Question

Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects...

Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable.

WACC: 7.75%                                              

Year            0                 1           2           3          4

CFS        −$1,050     $675     $650              

CFL         −$1,050     $360     $360    $360   $360

  1. If the decision is made by choosing the project with the higher IRR, how much value will be forgone?
  2. What is the underlying cause of ranking conflicts between NPV and IRR?

Please include all equations including NPV. I have gone through the question myself a few times and I think I am getting the wrong answer/using the wrong equation for NPV or perhaps somewhere else. Thank you.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
The IRR and NPV of the projects are calculated below:
CFS:
Year Cash Flow PVIF at 7.75% PV at 7.75% PVIF at 18% PV at 18% PVIF at 17% PV at 17%
0 $             -1,050 1 $          -1,050 1 $        -1,050 1 $       -1,050
1 $                  675 0.92807 $               626 0.84746 $ 572 0.85470 $ 577
2 $                  650 0.86132 $               560 0.71818 $ 467 0.73051 $             475
3 $                      -   0.79937 $                  -   0.60863 $                -   0.62437 $                -  
4 $                      -   0.74188 $                  -   0.51579 $                -   0.53365 $                -  
Total $               136 $ -11 $                 2
NPV = $136
IRR = 17%+1%*2/(2+11) = 17.15%
CFL:
Year Cash Flow PVIF at 7.75% PV at 7.75% PVIF at 13% PV at 13% PVIF at 14% PV at 14%
0 $             -1,050 1 $          -1,050 1 $        -1,050 1 $       -1,050
1 $                  360 0.92807 $               334 0.88496 $             319 0.87719 $             316
2 $                  360 0.86132 $               310 0.78315 $             282 0.76947 $             277
3 $                  360 0.79937 $               288 0.69305 $             249 0.67497 $             243
4 $                  360 0.74188 $               267 0.61332 $             221 0.59208 $             213
Total $               149 $               21 $                -1
NPV = $149
IRR = 13%+1%*21/(21+1) = 13.95%
ANSWERS:
a] If the decision is made using IRR, Project CFS with the higher IRR of 17.15% will be chosen.
If CFS is chosen, value equal to 149-136 = $13 will be foregone.
b] The underlying cause of conflict in rankings between NPV and IRR, is the different reinvestment rate
assumptions made by the two methods with respect to intervening cash flows.
While NPV assumes that the intervening cash flows are reinvested at the WACC of MARR
for all projects, the IRR assumes that the intervening cash flows of each project are reinvested at its own IRR.
Thus, under the IRR method, the reinvestment rate is different for each of the projects.
Due to this difference in the following situations for mutually exclusive projects would result in conflicting
rankings.
*Wide difference in initial investments of the different projects
*Differing lives of the projects
*Widely differing cash flow patterns
Add a comment
Know the answer?
Add Answer to:
Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects...

    Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. Identify also the range of discounting rates in which project L will be selected. WACC: Year...

  • Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects...

    Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, so no value...

  • Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These...

    Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, i.e., no...

  • section 8

    Kosovski Company is considering Projects S and L, whose cash flows are shown below. These projects aremutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project withthe higher IRR, how much value will be forgone? Note that under some conditions choosing projects on thebasis of the IRR will cause $0.00 value to be lost.WACC: 7.75%Year 0 1 2 3 4CFS ?$1,050 $675 $650CFL ?$1,050 $360 $360 $360 $360____

  • Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...

    Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? WACC: 8% Year 0 1 2 3 4 CFS -$1,100 $380 $380 $380 $380 CFL -2,200 $730 $730 $730 $730 Options: 59.24, 52,83, 48,56, 43.70, 39.24

  • Question 3 of 24 Tesar Chemicals is considering Projects S and L, whose cash flows are...

    Question 3 of 24 Tesar Chemicals is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the...

  • Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...

    Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 4 -$1,100 -$2,200 12 $375 $375 $725...

  • A firm is considering Projects S and L, whose cash flows are shown below. These projects...

    A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...

  • A firm is considering Projects S and L, whose cash flows are shown below. These projects...

    A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...

  • Murray Inc. is considering Projects S and L, whose cash flows are shown below. These projects...

    Murray Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise Murray on the best procedure. If the wrong decision criterion is used, how much potential value would Murray lose? r. 6.00% Year 0 1 2 3 4 CFS −$1,025 $380 $380 $380 $380 CFL −$2,150 $765...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT