You oversee a team of workers checking in Baruch students to a career fair. Currently, you have one person doing each of the following processes with the average cycle time in parenthesis. Steps 1-3 must go in the order below, though step 4 can be performed at any time.
Which step number is the bottleneck?
Step 1 |
||
Step 2 |
||
Step 3 |
||
Step 4 |
Step 2
Step 2 is considered to be the bottleneck because this step has the longest duration and therefore acts as an ompedimentvin the whole process as well.