You oversee a team of workers checking in Baruch students to a career fair. Currently, you have one person doing each of the following processes with the average cycle time in parenthesis. Steps 1-3 must go in the order below, though step 4 can be performed at any time.

  1. Check for name on registration list (30 seconds)
  2. Speak with student about which breakout sessions they want to attend (120 seconds)
  3. Put appropriate materials in a packet for the student (60 seconds)
  4. Enter student in a raffle to win a free dream job (45 seconds)

Which step number is the bottleneck?

Step 1

Step 2

Step 3

Step 4

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Step 2

Step 2 is considered to be the bottleneck because this step has the longest duration and therefore acts as an ompedimentvin the whole process as well.

Add a comment
Know the answer?
Add Answer to:
You oversee a team of workers checking in Baruch students to a career fair. Currently, you...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT