-hours 40,000 direct labor-hours Manufacturing overhead: Indirect labor cost...

  • 1. Compute the underapplied or overapplied overhead. 2. Assume that the company closes any underapplied or...

    1. Compute the underapplied or overapplied overhead. 2. Assume that the company closes any underapplied or overapplied overhead to Cost of Goods Sold. Prepare the appropriate journal entry. 3. Assume that the company allocates any underapplied or overapplied overhead proportionally to Work in Process, Finished Goods, and Cost of Goods Sold. Prepare the appropriate journal entry. 4. How much higher or lower will net operating income be if the underapplied or overapplied overhead is allocated to Work in Process, Finished...

  • Heathcote Corporation is a manufacturer that uses job-order costing. The company closes out any overapplied or...

    Heathcote Corporation is a manufacturer that uses job-order costing. The company closes out any overapplied or underapplied overhead to Cost of Goods Sold at the end of the year. The company has supplied the following data for the just completed year: Estimated total manufacturing overhead at the beginning of the year $ 546,000 Estimated direct labor-hours at the beginning of the year 42,000 direct labor-hours Results of operations: Actual direct labor-hours 47,000 direct labor-hours Manufacturing overhead: Indirect labor cost $...

  • Molzahn Corporation is a manufacturer that uses job-order costing. The company closes out any overapplied or...

    Molzahn Corporation is a manufacturer that uses job-order costing. The company closes out any overapplied or underapplied overhead to Cost of Goods Sold at the end of the year. The company has supplied the following data for the just completed year: Estimated total manufacturing overhead at the beginning of the year Estimated direct labor-hours at the beginning of the year $481,250 35,000 direct labor-hours Results of operations: 40,000 direct labor-hours Actual direct labor-hours Manufacturing overhead: Indirect labor cost Other manufacturing...

  • QUESTION 6 25 points Shatrau Inc., which uses job-order costing, has provided the following data for...

    QUESTION 6 25 points Shatrau Inc., which uses job-order costing, has provided the following data for December: Direct materials ....... Direct labor cost ....... Manufacturing overhead cost incurred..... Manufacturing overhead cost applied ....... $32.000 $45,000 $42.000 $45,000 Inventories: Work in process ..... Finished goods ....... Beginning $24,000 $35,000 Ending $14,000 $48,000 Required: Determine the unadjusted cost of goods sold (in other words, the cost of goods sold before adjusting for any underapplied or overapplied overhead) for December. Show your work!

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT