Question

On the tab labeled "Original Problem", I have provided a problem statement and the modeling of...

On the tab labeled "Original Problem", I have provided a problem statement and the modeling of a Linear Programming Model Problem. Carefully read the problem statement. Reference the Wyndor example from the text for an example of the integration of a linear model to Excel.

The first requirement is to fill in the formulas in the GREEN cells for the Objective function and the constraints. There is no need to change the values in the RED cells.

Next, open Solver and fill in the 'Set Target Cell', 'By Changing Cells', and 'Subject to the Constraints' boxes.

Once you completed the Solver inputs and solved the problem, you are required to obtain the sensitivity analysis. If you do this correctly, the 'Sensitivity Report' will show up in a new tab in the bottom of the sheet.

From there, proceed to the Solutions tab where you will find five questions. To answer each question, you will be required to consult the sensitivity analysis and locate the correct information from the analysis to answer each question. All answers should come from solving the model and obtaining and consulting the sensitivity data, not by resolving the model multiple times.

In your response to each question, you should begin with a written sentence(s) that explains where specifically in the sensitivity analysis you found the information you need to answer each question followed by a sentence answering each respective question. Each question will be evaluated on explaining where in the sensitivity analysis you found the information necessary to answer the question (mechanical component) and for a clear, concise, grammatically correct answer to the question (written component). Questions should be answered on the Solutions tab and typed in unbolded print right after the statement of the question.

Good luck, and HAVE FUN!

Problem Statement:

The Charger Club of America sponsors driver education events that provide high-performance driving instruction on actual race tracks. Because safety is a primary consideration at such events, many owners elect to install roll bars in their cars. Wilson Industries manufactures two types of roll bars for Chargers, Model 1 and Model 2. Model 1 requires 20 pounds of a special high alloy steel, 50 minutes of manufacturing time, and 60 minutes of assembly time. Model 2 requires 25 pounds of the special high alloy steel, 100 minutes of manufacturing time, and 50 minutes of assembly time.   Wilson’s steel supplier indicated that at most 40,000 pounds of the high-alloy steel will be available next quarter. In addition, Wilson estimates that 120,000 minutes of manufacturing time and 96,000 minutes of assembly time will be available next quarter. The profit contributions are $200 per unit for Model 1 and $280 per unit for Model 2. The linear programming model for this problem is as follows:

Variables:

Model1 = Number of Model 1 to produce

Model2 = Number of Model 2 to produce

Objective:

Max 200 Model1 + 280 Model2

Constraints subject to:

20 Model1 + 25   Model2 <= 40,000 Steel available

50 Model1 + 100 Model2 <= 120,000 Manufacturing minutes

60 Model1 + 50   Model2 <= 96,000 Assembly minutes

Model1, Model2 >= 0

Question 1) What are the optimal solution and the total profit?

Question 2) If the unit profit of the Model 2 decreases to $250 per unit, how would the optimal solution change?

Question 3): How much should the company be willing to pay to acquire additional capacity in the 'Assembly minutes' area? Explain in detail.

Question 4) How much should the company be willing to pay to acquire additional 'Steel'? Explain in detail.

Question 5) How much will the objective function, 'Total Profit', change if there was one additiional hour of Manufacturing capacity available?


0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER:-

Objective Cell (Max)

CELL NAME ORIGINAL VALUE FINAL VALUE
$D$6 Total points 0 397714.29

Variable Cells

CELL NAME ORIGINAL VALUE FINAL VALUE INTEGER
$B$5 Number to Make Model 1 0 1028.57 Contin
$C$5 Number to Make Model 2 0 685.71 Contin

Constraints

CELL NAME CELL VALUE FORMULA STATUS SLACK
$D$9 Steel Available Used 37714.28571 $D$9<=$E$9 Not Binding 2285.714286
$D$10 Manufacturing Minutes Used 120000 $D$10<=$E$10 Binding 0
$D$11 Assembly Minutes Used 96000 $D$11<=$E$11 Binding 0

Sensitivity Report

Variable Cells

CELL NAME FINAL VALUE REDUCED COST OBJECTIVE COEFFICIENT ALLOWABLE INCREASE ALLOWABLE DECREASE
$B$5 Number to Make Model 1 1028.571429 0 200 136 60
$C$5 Number to Make Model 2 685.7142857 0 280 120 113.34

Constraints

CELL NAME FINAL VALUE SHADOW PRICE CONSTRAINT R.H. SIDE ALLOWABLE INCREASE ALLOWABLE DECREASE
$D$9 Steel Available Used 37714.28571 0 40000 1E+30 2285.714286
$D$10 Manufacturing Minutes Used 120000 1.942857143 120000 16000 2285.714286
$D$11 Assembly Minutes Used 96000 1.714285714 96000 10666.67 36000

(1)

Optimal solution: Model 1 = 1028.57

Model 2 = 685.71

Total profit = $397,714.29

(2)

The proposed decrease is 280 - 250 = 30

The proposed decrease is =30

The allowable decrease is 113.33.

So, there will be no change in the optimality.

(3)

Shadow price for assembly minutes = $1.714.

one additional assembly minute will generate an additional profit of $1.714.

the willingness to pay should be any amount less than $1.714 per minute.

(4)

Shadow price for steel = 0. This is a non-binding constraint.

one additional unit of steel will not generate any additional profit.

So, the willingness to pay should be zero.

(5)

Shadow price for manufacturing units = 1.943. So, one additional manufacturing unit will generate an additional profit of $1.943.

IF YOU HAVE ANY CLARIFICATION ASK ME IN THE COMMENT BOX.IF YOU SATISHFIED MY WORK GIVE ME THUMBS UP RATING

Add a comment
Know the answer?
Add Answer to:
On the tab labeled "Original Problem", I have provided a problem statement and the modeling of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Assignment 1. Linear Programming Case Study Your instructor will assign a linear programming project for this assignment...

    Assignment 1. Linear Programming Case Study Your instructor will assign a linear programming project for this assignment according to the following specifications. It will be a problem with at least three (3) constraints and at least two (2) decision variables. The problem will be bounded and feasible. It will also have a single optimum solution (in other words, it won’t have alternate optimal solutions). The problem will also include a component that involves sensitivity analysis and the use of the...

  • Sensitivity Analysis Question The manager of a small breakfast shop is determining how many sausage biscuits...

    Sensitivity Analysis Question The manager of a small breakfast shop is determining how many sausage biscuits and ham biscuits to prepare each morning for customers. Each type of biscuit requires a certain amount of labor time, sausage, ham, and flour. Below is the linear program that defines his problem where x1-# of sausage biscuits to make and x2:# of ham biscuits to make Max Profit-6x1+5x2 Constraints 0.01x1+0.024x2 6 (Labor in terms of hours) 0.1x1< 30 (Pounds of sausage available) 0.15x2<...

  • The sensitivity report is shown in Figure below SENSITIVITY REPORT FOR THE DIGITAL CONTROLS, INC., PROBLEM Variable Cel...

    The sensitivity report is shown in Figure below SENSITIVITY REPORT FOR THE DIGITAL CONTROLS, INC., PROBLEM Variable Cells Model Final Reduced Objective Allowable Allowable Name Variable Value Coefficient Increase Decrease Cost Models A Manufactured 1.750 IE+30 AM 00.000 0.000 10.000 3.000 Models B Manufactured 0.000 2.333 BM 60.000 6.000 1.750 AP BP Models A Purchased E+30 1.750 0.000 90.000 14.000 0.000 3.000 Models B Purchased 9.000 2.333 Constraints Final Shadow Constraint Allowable Allowable Price Constraint Number Name R.H. Side Value...

  • Problem 1 (10 pts): Construct a mathematical model (define your variables, write an objective function and...

    Problem 1 (10 pts): Construct a mathematical model (define your variables, write an objective function and constraints). Problem 2 (10 pts): Use Excel's Solver tool to determine the optimal solution that will maximize profit. Summarize your results. In the Solver toolbox, choose "Simplex LP". Problem 3 (10 pts): Discuss the effect on the optimal solution in Problem 2 if the profit on a small table increases to $12. In the Solver toolbox, rchoose "Simplex LP". If you Copy/Paste from Problem...

  • Brown Furniture Company makes three kinds of office furniture: chairs, desks, and tables. Each product requires...

    Brown Furniture Company makes three kinds of office furniture: chairs, desks, and tables. Each product requires skilled labor in the parts fabrication department, unskilled labor in the assembly department, machining on some key pieces of equipment, and some wood as raw material. At current prices, the unit profit contribution for each product is known, and the company can sell everything it manufactures. The size of the workforce has been established, so the number of skilled and unskilled labor hours is...

  • Performance Cooling Inc. manufactures air conditioners for home use and they currently have three models serving...

    Performance Cooling Inc. manufactures air conditioners for home use and they currently have three models serving this market: (1) the essential model, (2) the comfort model, and (3) the majestic model. The units sell for reasonable prices and bring in a profit of $63, $95, and $135 respectively. Currently, the resources required for production of each unit is given in the table below. Fans Cooling Coils Assembly Time (hr) 1 8 1 2 12 Essential Comfort Majestic In Stock/Available 1...

  • MSA Computer Corporation manufactures three models of computers: the Alpha4, Beta5, and the Delta6. The firm...

    MSA Computer Corporation manufactures three models of computers: the Alpha4, Beta5, and the Delta6. The firm employs thirteen technicians working 160 hours each per month on its assembly line. Management insists that no more than full employment on the assembly line (i.e., all 160 hours of time) can be maintained for each worker during next month’s operations, so there will be no overtime. It requires 20 labor hours to assemble each Alpha4 computer, 25 labor hours for each Beta5 model,...

  • Part 1: Goal Seek Pampa Parts produces a single product, the NF-9. The product has a...

    Part 1: Goal Seek Pampa Parts produces a single product, the NF-9. The product has a unit variable cost of $70 and annual fixed costs of $343,200. Pampa is subject to a 20 percent tax rate. Suppose the NF-0 sells for $110 per unit. Using the Goal Seek function in Microsoft Excel, how many units of NF-9 must Pampa sell to earn an annual operating profit after taxes of $38,400? Now, suppose Pampa expects to sell 8,150 units of NF-9...

  • Help!! - I need excel with formula shown 1) Sungram, an active lifestyle company, manufactures three models of novel fitness trackers called Jump (J), Run (R), and Walk (W). They have a limited supply...

    Help!! - I need excel with formula shown 1) Sungram, an active lifestyle company, manufactures three models of novel fitness trackers called Jump (J), Run (R), and Walk (W). They have a limited supply of common parts---wifi module (450 in inventory), cellular module (250 in inventory), heart rate monitor (800 in inventory), GPS module (450 in inventory), LCD screen (600 in inventory)---that these products use. A Jump model requires a wifi module, 2 heart rate monitors, a GPS module, and...

  • 2. In a Air Conditioning manufacturing problem, the firm is maximizing the profit by selling three...

    2. In a Air Conditioning manufacturing problem, the firm is maximizing the profit by selling three different products. Linear programming model for this problem will be as follows: Decision Variables: E := Number of economy models to be produced S := Number of standard models to be produced D := Number of deluxe models to be produced Linear Program: max 68E + 86S + 118D s.t. E + S + D ≤ 230 (Fan Motors) E + 2S + 4D...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT