Question

MA Company uses a standard cost system in which manufacturing overhead costs are applied to units...

MA Company uses a standard cost system in which manufacturing overhead costs are applied to units of the company's single product on the basis of direct laborhours (DLHs). The cost information for the product is as follows:

Standard Cost per unit of product:

Direct Materials, 2 metres at $4 per metre ....................................... $ 8

Direct Labor, 2 DLHs at $10 per DLH .................................................. $20

Variable Manufacturing Overhead, 2 DLHs at $2 per DLH ............ $ 4

Fixed ManufacturingOverhead, 2 DLHs at $4.5 per DLH ................ $ 9

Standard cost per unit ......................................................................... $41

The following data pertain to last year's activities:

At the start of the year, the company had forecast the manufacture of 15,000 units and the sale of 14,000 units at a selling price of $50.

During the year, the company manufactured 18,000 units of product. Of the 18,000 units of product manufactured, 16,000 units were sold at a selling price $48.

A total of 40,000 meters of direct materials was purchased during the year at a cost of $3 per meter. 38,000 meters were used to manufacture the 18,000 units

The company worked 35,000 direct labor-hours during the year at a cost of $8 per hour

The denominator activity level was 30,000 direct labor-hours.

Budgeted fixed manufacturing overhead costs were $135,000 while actual fixed manufacturing overhead costs were $150,000.

Actual variable manufacturing overhead costs were $74,000.

1. The revenue price variance is:

A. $32,000 (U) B. $0 C. $36,000 (U) D. $28,000 (U) E. None of the above

2. The direct materials quantity variance is:

A. $8,000 (U) B. $8,000 (F) C. $40,000 (U) D. $40,000(F) E. None of the above

3. The labor rate variance is:

A. $10,000 (U) B. $10,000 (F) C. $70,000 (U) D. $70,000 (F) E. None of the above

4. The variable manufacturing overhead spending variance is:

A. $2,000 (U) B. $2,000 (F) C. $4,000 (U) D. $4,000 (F) E. None of the above

5. The fixed overhead volume variance is:

A. $27,000 (U) B. $27,000 (F) C. $15,000 (U) D. $15,000 (F) E. None of the above

6.The allocation of manufacturing overhead is:

A. $10,000 under-allocated B. $10,000 over-allocated C. $29,000 under-allocated D. $19,000 over-allocated E. None of the above

Please write the calculation process. please~~

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Hi

Let me know in case you face any issue:

Add a comment
Answer #2
  1. The revenue price variance is: Actual revenue = Actual units sold * Selling price = 16,000 units * $48 = $768,000 Budgeted revenue = Budgeted units sold * Selling price = 14,000 units * $50 = $700,000

Revenue price variance = Actual revenue - Budgeted revenue = $768,000 - $700,000 = $68,000 (U)

Therefore, the correct answer is E. None of the above.

  1. The direct materials quantity variance is: Standard quantity of materials = Standard quantity per unit * Actual units produced Standard quantity per unit = 2 meters Actual units produced = 18,000 units

Standard quantity of materials = 2 meters * 18,000 units = 36,000 meters

Direct materials quantity variance = (Standard quantity of materials - Actual quantity of materials) * Standard cost per unit Actual quantity of materials = Total purchased - Materials unused

Total purchased = 40,000 meters Materials unused = Total purchased - Materials used Materials used = 38,000 meters

Actual quantity of materials = 40,000 meters - (40,000 meters - 38,000 meters) = 38,000 meters

Direct materials quantity variance = (36,000 meters - 38,000 meters) * $4 = $8,000 (U)

Therefore, the correct answer is A. $8,000 (U).

  1. The labor rate variance is: Actual labor cost = Actual direct labor-hours * Actual rate per hour Actual direct labor-hours = 35,000 hours Actual rate per hour = $8

Actual labor cost = 35,000 hours * $8 = $280,000

Labor rate variance = (Actual rate per hour - Standard rate per hour) * Actual direct labor-hours Standard rate per hour = $10

Labor rate variance = ($8 - $10) * 35,000 hours = $-70,000 (U)

Therefore, the correct answer is C. $70,000 (U).

  1. The variable manufacturing overhead spending variance is: Actual variable manufacturing overhead cost = Actual direct labor-hours * Actual rate per DLH Actual direct labor-hours = 35,000 hours Actual rate per DLH = $2

Actual variable manufacturing overhead cost = 35,000 hours * $2 = $70,000

Variable manufacturing overhead spending variance = Actual variable manufacturing overhead cost - Budgeted variable manufacturing overhead cost Budgeted variable manufacturing overhead cost = Budgeted DLHs * Variable overhead rate per DLH Budgeted DLHs = Denominator activity level = 30,000 hours Variable overhead rate per DLH = $2

Budgeted variable manufacturing overhead cost = 30,000 hours * $2 = $60,000

Variable manufacturing overhead spending variance = $70,000 - $60,000 = $10,000 (U)

Therefore, the correct answer is A. $10,000 (U).

  1. The fixed overhead volume variance is: Fixed overhead volume variance = Actual fixed manufacturing overhead cost - (Budgeted fixed manufacturing overhead cost * (Actual DLHs / Denominator activity level))

Actual fixed manufacturing overhead cost = $150,000 Budgeted fixed manufacturing overhead cost = $135,000 Actual DLHs = 35,000 hours Denominator activity level = 30,000 hours

Fixed overhead volume variance = $150,000 - ($135,000 * (35,000 hours / 30,000 hours)) = $15,000 (F)

Therefore, the correct answer is D. $15,000 (F).

  1. The allocation of manufacturing overhead is: Allocation of manufacturing overhead = Applied manufacturing overhead -


answered by: Mayre Yıldırım
Add a comment
Know the answer?
Add Answer to:
MA Company uses a standard cost system in which manufacturing overhead costs are applied to units...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • MA Company uses a standard cost system in which manufacturing overhead costs are applied to units of the company's s...

    MA Company uses a standard cost system in which manufacturing overhead costs are applied to units of the company's single product on the basis of direct laborhours (DLHs). The cost information for the product is as follows: Standard Cost per unit of product: Direct Materials, 2 metres at $4 per metre ....................................... $ 8 Direct Labor, 2 DLHs at $10 per DLH .................................................. $20 Variable Manufacturing Overhead, 2 DLHs at $2 per DLH ............ $ 4 Fixed ManufacturingOverhead, 2 DLHs...

  • The Chuba Corporation uses a standard cost system in which manufacturing overhead is applied on the...

    The Chuba Corporation uses a standard cost system in which manufacturing overhead is applied on the basis of standard direct labor-hours (DLHs). During December, the company actually used 7,200 direct labor-hours and made 1,900 units of finished product. The standard cost card for one unit of product includes the following data concerning manufacturing overhead: Variable overhead: 4 DLHs @ $5.25 per DLH Fixed overhead: 4 DLHs @ $2.00 per DLH For December, the company incurred $16,550 in fixed manufacturing overhead...

  • 1. Lee Manufacturing uses a standard cost system with overhead applied based on direct labor hours....

    1. Lee Manufacturing uses a standard cost system with overhead applied based on direct labor hours. The manufacturing budget for the production of 5,000 units for the month of May included the following information. Direct labor (10,000 hours at $15 per hour) $150,000 Variable overhead                                          $30,000 Fixed overhead                                                $80,000 During May, 6,000 units were produced and the direct labor efficiency variance was $1,500 unfavorable. Based on this information, the actual number of direct labor hours used in...

  • Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the bas...

    Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the basis of standard direct labor-hours. The budgeted variable manufacturing overhead is $3.40 per direct labor-hour and the budgeted fixed manufacturing overhead is $999,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $6.50 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $12.70 per...

  • Flandro Company uses a standard cost system and sets its predetermined overhead rate on the basis...

    Flandro Company uses a standard cost system and sets its predetermined overhead rate on the basis of direct labor-hours. The following data are taken from the company’s planning budget for the current year: Denominator activity (direct labor-hours) 12,000 Variable manufacturing overhead cost $ 37,200 Fixed manufacturing overhead cost $ 103,200 The standard cost card for the company’s only product is given below: Required: 1. Create a new standard cost card that separates the variable manufacturing overhead per unit and the...

  • In March, Leona Company made 4,500 units of its product. Leona uses a standard cost system...

    In March, Leona Company made 4,500 units of its product. Leona uses a standard cost system and applies overhead cost based on direct labor hours.   Standard: DLH per unit 2.50 Variable overhead per DLH $1.75 Fixed overhead per DLH $3.10 Budgeted variable overhead $21,875 Budgeted fixed overhead $38,750 Actual: Direct labor hours 10,000 Variable overhead $26,250 Fixed overhead $38,000 Refer to LeonaCompany. Using the four-variance approach, what is the fixed overhead spending variance? a. $7,000.00 U b. $ 750.00 F...

  • Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost...

    Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the basis of standard direct labor-hours. The budgeted variable manufacturing overhead is $5.00 per direct labor-hour and the budgeted fixed manufacturing overhead is $2,295,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $10.50 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $13.50 per...

  • Flandro Company uses a standard cost system and sets its predetermined overhead rate on the basis of direct labor...

    Flandro Company uses a standard cost system and sets its predetermined overhead rate on the basis of direct labor-hours. The following data are taken from the company's planning budget for the current year: Denominator activity (direct labor-hours) Variable manufacturing overhead coat Fixed manufacturing overhead coat $ 4,250 The standard cost card for the company's only product is given below. Standard Inputs Direct materials Direct labor Mutacturing overhead Total standard cost per Standard Quantity Dr Hours yards 2 hours 2 hour...

  • Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost...

    Lane Company manufactures a single product that requires a great deal of hand labor. Overhead cost is applied on the basis of standard direct labor-hours. The budgeted variable manufacturing overhead is $4.40 per direct labor-hour and the budgeted fixed manufacturing overhead is $1,764,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $9.00 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $13.20 per...

  • Vivaldi Enterprises uses a standard cost system in which it applies manufacturing overhead to units of product on the ba...

    Vivaldi Enterprises uses a standard cost system in which it applies manufacturing overhead to units of product on the basis of standard direct labor-hours. During the month of September, the company applied $51,000 in fixed manufacturing overhead cost to units of product. At the end of the month, manufacturing overhead was overapplied by $3,000. If the volume variance in September was $2,000 favorable, then the budgeted fixed manufacturing overhead cost for the month was: A. $48,000 B. $49,000 C. $54,000...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT